New England Building & Bridge Co., Inc. v. Town of Cohasset

District Court, D. Massachusetts·Decided December 19, 2024·No. 1:21-cv-11567·Unknown

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MASSACHUSETTS __________________________________________ ) ) NEW ENGLAND BUILDING & BRIDGE, ) CO., INC., ) ) Plaintiff, ) ) v. ) ) TOWN OF COHASSET, ) ) Defendant/ ) Third-Party Plaintiff , ) ) Civil Action No. 21-cv-11567-DJC v. ) ) CDM SMITH, INC., ) ) Third-Party Defendant. ) ) __________________________________________)

MEMORANDUM OF DECISION

CASPER, J. December 19, 2024

I. INTRODUCTION Plaintiff New England Building & Bridge, Co., Inc. (“NEBB”) filed this lawsuit against Defendant Town of Cohasset (the “Town”) asserting state law claims arising out of work NEBB performed as a contractor on the Town’s dam rehabilitation project. The Town and NEBB have since settled. D. 70. What then remained was the third-party action between the Town and CDM Smith, Inc. (“CDM Smith”), the Town’s engineering firm. After entering summary judgment on the Town’s claims against CDM Smith for contractual indemnification, D. 64, only CDM Smith’s 1 counterclaims, Count I (breach of contract) and Count II (unjust enrichment), against the Town remained for a bench trial. D. 22 at 6-8. Perhaps because its attention previously was focused on litigation (and then settlement) with NEBB, the Town raised two legal challenges to both counterclaims on the eve of the bench trial. D. 93; D. 94 at 2-15. After hearing counsel’s arguments about this matter at the Final Pretrial Conference, the Court allowed the parties to file

proposed findings of facts and conclusions of law, particularly focused on this issue, D. 104, and postponed the first day of trial to hear further argument from counsel. D. 112. After hearing those additional arguments and expressing concerns about the need for trial where the challenges to the breach of contract and unjust enrichment claims raised by the Town were matters of law for which no further factual development was required, the Court gave CDM Smith an opportunity for additional briefing on the matter (and the Town the opportunity to respond). Id. After having considered that further briefing, D. 115; D. 118, and having had heard the parties on this matter, the Court concludes that there remains no disputed factual issues for trial on either the breach of contract claim or the unjust enrichment claim. Accordingly, the Court now issues its findings of

facts and conclusions of law on the aforementioned claims and shall enter judgment for the Town on these claims. II. PROCEDURAL HISTORY NEBB filed this lawsuit against the Town on September 23, 2021, D. 1, and the Town, in turn, impleaded CDM Smith, seeking indemnification for any liability to NEBB. D. 14. CDM Smith filed a counterclaim against the Town and a crossclaim against NEBB. D. 22. After CDM Smith moved for summary judgment on the Town’s claims seeking contractual indemnification against them, the Court allowed the motion. D. 64. Following summary judgment, NEBB and the 2 Town entered into a settlement resolving all claims between the two parties, D. 70, and CDM Smith dismissed its crossclaim against NEBB. D. 77. Accordingly, only CDM Smith’s counterclaims, Count I (breach of contract) and Count II (unjust enrichment), against the Town remain for the Court. III. FINDINGS OF FACT

The Court has already recited the undisputed facts in this matter in its Memorandum and Order allowing CDM Smith’s motion for summary judgment, D. 64, and incorporates those facts by reference here. The Court makes the following findings of fact (which also are not disputed) as to its ruling on Count I and Count II of CDM Smith’s counterclaims below. A. Contract Between CDM Smith and the Town 1. On or about November 10, 2015, the Town and CDM Smith entered into a “Contract for Services” providing that CDM Smith would provide “Design, Permitting and Construction Services for the Bound Brook Dam Repairs Project” (hereinafter “Project”) between November 10, 2015 and December 31, 2016” (the “Contract”). D. 107 ¶ 1; D. 109 ¶ 9. 2. The Contract stated a not-to-exceed contract price of $246,395. D. 107 ¶ 1; D. 109 ¶ 11. 3. In relevant part, the Contract provided that the “TOWN shall pay to [CDM Smith] the sum

set forth any invoice (sic) which has been approved by the Town Manager or his/her authorized designee.” D. 109 ¶ 14. 4. As to any amendments, the Contract provided that: “[t]he provisions contained in this contract may be modified only by the express written consent of the parties. Any amendments must be made only by written amendment executed by all signatories to the original agreement, prior to the effective date of the amendment.” Id. ¶ 17. 3 5. The Contract also includes an integration clause: “[t]his contract constitutes the entire Agreement of the parties hereto with respect to the subject matter hereto, and no representations, inducements, promises or agreements, oral or otherwise, between the parties hereto with respect to the subject matter hereof not embodied herein shall be of any force or effect.” Id. ¶ 18.

B. Contract with NEBB and CDM Smith’s Work on the Project 6. On July 22, 2016, the Town and NEBB entered into a construction contract for the Project. D. 107 ¶ 5; D. 109 ¶ 23. 7. Despite having contracted with NEBB for the Project to be completed by May 31, 2017, the Town did not extend the Contract with CDM Smith correspondingly. D. 107 ¶ 6. 8. As contemplated by the Town-NEBB Contract, NEBB’s work on the Project continued beyond the December 31, 2016 end date of the Contract. See id. ¶ 9. 9. In general, the Project encompassed replacement of a culvert at the bridge on Beechwood Street spanning Bound Brook and associated work. D. 109 ¶ 24. 10. The design for the Project included a system of dewatering and drainage control, including

a bypass pipe, that would divert water so as to allow for a dry work area both upstream and downstream from the bridge and culvert structures. Id. ¶ 25. 11. In late 2016 and early 2017, the Project encountered various problems, the causes of which were vigorously debated between and among the Town, CDM Smith, and NEBB. D. 107 ¶ 10; see D. 109 ¶¶ 32-36. 12. Prior to December 31, 2016, the Town and CDM Smith began to negotiate a formal written amendment to their contract that would serve to (a) extend the duration of the Town-CDM 4 Smith Contract, and (b) confirm CDM Smith’s compensation for the past and future out- of- scope services requested by the Town. D. 107 ¶ 8. C. Amendments to the Contract between the Town and CDM Smith 13. At the end of May 2017, CDM Smith and the Town engaged in a mediation regarding CDM Smith’s request for payment of unpaid invoices and additional compensation for the

Project. D. 109 ¶ 49. 14. Following the mediation, the Town and CDM Smith signed Amendment No. 1 to the Contract. D. 109 ¶ 50; see D. 107 ¶ 14. 15. “Amendment No. 1” to the Contract, dated June 2, 2017, provided as follows: a. The Agreement expiration date in Article II shall be extended from December 31, 2016 to September 30, 2017. If additional time is needed to complete construction, the TOWN and CONTRACTOR agree to negotiate an appropriate extension. b. The Town shall pay outstanding [CDM Smith] invoices #1, #2, #3 for (Resident Engineer (“RE”) Services) for the base contract, totaling $64,852.88 (see attached breakdown) by June 9, 2017.

Free access — add to your briefcase to read the full text and ask questions with AI

New England Building & Bridge Co., Inc. v. Town of Cohasset, (D. Mass. 2024).

New England Building & Bridge Co., Inc. v. Town of Cohasset (New England Building & Bridge Co., Inc. v. Town of Cohasset) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Smart v. Gillette Co. Long-Term Disability Plan
70 F.3d 173 (First Circuit, 1995)
Den Norske Bank As v. First Nat'L of Bost
75 F.3d 49 (First Circuit, 1996)
INTERNATIONAL SALT CO., LLC v. City of Boston
590 F.3d 1 (First Circuit, 2009)
INTERNATIONAL SALT CO., LLC v. City of Boston
547 F. Supp. 2d 62 (D. Massachusetts, 2008)
Adalian Bros. v. City of Boston
84 N.E.2d 35 (Massachusetts Supreme Judicial Court, 1949)
MCI WorldCom Communications, Inc. v. Department of Telecommunications & Energy
442 Mass. 103 (Massachusetts Supreme Judicial Court, 2004)
Bank v. Thermo Elemental Inc.
451 Mass. 638 (Massachusetts Supreme Judicial Court, 2008)
Baltazar Contractors, Inc. v. Town of Lunenburg
843 N.E.2d 674 (Massachusetts Appeals Court, 2006)
Sawyer v. United States
76 F. Supp. 3d 353 (D. Massachusetts, 2015)
Infinity Fluids Corp. v. General Dynamics Land Systems, Inc.
210 F. Supp. 3d 294 (D. Massachusetts, 2016)
BIPING HUANG & another v. RE/MAX LEADING EDGE & others.
190 N.E.3d 518 (Massachusetts Appeals Court, 2022)