D. Federico Co. v. New Bedford Redevelopment Authority (In Re D. Federico Co.)

8 B.R. 888, 1981 Bankr. LEXIS 4986
CourtUnited States Bankruptcy Court, D. Massachusetts
DecidedFebruary 3, 1981
Docket19-40435
StatusPublished
Cited by10 cases

This text of 8 B.R. 888 (D. Federico Co. v. New Bedford Redevelopment Authority (In Re D. Federico Co.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D. Federico Co. v. New Bedford Redevelopment Authority (In Re D. Federico Co.), 8 B.R. 888, 1981 Bankr. LEXIS 4986 (Mass. 1981).

Opinion

MEMORANDUM ON PROSPECTIVE LIABILITY

HAROLD LAVIEN, Bankruptcy Judge.

PROCEDURAL POSTURE

These cases are presently before the Court by virtue of an Order of Removal issued by this Court on October 1, 1980. The Plaintiff, D. Federico Co., Inc., an Order for Relief having been issued on September 18, 1980, is seeking monies due on account of construction work performed by the Debtor on three public contracts. Since there was no chance of an expedient resolution in State Court, this Court removed the actions from the Norfolk Superior Court pursuant to 28 U.S.C. §§ 1471 and 1478 and the Court’s mandate of expedient administration of debtors’ estates. Katchen v. Landy, 382 U.S. 323, 86 S.Ct. 467, 15 L.Ed.2d 391 (1966).

The Plaintiff in this case, a general contractor, was awarded five public contracts by the Defendant, New Bedford Redevelopment Authority (hereinafter Authority) involving the construction of storm drainage, sanitary sewers, water mains, curbs, sidewalks, new pavement, pavement resurfacing and other related work. Three of those contracts are presently before the Court. The three are: South Terminal Urban Renewal Project (hereinafter South Terminal project), North Terminal Urban Renewal Project (hereinafter North Terminal project) and West End Urban Renewal Project (hereinafter West End project).

Plaintiff’s complaint is comprised of five counts, as follows: Count I is a claim for extra fittings and adapters used in the installation of underground piping as a result of unanticipated underground obstructions due to the inaccurate depiction of such obstructions on the drawings of the Authority. This count is based on breach of contract, as plaintiff alleges that the Authority authorized the use of the extra fittings but has not paid Plaintiff as per the alleged authorization. Counts II and III seek damages for the extra fittings and adapters as in Count I but based on a contract implied in fact (Count II) and a contract implied in law, quantum meruit (Count III). Count IV is a claim for final measurements, final payments, interest as permitted under M.G.L. Ch. 30 § 39G and the release of retainages held by the Authority. Count IV of the West End complaint is for damages for a scribner’s error in that contract for the bid price of some stone curbing. Counts V and VI of the West End correspond to Counts IV and V of the other two cases. Count V seeks damages for fittings and adapters as in Count I, but is based on a breach of warranty of accurate disclosure because of the failure of the Authority’s drawings to depict the proper location of underground obstructions with the Authority knowing that Plaintiff would rely on the drawings in determining its bid and also knowing that it was impossible for Plaintiff to confirm the exact location of the existing utilities.

The Authority denies the allegations of each count of Federico’s complaint and alleges twelve defenses to the complaint. These defenses in general state that plaintiff failed to conform to the requirements of the written contract between the parties which required written notice and authority for any changes in work, as well as written requests for extra costs, and that the contract entered into between the parties was an express contract which limited Plaintiff to the remedies allowed under the terms of *891 the contract. Defendant denies the existence of a contract implied in law or fact. Defendant also counterclaims against the Plaintiff, claiming liquidated damages for delays in completion of the various projects.

Prior to trial, the Court ruled on Defendant’s Motion for Summary Judgment. The requested motion was denied with respect to all of the technical counts of Plaintiff’s complaint, except for the limited issue of whether the Defendant’s chief engineer and its on-site engineer had any type of authority to orally alter the terms of the contracts. The Court ruled in favor of Defendant’s motion on this limited issue. However, since the factual issues involved in that one issue are similar to other issues involved in Plaintiff’s complaint, I allowed evidence on whether defendant's engineers had authority to vary the terms of the contract.

THE FACTS

The Plaintiff learned of the open bidding on the Site Improvements from an advertisement in trade journals in January, 1973. Upon learning of the bids, Plaintiff requested, and did receive from the Authority, contract specifications and drawings for each project. The plans and specifications for the South and North Terminal projects were prepared by Goodkind & O’Dea, an independent engineering company; and, for the West End project, by Meridian Engineering Company, also an independent firm. Although the drawings for each contract indicated locations of proposed new construction and locations of existing improvements, such as electrical distribution, telephone distribution, sanitary and storm drainage, water distribution, roadway and curbing, the Instructions to Bidders, which were sent out with each set of plans contained a clause which warned prospective bidders to visit the sites to become acquainted with on-site conditions. 1 In addition, the Technical Specifications for Cast Iron Water Mains and Appurtanances provided in part, that “the location of existing underground utilities and structures as shown on the Drawings is approximate only and is shown only for the convenience of the contractor who must verify the information to his own satisfaction.” In preparing the plans, both engineering firms performed topographical surveys, and inspected maps and drawings of private and public agencies including records of installation of utilities. In addition, the engineers submitted the plans to the utility companies and the water and sewer departments of the City of New Bedford to have the locations of existing utilities verified. In short, I find as fact that the design engineers prepared the drawings from the best information available and did everything feasible to accurately depict existing utilities. Neither the design engineers, the bidders, nor the Authority could do anything more to ascertain the obstructions without the actual excavation. All parties were aware of these limitations on the drawings. Bidders were told that they could only rely on the approximate locations of the existing underground utilities as depicted in the drawings at their own peril, and the Authority did all it could be expected to do to bring that fact home to all bidders.

The plans for each contract depicted the location for the placing of new pipe and the bidder could judge the approximate number and type of fittings by matching the pipe to the obstructions. Fittings are connections between pipes including elbows, bends, crosses or reducers which enable the pipe to change directions. The bid for each contract was by numerous line items for which the Plaintiff would prepare a unit price. There was no separate line item for fittings and adapters. The bid for line items for piping was intended to include any necessary fittings. The Plaintiff would determine the overall bid price for piping by doing a “take-off” from the plans.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
8 B.R. 888, 1981 Bankr. LEXIS 4986, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-federico-co-v-new-bedford-redevelopment-authority-in-re-d-federico-mab-1981.