Earth Tech Environment & Infrastructure, Inc. v. Perini/Kiewit/Cashman

18 Mass. L. Rptr. 305
CourtMassachusetts Superior Court
DecidedSeptember 23, 2004
DocketNo. 030566BLS
StatusPublished

This text of 18 Mass. L. Rptr. 305 (Earth Tech Environment & Infrastructure, Inc. v. Perini/Kiewit/Cashman) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Earth Tech Environment & Infrastructure, Inc. v. Perini/Kiewit/Cashman, 18 Mass. L. Rptr. 305 (Mass. Ct. App. 2004).

Opinion

van Gestel, J.

This matter is before the Court on the motion by the defendants Perini/Kiewit/Cashman, a Joint Venture (“PKC”), and Fidelity and Deposit Company of Maryland (“Fidelity”), seeking summary judgment pursuant to Mass.R.Civ.P. Rule 56. The case is a construction contract dispute involving the Cl 1A1 portion of the Central Artery/Tunnel Project (“CA/T’) in Boston (the “Project”), which is a public construction project.

It should be noted at the outset that the issues raised in the summary judgment motion relate solely to certain contractual notice requirements and a statutory commencement of suit limitation. Otherwise, the merits of any claims are not in issue here.

BACKGROUND

The following facts are not in dispute.

Contract Cl 1A1 includes the construction of interstate Highway 1-93 northbound from Kneeland Street to Congress Street, in Boston. Among other things, what is involved is the excavation for the construction of approximately 2,000 feet of highway tunnel under Atlantic Avenue, along with the reconstruction of the MBTA Red Line South Station Subway Station and the construction of a portion of the new MBTA “Silver Line.”

The sites to be excavated pass through a number of areas that the CA/T had previously determined to be contaminated. These areas were delineated on the contract drawings and in the specifications as “Clearance Areas” (where contamination had been confirmed) and “Potential Clearance Areas” (where contamination was suspected). The specifications required the contractor — here PKC — to conduct an “insitu sampling program” in these areas. The purpose of the in-situ sampling program was “to further characterize the Potential Clearance Material as either clearance or non-clearance material.” Based on the results of the testing program, the CA/T then determined the “(flinal delineation of the boundary between the Clearance Material or Non-Clearance Material.”

Once the Clearance Areas were set by the CA/T, all of the materials within the Clearance Areas had to be excavated in accordance with the “Contaminated Soil Excavation” specification section, which prescribed a number of excavation restrictions. The material from the Clearance Areas also had to be “disposed of... at a Non-RCRA Out-of-State Lined Landfill (or recycled at a recycling facility if materials are suitable and the Contractor can identify a facility to accept the material),” all in accordance with the ‘Transportation and [360]*360Disposal of Contaminated Material” specification section.

The material to be disposed of was broadly defined to include “soil, pavement, cobblestones, ballast, railroad ties, rocks, concrete pipes, and miscellaneous structures and debris.”

PKC entered into a subcontract with the plaintiff, Earth Tech Environment and Infrastructure, Inc. (“Earth Tech”) in March 1995. The subcontract work included the in-situ testing and the transportation and disposal of PAH/TPH contaminated soil.

Earth Tech, not PKC, performed the in-situ testing in the summer of 1995, and thereafter the CA/T set the final boundaries of the Clearance Area based on that testing. Earth Tech alleges in this case that this 1995 in-situ testing “establish(ed) the presence of contaminated clay at numerous levels and locations not shown on the original borings,” and contends that this constituted a differing site condition. Earth Tech, however, did not notify PKC of these alleged differing site conditions when discovered or at any time over the next four years.

Earth Tech began its transportation and disposal work in December 1995 and periodically performed that work into July of 1999. Earth Tech further alleges that on June 16, 1999, it encountered contaminated clay material in Clearance Area E. This material is said to have been rejected by Earth Tech’s soil recycling facility as containing too much clay to be recycled. Nevertheless, Earth Tech was ordered to remove the clay. From June 18 through July 15,1999, Earth Tech claims that it transported and disposed of the clay material from Clearance Area E to a landfill area at a much higher cost than non-clay material, and it seeks to recover the alleged extra cost in this lawsuit.

On July 29, 1999, Earth Tech, for the first time, notified PKC in writing of a claim for an equitable adjustment for the clay materials. In a letter dated September 17, 1999, Earth Tech stated that it considered “the presence of unforeseen contaminated clay material” to be a differing site condition pursuant to Sec. 4.04 of certain of the contract documents. In a December 30, 1999 letter, Earth Tech asserted that “the original borings... are not indicative of the actual conditions on the site with regard to the level/quantity of clay and the presence of contamination within the clay.”

In September 2000, Earth Tech submitted a more detailed “Claim for Differing Site Conditions” for the transportation and disposal of the contaminated clay from Area E of the Project. It further revised this claim submission in October 2000 and January 2001. Earth Tech asserted that “[i]n short, the contaminated clay is a differing site condition for which Earth Tech is entitled to an equitable adjustment under General Laws c. 30, Sec. 39N, as incorporated into Section 4.04, Division 1 of the Construction Contract.”

In February 2003, Earth Tech filed this lawsuit against PKC and Fidelity. It alleges that in 1997, and again in 1999, it was required to transport and dispose of certain contaminated clay materials which “had not been identified in the subcontract documents” and “could not have been foreseen by Earth Tech.”

In a deposition of an Earth Tech Rule 30(b)(6) deponent, Earth Tech stated that its claim is that its work was supposed to include transportation and disposal of only certain types of soils from the Clearance Areas. It contends that its work was limited to soil types A (brick, concrete, and granular historic fill), B (non-granular historic fill and other non-granular materials), and C (interface clay). It claims that type D soils (clay and till) are excluded from the scope of the subcontract.

The Rule 30(b)(6) witness further said that, unlike Earth Tech’s earlier differing-site-condition claim, its current claim is not based on any inaccuracies in the original boring logs.

Two different sections of Division 1 of the General Requirements and Covenants provide notice requirements, depending upon whether Earth Tech is pressing a differing-site-condition claim or some other form of equitable adjustment for a change. They are Sections 4.03 and 4.04.

Section 4.03 is entitled “Change Orders,” and reads in pertinent part as follow.

B. If the Contractor believes that any order from the Department should be treated as a Change Order, the Contractor shall notify the Engineer in writing, within three (3) Workdays after receipt of such order, identifying the order and stating with particularity the basis for regarding it as a Change Order.
E. If the Contractor intends to assert a claim for an equitable adjustment covering a change in the Work under this Subsection, Contractor must, within ten (10) Days after receipt of a written Change Order under Paragraph A above, or furnishing of a notice under Paragraph B above, submit to the Engineer a written statement concerning the claim with supporting documentation setting forth the nature and impact of the claim on the Contract Price, Contract Milestone(s), or Contract Time(s).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glynn v. City of Gloucester
487 N.E.2d 230 (Massachusetts Appeals Court, 1986)
General Electric Co. v. Lexington Contracting Corp.
292 N.E.2d 874 (Massachusetts Supreme Judicial Court, 1973)
D. Federico Co., Inc. v. Commonwealth
415 N.E.2d 855 (Massachusetts Appeals Court, 1981)
Glynn v. City of Gloucester
401 N.E.2d 886 (Massachusetts Appeals Court, 1980)
Kesler v. Pritchard
284 N.E.2d 602 (Massachusetts Supreme Judicial Court, 1972)
Marinucci Bros. v. Commonwealth
235 N.E.2d 783 (Massachusetts Supreme Judicial Court, 1968)
M.P.M. Builders, LLC v. Dwyer
809 N.E.2d 1053 (Massachusetts Supreme Judicial Court, 2004)
D & P Equipment Corp. v. Harvey Construction Co.
363 N.E.2d 1369 (Massachusetts Appeals Court, 1977)
Sutton Corp. v. Metropolitan District Commission
652 N.E.2d 627 (Massachusetts Appeals Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
18 Mass. L. Rptr. 305, Counsel Stack Legal Research, https://law.counselstack.com/opinion/earth-tech-environment-infrastructure-inc-v-perinikiewitcashman-masssuperct-2004.