New England Building & Bridge Co., Inc. v. Town of Cohasset

CourtDistrict Court, D. Massachusetts
DecidedMay 21, 2024
Docket1:21-cv-11567
StatusUnknown

This text of New England Building & Bridge Co., Inc. v. Town of Cohasset (New England Building & Bridge Co., Inc. v. Town of Cohasset) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New England Building & Bridge Co., Inc. v. Town of Cohasset, (D. Mass. 2024).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MASSACHUSETTS __________________________________________ ) ) NEW ENGLAND BUILDING & BRIDGE, ) CO., INC., ) ) Plaintiff, ) ) v. ) ) TOWN OF COHASSET, ) ) Defendant/ ) Third-Party Plaintiff , ) ) Civil Action No. 21-cv-11567-DJC v. ) ) CDM SMITH, INC., ) ) Third-Party Defendant. ) ) __________________________________________)

MEMORANDUM AND ORDER

CASPER, J. May 21, 2024

I. Introduction Plaintiff New England Building & Bridge, Co., Inc. (“NEBB”) filed this lawsuit against Defendant Town of Cohasset (the “Town”) asserting state law claims arising out of work NEBB performed as a contractor on the Town’s dam rehabilitation project. D. 1. Shortly after the lawsuit commenced, the Town filed a third-party complaint against CDM Smith, Inc. (“CDM Smith”), the Town’s engineering firm, seeking contractual indemnification for any liability to NEBB arising out of CDM Smith’s negligence or reckless or intentional misconduct. D. 14. CDM Smith has moved for summary judgment as to the third-party complaint. D. 45. For the reasons stated below, the Court ALLOWS CDM Smith’s motion for summary judgment. II. Standard of Review The Court grants summary judgment where there is no genuine dispute as to any material fact and the undisputed facts demonstrate that the moving party is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(a). “A fact is material if it carries with it the potential to affect the outcome of the suit under applicable law.” Santiago–Ramos v. Centennial P.R. Wireless Corp.,

217 F.3d 46, 52 (1st Cir. 2000) (citation omitted). The movant “bears the burden of demonstrating the absence of a genuine issue of material fact.” Carmona v. Toledo, 215 F.3d 124, 132 (1st Cir. 2000); see Celotex Corp. v. Catrett, 477 U.S. 317, 322–23 (1986). If the movant meets its burden, the non-moving party may not rest on the allegations or denials in its pleadings, Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249 (1986), but must come forward with specific, admissible facts showing that there is a genuine issue for trial. See Borges ex rel. S.M.B.W. v. Serrano–Isern, 605 F.3d 1, 5 (1st Cir. 2010). The Court “view[s] the record in the light most favorable to the nonmovant, drawing reasonable inferences in his favor.” Noonan v. Staples, Inc., 556 F.3d 20, 25 (1st Cir. 2009). III. Factual Background The Court draws the following facts from the parties’ statements of undisputed facts,

responses to the same and accompanying exhibits, D. 46, D. 52, D. 58, D. 61. Unless otherwise noted, these facts are undisputed. On November 10, 2015, the Town and CDM Smith entered an engineering services contract (“Engineering Contract”). D. 61 ¶ 1. Under the Engineering Contract, CDM Smith performed design and construction administration services for the Town’s efforts to repair the Bound Brook Dam (the “Project”). Id. ¶¶ 1, 3. The Engineering Contract also contained an indemnification provision which provides that CDM Smith “shall assume the defense, indemnify and [h]old harmless the TOWN, the TOWN’s agents and employees, from and against all losses and all claims, demands, payments, suits, actions, recoveries and Judgements brought or recovered against them to the extent of the negligent acts, errors or omissions, reckless or intentional misconduct of [CDM Smith], its agent(s), officers, employees or subcontractors in the execution of the work or in guarding the same.” D. 46-2 at 4; D. 61 ¶ 9. In August 2016, the Town awarded a contract for the construction work to NEBB (the

“Construction Contract”). D. 61 ¶ 4 (citing D. 14 ¶ 5); see D. 1 ¶ 8. On September 23, 2021, NEBB sued the Town for breaching the Construction Contract and failing to pay NEBB for the work NEBB performed on the Project. D. 61 ¶ 5; see D. 1. On November 19, 2021, shortly after NEBB initiated its action against the Town, the Town impleaded CDM Smith as a third-party defendant. D. 61 ¶ 7; see D. 14. The Town seeks indemnification for any liability it owes “to NEBB on account of errors or omissions or intentional misconduct in CDM [Smith]’s performance of the [Engineering] Contract.” D. 14 ¶ 13. Although the Town’s complaint does not specify precise acts of negligence by CDM Smith, the Town references allegations in NEBB’s complaint “that certain elements of the Project design prepared by CDM [Smith] were deficient, that CDM

[Smith] nevertheless provided erroneous assurances that its design was adequate for the Project, and that on account of those deficiencies and CDM [Smith]’s assurances NEBB incurred additional costs to perform the work of the Project, for which it claims the Town is responsible.” D. 14 ¶ 8. NEBB’s complaint identified several challenges that negatively affected its performance of the Construction Contract. D. 1 ¶¶ 9–38. Of particular relevance here, NEBB alleged that the Construction Contract “required the design of a cofferdam, drainage bypass system, the dewatering of the area adjacent to the cofferdam and required installation of piping to maintain a minimum water flow of sixty cubic feet per second.”1 D. 1 ¶ 20. The Construction Contract specified the “use of a 30” diameter siphon pipe” to ensure adequate drainage and CDM Smith “assur[ed]” that a 30-inch pipe was adequate. D. 1 ¶¶ 21–22. NEBB alleged that “it quickly became apparent that the 30” pipe was grossly insufficient for the actual field conditions encountered” and that NEBB and the Town sought out an outside engineering firm, which concluded that “there was a problem

with the hydraulic calculations and modeling.” D. 1 ¶¶ 24–26. This issue, combined with other delays described in NEBB’s complaint, allegedly cost NEBB “lost months of work pumping out the additional and unanticipated water” and required the installation of new pumps for which NEBB has not been paid by the Town. D. 1 ¶¶ 27–28, 32–33. IV. Procedural History NEBB filed this lawsuit against the Town on September 23, 2021, D. 1, and the Town, in turn, impleaded CDM Smith, seeking indemnification for any liability to NEBB. D. 14. CDM Smith has moved for summary judgment as to the third-party complaint. D. 45.2 The Court heard the parties on the pending motion and took the matter under advisement. D. 63. V. Discussion The Town and CDM Smith agree that the language of the Engineering Contract requires

CDM Smith to indemnify the Town for liability “to the extent of the negligent acts, errors or omissions, reckless or intentional misconduct of [CDM Smith].” D. 61 ¶ 9. Both parties further agree that “the Town is not asserting reckless or intentional misconduct by CDM Smith.” D. 51

1 As alleged by NEBB, the cofferdam system is a “water diversion channel” that “would enable [NEBB] to work in the water during the restricted time of year period” imposed by the Massachusetts Department of Fisheries. D. 1 ¶¶ 7, 9. 2 CDM filed leave to file a reply brief, D. 56, and the Town moved to file a surreply brief, D. 59. The Court ALLOWS both motions nunc pro tunc and has considered those briefs, D. 57 and D. 60, in the resolution of CDM’s motion for summary judgment. at 4 n.3; see D. 47 at 3 n.1. Thus, to obtain indemnification, the Town must show that NEBB’s claims stem from CDM Smith’s “negligent acts, error or omissions.” D. 47 at 3. A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Borges Ex Rel. SMBW v. Serrano-Isern
605 F.3d 1 (First Circuit, 2010)
Bank v. International Business MacHines Corp.
145 F.3d 420 (First Circuit, 1998)
Carmona v. Toledo
215 F.3d 124 (First Circuit, 2000)
Santiago-Ramos v. Centennial P.R. Wireless Corp.
217 F.3d 46 (First Circuit, 2000)
Jakobiec v. Merrill Lynch Life Insurance
711 F.3d 217 (First Circuit, 2013)
Parent v. Stone & Webster Engineering Corp.
556 N.E.2d 1009 (Massachusetts Supreme Judicial Court, 1990)
Kelly v. DIMEO, INC. WATERPROOFING CO.
581 N.E.2d 1316 (Massachusetts Appeals Court, 1991)
Golden v. Amory
109 N.E.2d 131 (Massachusetts Supreme Judicial Court, 1952)
Aponte-Bermudez v. Colon
944 F.3d 963 (First Circuit, 2019)
Pongonis v. Saab
486 N.E.2d 28 (Massachusetts Supreme Judicial Court, 1985)
Jupin v. Kask
447 Mass. 141 (Massachusetts Supreme Judicial Court, 2006)
LeBlanc v. Logan Hilton Joint Venture
463 Mass. 316 (Massachusetts Supreme Judicial Court, 2012)
Herson v. New Boston Garden Corp.
667 N.E.2d 907 (Massachusetts Appeals Court, 1996)
Atlas Tack Corp. v. Donabed
712 N.E.2d 617 (Massachusetts Appeals Court, 1999)
Hayes v. CRGE Foxborough, LLC
167 F. Supp. 3d 229 (D. Massachusetts, 2016)
Noonan v. Staples, Inc.
556 F.3d 20 (First Circuit, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
New England Building & Bridge Co., Inc. v. Town of Cohasset, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-england-building-bridge-co-inc-v-town-of-cohasset-mad-2024.