Glynn v. City of Gloucester

401 N.E.2d 886, 9 Mass. App. Ct. 454, 1980 Mass. App. LEXIS 1075
CourtMassachusetts Appeals Court
DecidedMarch 25, 1980
StatusPublished
Cited by55 cases

This text of 401 N.E.2d 886 (Glynn v. City of Gloucester) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glynn v. City of Gloucester, 401 N.E.2d 886, 9 Mass. App. Ct. 454, 1980 Mass. App. LEXIS 1075 (Mass. Ct. App. 1980).

Opinion

Greaney, J.

The city of Gloucester appeals from orders denying its motions (predicated on objections) challenging subsidiary and general findings in a master’s report and adopting the report and from a judgment awarding the plaintiff, as receiver of R. & J. Salvucci Corporation (Sal- *455 vucci), $243,007.05 in damages (and $95,711.47 in interest) for several alleged breaches by the city of its road construction contract with Salvucci. 1 We reverse the judgment, holding that the report in its present form should not have been adopted but rather should have been recommitted for additional findings, summaries of the evidence, and production of certain exhibits.

The procedural background follows. Salvucci contracted to construct a road in and through the Cape Ann Industrial Park in Gloucester. Work commenced around July 1,1972, and was completed on October 31, 1973. In July, 1976, Salvucci’s receiver filed suit against the city. The amended complaint claimed that the contractor had incurred $528,753.76 in damages stemming from certain activities by the city in violation of the contract, among them a refusal to provide a disposal area for inorganic debris removed from the job, a failure seasonably to designate areas where suitable off-site borrow could be obtained, and a refusal to grant reasonable relief when the contractor encountered subsurface soil conditions at variance with those to be anticipated from the plans and test borings. The master, acting under a non-jury order of reference with evidence to be left unreported, found that the city had breached the contract: (1) by misrepresenting the subsurface soil conditions on the plans and thereafter refusing to allow Salvucci to deal with the actual conditions in a reasonable and economical fashion; (2) by seeking to impose a charge for use of the city dump in violation of a contract provision that promised a free disposal site for inorganic debris; (3) by ordering Salvucci to rebuild the road’s embankments after rocks buried in their sides at the engineers’ directions had caused concave slopes; and (4) by failing, as required by the agree *456 ment, to designate a suitable area for the excavation of usable gravel borrow and fill for the road’s subgrade. The master also found that a memorandum signed by Salvucci’s president just prior to the job’s completion, which stated that the contractor had no present or anticipated claims under the agreemént against the city, did not constitute a waiver or release of the contractor’s rights, and that, if the memorandum was held sufficient to waive or release Salvucci’s claims, it was signed under duress. Finally, the master found that, although Salvucci had failed to comply with the contract procedure for claiming payment for extras, the city was “aware that the corporation was incurring . . . extra costs and intended to make a claim in connection therewith.”

Following the filing of the report, the city, punctiliously adhering to the requirements of Mass.R.Civ.P. 53, as amended, 367 Mass. 917 (1975), and Rule 49(7) of the Superior Court, as amended (1976), as explained by the cases (see post-1976, Miller v. Winshall, ante 312, 315-317 [1980]), filed fifteen specific and detailed objections which challenged the legal sufficiency of specific parts of the report. Wherever the objections questioned the adequacy of the underlying evidence to support the master’s subsidiary findings, fair summaries of the evidence were requested, and annexed to each such objection, as required by the rule, were references to the portions of the approved transcript (by volume, page and line) where the material and relevant testimony necessary for each summary could be found. Wherever the objection depended on a documentary exhibit, the exhibit or specific portion thereof that was needed was identified with particularity. Each objection, wherever pertinent, reasonably synopsized the city’s view of the contents of the evidence it relied upon for support. Together with the objections, the city filed motions to strike the master’s ultimate findings or to recommit for summaries of the evidence. Bills v. Nunno, 4 Mass. App. Ct. 279, 282-283 (1976).

1. The central task confronting the court based on the report’s findings was one of contract interpretation. Daley *457 V. J.F. White Contr. Co., 347 Mass. 285, 288 (1964). Gil-Bern Constr. Corp. v. Medford, 357 Mass. 620, 623 (1970). As discussed more fully in part 2 of this opinion, the judge needed to determine whether Salvucci’s claims arose in connection with its performance of the contract. If so, recovery for extras would hinge on the contractor’s showing that it had complied with the notice, claim and cost adjustment clauses in the agreement (paragraphs 17, 21, and 22 of the General Conditions), and with applicable provisions of the “Standard Specifications for Highways, Bridges and Waterways” adopted by the Commonwealth’s Department of Public Works (the Blue Book), or in the alternative, that the city had waived or excused compliance with the necessary formalities. Certain statutes governing claims of this sort, as will be noted, also might apply to Salvucci’s right to recover.

In our view, the master’s findings, both subsidiary and general, are insufficient to permit a judge to address adequately the dispositive legal questions. The report does not (as it should) disclose on its face all the subsidiary findings which the master had in mind and upon which he based his general findings. Bi lls v. Nunno, supra at 282, and cases cited. The subsidiary findings on several of the vital issues are vague and non-specific and leave the general findings ultimately predicated thereon lacking in sufficient foundation. See Lattuca v. Cusolito, 343 Mass. 747, 752-753 (1962), and cases cited. By way of examples, the report fails to indicate what action Salvucci took to clarify an obvious deviation from the terms of the contract when the city sought to charge Salvucci for the use of its dump for disposal of inorganic as well as organic materials 2 (see John F. Miller Co. v. George Fichera Constr. Corp., 7 Mass. App. Ct. 494, 499 [1979]); it fails to indicate precisely what the preliminary test-borings indicated; 3 it fails to find *458 whether the extras had written or express approval by the project engineer, implying that one claim may not have (screening plant) and that another might have (slope reconfigured at engineers’ “direction”); it leaves the damages only loosely accounted for with much emphasis on reasonableness. The report is replete with rulings of law which were not expressly addressed by the judge. Some of the other defects in the report are noted in the margin.- 4 The master also failed to incorporate all relevant portions of the contract and such of the documents integrally related to it (plans, specifications, Blue Book and borings) that are needed for analysis of the legal questions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Liu v. Mystery, LLC
Massachusetts Land Court, 2021
Old Colony Construction, LLC v. Southington
Supreme Court of Connecticut, 2015
Celco Construction Corp. v. Town of Avon
26 N.E.3d 202 (Massachusetts Appeals Court, 2015)
XL Specialty Insurance v. Massachusetts Highway Department
31 Mass. L. Rptr. 147 (Massachusetts Superior Court, 2013)
Bachorz v. Miller-Forslund
703 F.3d 27 (First Circuit, 2012)
Garrity v. Conservation Commission
971 N.E.2d 748 (Massachusetts Supreme Judicial Court, 2012)
Eldamar Development Co. v. Sweeney
27 Mass. L. Rptr. 63 (Massachusetts Superior Court, 2010)
Fresh Pond Mall Ltd. Partnership v. Payless ShoeSource, Inc.
26 Mass. L. Rptr. 32 (Massachusetts Superior Court, 2009)
City of Lynn v. Lynn Police Ass'n
899 N.E.2d 106 (Massachusetts Appeals Court, 2009)
Trans-Spec Truck Service, Inc. v. Caterpillar Inc.
524 F.3d 315 (First Circuit, 2008)
In Re Millivision, Inc.
328 B.R. 1 (D. Massachusetts, 2005)
G. Conway, Inc. v. Tocci Building Corp.
18 Mass. L. Rptr. 565 (Massachusetts Superior Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
401 N.E.2d 886, 9 Mass. App. Ct. 454, 1980 Mass. App. LEXIS 1075, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glynn-v-city-of-gloucester-massappct-1980.