D. Federico Co., Inc. v. Commonwealth

415 N.E.2d 855, 11 Mass. App. Ct. 248, 1981 Mass. App. LEXIS 897
CourtMassachusetts Appeals Court
DecidedJanuary 28, 1981
StatusPublished
Cited by18 cases

This text of 415 N.E.2d 855 (D. Federico Co., Inc. v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D. Federico Co., Inc. v. Commonwealth, 415 N.E.2d 855, 11 Mass. App. Ct. 248, 1981 Mass. App. LEXIS 897 (Mass. Ct. App. 1981).

Opinion

Armstrong, J.

The plaintiff, a construction contractor, brought this action to recover additional compensation which it claims to be owed for its work in the development of a campsite at Wompatuck State Park in Hingham. From *249 a judgment, entered on a master’s report, dismissing the complaint, the plaintiff appeals.

The master’s findings are not in dispute; and our function on appeal, like that of the judge who ordered the entry of judgment, is to determine what disposition of the case is legally required by the master’s findings. 1 Central Tow Co. v. Boston, 371 Mass. 341, 342 n.3 (1976).

The dispute arose because of a substantial underestimation by the Commonwealth’s designer, a private engineering firm, of the amount of excavation and replacement fill (“ordinary borrow”) that would be required to lay a proper base for the roads to be constructed within the campsite. No test borings or soil analyses were done for the purposes of accurate estimation; 2 the designer instead based his estimate on an assumption that, because roads had been constructed previously without difficulty in the same vicinity (the campsite had been used earlier as a naval ammunition depot), it would not be necessary to excavate beyond an average depth of twelve inches. In fact excavation revealed substantial amounts of unsuitable organic material and nested boulders, all of which had to be removed; and instead of excavating 85,650 cubic yards of material, the amount the designer had estimated, the plaintiff was required to excavate 215,492 cubic yards of material. The amount of ordinary borrow required to be brought in from other locations amounted to 278,493 cubic yards, rather than the 30,150 cubic yards which had been estimated by the designer.

The excavation and borrow items were bid on the basis of unit prices. The plaintiff had bid $1.60 per cubic yard for excavation and $ .90 per cubic yard for borrow. Multiply *250 ing these figures by the applicable estimates, the plaintiff had included as components of its total bid for the entire project ($2,113,597.20) $137,040.00 for excavation and $21,135.00 for borrow, a total of $158,175.00 for the two. In fact, because the work in those two categories so greatly exceeded that which had been estimated, the plaintiff has been paid a total, on the basis of unit prices, of $595,430.90 for the excavation and borrow items combined.

The master, however, found that that sum did not adequately compensate the plaintiff for the work it did in excavating and filling with borrow, and that fair compensation to the plaintiff for its work in those categories would have been $913,522.40. 3 The plaintiff advances two theories why it is entitled to the difference of $318,091.50.

The first is based on a finding that “[t]he earth moving operation was an entirely different type of job in scope and magnitude from the one that Federico offered to perform in its sealed proposal.” This finding, the plaintiff argues, brings the case within the authority of Long v. Athol, 196 Mass. 497 (1907), where the plaintiff was permitted to rescind a sewer-laying contract when it became apparent that the excavation estimates which had been the basis of the bidding were, due to a calculation error by the town’s engineer, materially erroneous. The “mistake” here is of a different type: a guess or assumption made from insufficient factual data, rather than an erroneous interpretation of known data. Nothing in the master’s report suggests that the flimsy basis for the engineer’s estimates was not available to bidders for the asking (contrast, in this respect, Alpert v. Commonwealth, 357 Mass. 306 [1970]); but all parties apparently proceeded content to rely on the estimates rather than go to the trouble of making test borings. The contract made clear that the excavation unit *251 price was to control regardless of actual quantities and covered peat-removal, boulder-removal, and ledge-blasting; it also made clear that the estimates shown for unit-price items were for purposes of bid-comparison only and were not guaranteed. It cannot be said, therefore, that the estimates were the very basis of the contract, such as to amount to a material mistake of fact which would have permitted unilateral rescission; and, in any event, the plaintiff did not purport promptly to rescind, as in the Long case, but instead continued to work under and in accordance with the terms of the contract until the work was completed. In these circumstances the Long case has no particular bearing.

The second theory is that the Commonwealth impliedly warranted the accuracy, not to the precise yard but as fair approximations (compare Muir Bros. v. Sawyer Constr. Co., 328 Mass. 413, [1952]), of its estimates, and that the plaintiff is entitled to damages for breach of that warranty. The provisions of the contract, however, explicitly preclude such a warranty: the provision mentioned earlier, to the effect that the estimates were furnished for bid-comparison purposes only, goes on to state that “[estimated quantities shown for unit price items . . . are not guaranteed”; another provision requires the bidders to declare “that in regard to the conditions affecting the work to be done and the labor and materials needed, this proposal is based solely on their own investigation and research and not in reliance upon any plans, surveys, measurements, dimensions, calculations, estimates, borings or representations of any employee, officer or agent of the Commonwealth.” The master dismissed the latter provision as “inconsistent with the express approximations” (i.e., the estimates in question) furnished by the Commonwealth “for bidding purposes,” and found that it was “impossible” for bidders, who had three weeks to prepare their bids, to do independent test borings; but that misses the point that the object of such a provision, one to which the plaintiff assented by bidding ' and contracting, was to preclude a warranty of the ac *252 curacy of estimates and to place on the bidder the risk that subsoil conditions might be more adverse than the parties had hoped. Our cases have recognized the possibility of an implied warranty of estimates in some circumstances (see, e.g., M.L. Shalloo, Inc. v. Ricciardi & Sons Constr., Inc., 348 Mass. 682, 686-688 [1965]; Alpert v. Commonwealth, 357 Mass. 306, 321 [1970]), but not where the contract terms specifically precluded warranty of, or reliance on, the furnished estimates. See, e.g., Benjamin Foster Co. v. Commonwealth, 318 Mass. 190, 201-202 (1945); Daniel O’Connell’s Sons v. Commonwealth, 349 Mass. 642, 647 (1965). There was no suggestion in the master’s findings that the Commonwealth concealed the existence of borings reports or soil analyses which would have revealed the subsoil conditions or shown the unreliability of the estimates, as was the fact in the Alpert case, 357 Mass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coghlin Electrical Contractors, Inc. v. Gilbane Building Co.
472 Mass. 549 (Massachusetts Supreme Judicial Court, 2015)
AECOM Technical Services Inc. v. Mallinckrodt LLC
117 F. Supp. 3d 98 (D. Massachusetts, 2015)
Trans-Spec Truck Service, Inc. v. Caterpillar Inc.
524 F.3d 315 (First Circuit, 2008)
Earth Tech Environment & Infrastructure, Inc. v. Perini/Kiewit/Cashman
18 Mass. L. Rptr. 305 (Massachusetts Superior Court, 2004)
Nota Construction Corp. v. Keyes Associates, Inc.
694 N.E.2d 401 (Massachusetts Appeals Court, 1998)
Sutton Corp. v. Metropolitan District Commission
667 N.E.2d 838 (Massachusetts Supreme Judicial Court, 1996)
J. F. White Contracting Co. v. Massachusetts Bay Transportation Authority
666 N.E.2d 518 (Massachusetts Appeals Court, 1996)
Sutton Corp. v. Metropolitan District Commission
652 N.E.2d 627 (Massachusetts Appeals Court, 1995)
J.F. White Contracting Co. v. Massachusetts Bay Transportation Authority
4 Mass. L. Rptr. 37 (Massachusetts Superior Court, 1995)
Goudreau Corp. v. City of Springfield
1 Mass. L. Rptr. 547 (Massachusetts Superior Court, 1994)
Glynn v. City of Gloucester
487 N.E.2d 230 (Massachusetts Appeals Court, 1986)
Lawrence-Lynch Corp. v. Department of Environmental Management
467 N.E.2d 838 (Massachusetts Supreme Judicial Court, 1984)
A. Amorello & Sons, Inc. v. Beacon Construction Co.
422 N.E.2d 467 (Massachusetts Appeals Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
415 N.E.2d 855, 11 Mass. App. Ct. 248, 1981 Mass. App. LEXIS 897, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-federico-co-inc-v-commonwealth-massappct-1981.