GARY SAWAYER v. TOWN OF BARNSTABLE & Another.

CourtMassachusetts Appeals Court
DecidedJune 24, 2025
Docket24-P-0861
StatusUnpublished

This text of GARY SAWAYER v. TOWN OF BARNSTABLE & Another. (GARY SAWAYER v. TOWN OF BARNSTABLE & Another.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GARY SAWAYER v. TOWN OF BARNSTABLE & Another., (Mass. Ct. App. 2025).

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

24-P-861

GARY SAWAYER

vs.

TOWN OF BARNSTABLE & another.1

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

In this negligence action, the plaintiff, Gary Sawayer,

claims that a public works project designed and constructed by

Comprehensive Environmental Inc. (CEI), and operated and

maintained by the Town of Barnstable (town), caused flooding

damage to his property. The defendants each moved for summary

judgment on the ground that Sawayer could not prove his claims

without expert testimony. A Superior Court judge allowed the

motions, and Sawayer appeals. We affirm.

Background. The following facts are undisputed. At all

relevant times, Sawayer owned a six-unit rental property located

1 Comprehensive Environmental Inc. on South Street in Barnstable. In or around 2007, the town

acquired abutting property on Pleasant Street as part of a

downtown improvement project intended "to provide connectivity

between the Hyannis Inner Harbor and the existing recreational,

commercial, and open space located directly on Hyannis Harbor by

way of a harbor walk extension." To create the extension, the

town demolished a residence on the Pleasant Street property and

regraded the area to level the site. Between 2008, when this

project was completed, and July 2017, Sawayer did not experience

any pattern of flooding on his property.

In 2014 the United States Environmental Protection Agency

(EPA) selected the Pleasant Street property as one of two Cape

Cod locations for construction of a stormwater best management

practice (BMP) project. The goal of the BMP project was to

"demonstrate the efficacy of an innovative subsurface gravel

wetland stormwater best management practice (BMP) retrofit for

the control of nitrogen and improve the water quality of the

Hyannis Inner Harbor." The system was designed to "store and

treat stormwater from up to a 0.3-inch rainfall event." During

a rainfall event, stormwater is collected in catch basins,

carried by a twenty-four-inch diameter clay pipe to a

bioretention area, and "eventually discharge[d] to Hyannis Inner

2 Harbor." The system is also equipped with a catch basin grate,

"which serves as an emergency overflow."

The EPA hired CEI, along with a second company that is not

a party to this case, to design and construct the BMP project.

Construction began in April 2015 and concluded in May 2015.

Landscaping and installation of monitoring equipment took place

in late 2015 through early 2016. The system was then "allowed

to settle for several months as the plants and vegetation took

root," after which it became operational.

On July 7, 2017, a large storm struck the town and "dropped

3.10 inches of rain" in eight hours, with "[t]he bulk of the

rain, i.e., 2.92 inches," falling between 1 P.M. and 4 P.M.

This "one-day storm . . . accounted for [seventy-nine percent]

of all rainfall in Hyannis for the month of July 2017." During

the storm, excess stormwater from South Street flooded Sawayer's

property, causing damage.

In May 2019 Sawayer filed this suit, asserting separate

negligence claims against the town and CEI. In count I against

the town, Sawayer claimed that the town knew or should have

known that the design of the BMP system would result in flooding

to his property, that the town negligently operated and

maintained the system, and that the town failed to take

appropriate action during the storm. In count II against CEI,

3 Sawayer claimed that CEI negligently engineered, designed,

constructed, and maintained the BMP system.

After the close of discovery, the town and CEI each moved

for summary judgment, arguing in part that Sawayer's failure to

designate an expert meant that he would be unable to meet his

burden of proof at trial. The judge allowed the motions on this

basis, and this appeal followed.

Discussion. Our review of a grant of summary judgment is

de novo. See Carroll v. Select Bd. of Norwell, 493 Mass. 178,

182 (2024). "Summary judgment is appropriate where there is no

material issue of fact in dispute and the moving party is

entitled to judgment as a matter of law" (citation omitted).

Id. Where, as here, the nonmoving party will have the burden of

proof at trial, the moving party can prevail on summary judgment

by showing that the nonmoving party "has no reasonable

expectation of proving an essential element of that party's

case" (citations omitted). Dulgarian v. Stone, 420 Mass. 843,

846 (1995). See Flesner v. Technical Communications Corp.,

410 Mass. 805, 809 (1991) (moving party's "burden need not be

met by affirmative evidence negating an essential element of the

plaintiff's case, but may be satisfied by demonstrating that

proof of that element is unlikely to be forthcoming at trial").

4 To prove a claim for negligence, a plaintiff must

establish, among other elements, that the defendant breached a

duty owed to the plaintiff and that "there is a greater

probability than not" that the breach caused the plaintiff's

injury. Enrich v. Windmere Corp., 416 Mass. 83, 87 (1993). See

Helfman v. Northeastern Univ., 485 Mass. 308, 315 (2020). If

the plaintiff's claim requires resolution of issues "beyond the

scope of an average person's knowledge," expert testimony is

required for the case to go to a jury. Esturban v.

Massachusetts Bay Transp. Auth., 68 Mass. App. Ct. 911, 911

(2007). See Goffredo v. Mercedes-Benz Truck Co., 402 Mass. 97,

103-104 (1988).

We agree with the judge that Sawayer has no reasonable

expectation of proving his claims at trial without expert

testimony. With respect to his claim against CEI, Sawayer would

have to show that CEI breached a standard of care in designing

and constructing the BMP system, an issue that is beyond the

understanding of ordinary jurors. See LeBlanc v. Logan Hilton

Joint Venture, 463 Mass. 316, 329 (2012) ("Expert testimony is

generally needed to establish [a] professional standard of

care"). In his amended complaint, Sawayer alleged that CEI did

not properly calculate the amount of stormwater that would run

through the BMP system and that the system had a number of

5 design defects, such as "an undersized bio-retention field," the

lack of "an automatic mechanism to redivert storm water not

adequately collected in the bio-retention area," and "stop logs"

that "required manual opening to release excess storm water from

the bio-retention field." These allegations raise highly

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Triangle Dress, Inc. v. Bay State Service, Inc.
252 N.E.2d 889 (Massachusetts Supreme Judicial Court, 1969)
Goffredo v. Mercedes-Benz Truck Co.
520 N.E.2d 1315 (Massachusetts Supreme Judicial Court, 1988)
Flesner v. Technical Communications Corp.
575 N.E.2d 1107 (Massachusetts Supreme Judicial Court, 1991)
Enrich v. Windmere Corp.
616 N.E.2d 1081 (Massachusetts Supreme Judicial Court, 1993)
Providence & Worcester Railroad v. Chevron U.S.A. Inc.
622 N.E.2d 262 (Massachusetts Supreme Judicial Court, 1993)
Dulgarian v. Stone
420 Mass. 843 (Massachusetts Supreme Judicial Court, 1995)
LeBlanc v. Logan Hilton Joint Venture
463 Mass. 316 (Massachusetts Supreme Judicial Court, 2012)
Atlas Tack Corp. v. Donabed
712 N.E.2d 617 (Massachusetts Appeals Court, 1999)
Estorban v. Massachusetts Bay Transportation Authority
68 Mass. App. Ct. 911 (Massachusetts Appeals Court, 2007)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
GARY SAWAYER v. TOWN OF BARNSTABLE & Another., Counsel Stack Legal Research, https://law.counselstack.com/opinion/gary-sawayer-v-town-of-barnstable-another-massappct-2025.