LeBlanc v. Logan Hilton Joint Venture

463 Mass. 316
CourtMassachusetts Supreme Judicial Court
DecidedAugust 30, 2012
StatusPublished
Cited by27 cases

This text of 463 Mass. 316 (LeBlanc v. Logan Hilton Joint Venture) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LeBlanc v. Logan Hilton Joint Venture, 463 Mass. 316 (Mass. 2012).

Opinion

Gants, J.

On August 4, 2004, Roger M. LeBlanc (LeBlanc), an electrician employed by the Massachusetts Port Authority (Massport), was killed by electrocution while attempting to repair an electrical transformer at the Logan Airport Hilton Hotel (hotel) in Boston. Kelly A. LeBlanc (plaintiff), as administratrix of her husband’s estate, filed suit in the Superior Court against, among others, the owner of the hotel, the Logan Hilton Joint Venture (Hilton); the architect that designed the hotel, Cambridge Seven Associates, Inc. (Cambridge Seven); the consultant Cambridge Seven retained to provide electrical engineering services, Cosentini Associates-MA, LLP (Cosentini); and the construction subcontractor for electrical services, Broadway Electrical Co., Inc. (Broadway), alleging negligence, gross negligence, and breach of warranty. Hilton and Broadway filed cross claims against Cambridge Seven and Cosentini for indemnification and contribution. On October 12, 2007, a judge in the Superior Court granted the motion for summary judgment brought by Cambridge Seven and Cosentini as to the complaint and cross claims, and ordered the entry of separate and final judgment. The plaintiff, Hilton, and Broadway moved for reconsideration; their motions were denied on May 7, 2008. After separate and final judgment entered on August 21, 2008, Hilton and Broadway timely appealed from the grant of summary judgment as to their cross claims. The Appeals Court affirmed the grant of summary judgment as to Broadway’s cross claim for indemnification, but reversed as to the remainder of the cross claims and remanded to the Superior Court. LeBlanc v. Logan Hilton Joint Venture, 78 Mass. App. Ct. 699, 713 (2011) (LeBlanc). We granted Cambridge Seven’s and Cosentini’s [318]*318applications for farther appellate review.3 We affirm the judge’s grant of summary judgment on behalf of Cambridge Seven and Cosentini as to the cross claims brought by Hilton and Broadway for indemnification but reverse as to the cross claims for contribution.

Background. In reviewing the grant of a motion for summary judgment, we conduct a de novo examination of the evidence in the summary judgment record, see Miller v. Cotter, 448 Mass. 671, 676 (2007), and view the evidence in the light most favorable to the parties opposing summary judgment, here, Hilton and Broadway. See Augat, Inc. v. Liberty Mut. Ins. Co., 410 Mass. 117, 120 (1991). Therefore, we recite the facts in the light most favorable to Hilton and Broadway.

1. Facts, a. Agreement to provide architectural services. Hilton and Cambridge Seven executed an agreement in which Cambridge Seven was to provide architectural services to Hilton for construction of the hotel (agreement). Under the agreement, Cambridge Seven was to provide various professional services, including architecture, technical specification writing, coordination of consultants’ services, and electrical engineering. It was to prepare “Design Development Documents” for the hotel consisting of “drawings, specifications and other documents which fix and describe the expected final size and character of [the] Project,” including “electrical systems materials.” Among the “Design Development Documents” it was to deliver were a “[preliminary layout of switchgear, transformer and generator placement,” and “[ojutline [specifications.” Based on the “Design Development Documents,” it was to prepare final “Construction Documents,” including plans for the design of electrical systems and “[fjinal electrical specifications.”

Once the construction phase of the project began, Cambridge Seven was to “visit the site at intervals appropriate to the stage of construction to become familiar with the progress and quality of Work and to determine, in general, if Work is being performed in accordance with the Construction Documents.” The agreement specified that Cambridge Seven was not required “to make exhaustive or continuous on-site inspections to check [319]*319quality or quantity of Work.”4 Cambridge Seven was required to “[s]ubmit written reports to Hilton every two weeks recording [Cambridge Seven’s] observations at the construction Site as to the progress and quality of the Work.” In addition, the agreement stated: “In particular, [Cambridge Seven] shall promptly inform Hilton in writing of any deficiencies in Work and/or deviations from the requirements of the Construction Contract which come to [Cambridge Seven’s] attention.”

When the project was substantially completed, Cambridge Seven was to “prepare a punch list of all incomplete and/or unacceptable systems and/or construction items for all trades, which must be corrected prior to Final Completion.” It was then to “ascertain the satisfactory completion by [the general contractor] of all punch list items for purposes of Final Completion.”

Cambridge Seven was entitled to retain the professional consultants it deemed necessary to provide the services required under the agreement, but was responsible for their proper performance of services as if these services were performed by its own employees.

The agreement included the following provision, § 2.1.9, limiting Cambridge Seven’s responsibilities:

“Notwithstanding anything in this Agreement which may indicate otherwise, [Cambridge Seven] shall not be deemed to have control over or charge of and shall not be responsible for construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with Work being performed at Site. [Cambridge Seven] shall not be responsible for [the general contractor’s] schedules or [the general contractor’s] failure to carry out Work in accordance with the Construction Contract. [Cambridge Seven] shall not have control over or charge of acts or omissions of [the general contractor], its subcontractors, vendors or their respective agents or employees, or of any other persons performing portions of Work on behalf of [the general contractor], ...”

[320]*320The agreement also provided that Cambridge Seven would indemnify Hilton from and against all claims “arising out of and to the extent caused by the negligent acts, errors or omissions during the performance of professional services” under the agreement by it or its consultants provided that the claims did not “result from the negligent acts or omissions of the Indemnitees or other parties for whom [Cambridge Seven] is not responsible.”56

b. The switchgear. The Appeals Court ably described the electrical transmission equipment known in the industry as the “switchgear” at the hotel, and how the absence of instruction regarding its operation led to LeBlanc’s death:

“For commercial consumers of high voltage electricity, it provided surge protection, measurement of current, and, in the configuration employed at the hotel, it switched or converted the flow of electricity from one distribution source to an alternate distribution source in the event of a power outage. Two transformers served the hotel. They reduced high voltage to low voltage as the electricity entered the building. A transformer failure could cause an outage. If one distribution line became inoperable, the gear switched the incoming flow to another line so as to preserve delivery and measurement of the supply.
“At the hotel, ten cabinets housed the switchgear. From [321]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GARY SAWAYER v. TOWN OF BARNSTABLE & Another.
Massachusetts Appeals Court, 2025
Casey v. Papamechail
Massachusetts Land Court, 2021
Wolsfelt v. Gloucester Times
Massachusetts Appeals Court, 2020
Helfman v. Northeastern University
Massachusetts Supreme Judicial Court, 2020
Jenkins v. Bakst
130 N.E.3d 199 (Massachusetts Appeals Court, 2019)
McCrohan v. Sandulli Grace, P.C.
D. Massachusetts, 2019
McCrohan v. Sandulli Grace, P.C.
369 F. Supp. 3d 324 (District of Columbia, 2019)
Yee v. Massachusetts State Police
121 N.E.3d 155 (Massachusetts Supreme Judicial Court, 2019)
Paoluccio v. Wells Fargo, N.A.
D. Massachusetts, 2019
Van Sicklin v. Nantucket Surveyors, LLC
111 N.E.3d 1113 (Massachusetts Appeals Court, 2018)
Brettel v. Omron Scientific Techs., Inc.
302 F. Supp. 3d 460 (District of Columbia, 2018)
Hernandez v. City of Boston
277 F. Supp. 3d 176 (D. Massachusetts, 2017)
Tusino v. Zoning Board of Appeals of Douglas
56 N.E.3d 863 (Massachusetts Appeals Court, 2016)
Bowers v. P. Wile's, Inc.
54 N.E.3d 1089 (Massachusetts Supreme Judicial Court, 2016)