MICHAEL GERHARDT & Another v. ROBERT S. BURR & Others.

CourtMassachusetts Appeals Court
DecidedApril 8, 2026
Docket25-P-0523
StatusUnpublished

This text of MICHAEL GERHARDT & Another v. ROBERT S. BURR & Others. (MICHAEL GERHARDT & Another v. ROBERT S. BURR & Others.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MICHAEL GERHARDT & Another v. ROBERT S. BURR & Others., (Mass. Ct. App. 2026).

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

25-P-523

MICHAEL GERHARDT & another 1

vs.

ROBERT S. BURR & others. 2

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

The plaintiffs, Michael Gerhardt and Lauren Seaverns,

worked for a real estate development company called College

Street Partners LLC, which was owned and managed by the

defendant, Robert Burr. In 2009, Burr entered into written

"participation agreements" with Gerhardt and Seaverns that gave

them economic interests in a construction project referred to as

"140 Commonwealth Avenue-Danvers," which they helped to develop.

In 2011, Burr entered into participation agreements with

Gerhardt and Seaverns that gave them economic interests in

1 Lauren Seaverns. 2College Street Partners LLC; 140 Commonwealth Avenue- Danvers, LLC; and Hawthorne Hill Development LLC. another construction project, "Hawthorne Hill." Gerhardt and

Seaverns left their employment with College Street Partners in

2013, and Burr stopped making distributions to them under the

participation agreements shortly thereafter.

In 2021, the plaintiffs filed suit in Superior Court

against Burr, College Street Partners, and two other limited

liability companies associated with the two construction

projects. After the parties cross-moved for summary judgment, a

judge allowed the plaintiffs' motion for partial summary

judgment as to Burr's liability for breach of contract. 3 The

judge concluded that "it is undisputed that Burr stopped

distributing profits to Gerhardt and Seaverns once their

employment with College Street Partners ended in 2013, Burr's

contractual obligation did not end when Gerhardt and Seaverns

stopped working for College Street, and this claim is not barred

by waiver or estoppel." The matter proceeded to a bench trial

on damages. In his written findings and conclusions, the judge

ordered Burr to pay (1) Gerhardt $1,030,744 in damages plus

prejudgment interest, and (2) Seaverns $575,758 in damages plus

prejudgment interest. The judge denied Burr's "emergency

3 In the event that the judge awarded them partial summary judgment on their claim for breach of contract, the plaintiffs waived their claims for breach of a contract formed by reasonable reliance, quantum meruit, or unjust enrichment. The judge dismissed defendant College Street Partners' counterclaims against Gerhardt.

2 motion" for reconsideration of the judge's summary judgment

ruling.

On appeal, Burr 4 contends that the plaintiffs' action should

have been dismissed as time-barred under the six-year statute of

limitations for contract claims. He contends that the judge

erred in granting partial summary judgment as to liability

because Burr's testimony established his estoppel and waiver

defenses and the judge purportedly "ignored" Burr's laches

defense. Burr also contends that, at the damages trial, the

judge misapplied the parol evidence rule, excluded key evidence

about reliance, and miscalculated the plaintiffs' damages and

prejudgment interest. Lastly, Burr claims that the judge erred

by declining to reconsider his summary judgment decision. We

affirm the judge's decisions in all respects.

Discussion. 1. Partial summary judgment. a. Standard of

review. "We review a decision on a motion for summary judgment

de novo." Conservation Comm'n of Norton v. Pesa, 488 Mass. 325,

330 (2021) (Pesa). "Summary judgment is appropriate where there

is no genuine issue of material fact and the moving party is

entitled to judgment as a matter of law." Barbetti v.

Stempniewicz, 490 Mass. 98, 107 (2022), quoting Pesa, supra.

See Mass. R. Civ. P. 56 (c), as amended, 436 Mass. 1404 (2002).

4 Because no recovery was awarded against the three defendant companies, we refer to the appellants as "Burr."

3 b. Statute of limitations. Burr stopped making

distributions to Gerhardt and Seaverns for the two projects in

2013. The plaintiffs filed suit in 2021. General Laws c. 260,

§ 1, provides that the statute of limitations for "[a]ctions

upon contracts under seal" is twenty years. General Laws

c. 260, § 2, provides that the statute of limitations for most

contract actions not "limited by section one" is six years. In

his summary judgment decision, the judge concluded that, because

the participation agreements are sealed instruments, the twenty-

year limitations period in G. L. c. 260, § 1, applies, and the

plaintiffs' action is not time-barred.

Massachusetts is "one of the minority of American

jurisdictions that have carried over significant elements of the

sealed contract doctrine to the Twenty-first Century." Knott v.

Racicot, 442 Mass. 314, 320 (2004). Although some aspects of

the sealed contract doctrine have "eroded" in the Commonwealth,

id., quoting Nalbandian v. Hanson Restaurant & Lounge, Inc., 369

Mass. 150, 155 (1975), the twenty-year statute of limitations

continues to apply to "[a]ctions upon contracts under seal."

G. L. c. 260, § 1. See, e.g., Premier Capital, LLC v. KMZ,

Inc., 464 Mass. 467, 469, 474 (2013); JB Mtge. Co. v. Ring, 90

Mass. App. Ct. 93, 95 (2016).

Burr contends that the participation agreements are not

"contracts under seal" because they do not say so in the

4 "Recitals" section of the agreements. We disagree. Each of the

agreements states that it is "EXECUTED under seal," directly

above the parties' signatures. That statement gives each

agreement the legal effect of a sealed instrument under

G. L. c. 4, § 9A. See Nalbandian, 369 Mass. at 151 n.2;

Lawrence H. Oppenheim Co. v. Bloom, 325 Mass. 301, 302 (1950);

Glendale Coal Co. v. Nesson, 312 Mass. 293, 294 (1942). See

also Knott, 442 Mass. at 319-320, citing G. L. c. 4, § 9A ("Over

time, simply the words 'under seal' or a similar phrase

appearing in a mass-produced, form contract became sufficient to

invest that document with the privileged status of a sealed

instrument"). There is no requirement that the words "under

seal" appear in a section titled "Recitals." In Glendale Coal

Co., supra, the Supreme Judicial Court stated that the words

"Witness hand and seal" before the plaintiff's signature gave

his release "the legal effect of a sealed instrument." In

Boston v. Roxbury Action Program, Inc., 68 Mass. App. Ct. 468,

473 n.10 (2007), we held that the defendant company's statement,

just above its agent's signature, that it "caused this

instrument to be signed and sealed in its name" sufficed "to

create a sealed instrument."

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deerskin Trading Post, Inc. v. Spencer Press, Inc.
495 N.E.2d 303 (Massachusetts Supreme Judicial Court, 1986)
Thibbitts v. Crowley
539 N.E.2d 1035 (Massachusetts Supreme Judicial Court, 1989)
Nalbandian v. Hanson Restaurant & Lounge, Inc.
338 N.E.2d 335 (Massachusetts Supreme Judicial Court, 1975)
Cullen Enterprises, Inc. v. Massachusetts Property Insurance Underwriting Ass'n
507 N.E.2d 717 (Massachusetts Supreme Judicial Court, 1987)
Harrington v. Fall River Housing Authority
538 N.E.2d 24 (Massachusetts Appeals Court, 1989)
Boylston Development Group, Inc. v. 22 Boylston Street Corp.
591 N.E.2d 157 (Massachusetts Supreme Judicial Court, 1992)
Lawrence H. Oppenheim Co. v. Bloom
90 N.E.2d 7 (Massachusetts Supreme Judicial Court, 1950)
Glynn v. City of Gloucester
401 N.E.2d 886 (Massachusetts Appeals Court, 1980)
Century Fire & Marine Insurance v. Bank of New England-Bristol County, N.A.
540 N.E.2d 1334 (Massachusetts Supreme Judicial Court, 1989)
Piemonte v. New Boston Garden Corp.
387 N.E.2d 1145 (Massachusetts Supreme Judicial Court, 1979)
Turnpike Motors, Inc. v. Newbury Group, Inc.
596 N.E.2d 989 (Massachusetts Supreme Judicial Court, 1992)
Hull v. Attleboro Savings Bank
596 N.E.2d 358 (Massachusetts Appeals Court, 1992)
Elias v. Suran
616 N.E.2d 134 (Massachusetts Appeals Court, 1993)
Schwanbeck v. Federal-Mogul Corp.
592 N.E.2d 1289 (Massachusetts Supreme Judicial Court, 1992)
Kace v. Liang
36 N.E.3d 1215 (Massachusetts Supreme Judicial Court, 2015)
JB Mortgage Co., LLC v. Ring
56 N.E.3d 866 (Massachusetts Appeals Court, 2016)
Wilkisius v. Sheehan
155 N.E. 5 (Massachusetts Supreme Judicial Court, 1927)
Doujotos v. Leventhal
171 N.E. 445 (Massachusetts Supreme Judicial Court, 1930)
Dana v. Wildey Savings Bank
2 N.E.2d 450 (Massachusetts Supreme Judicial Court, 1936)
Schiller v. Metropolitan Life Insurance
3 N.E.2d 384 (Massachusetts Supreme Judicial Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
MICHAEL GERHARDT & Another v. ROBERT S. BURR & Others., Counsel Stack Legal Research, https://law.counselstack.com/opinion/michael-gerhardt-another-v-robert-s-burr-others-massappct-2026.