N.E. Bridge Contractors, Inc. v. City of Lawrence.

CourtMassachusetts Appeals Court
DecidedJuly 24, 2023
Docket22-P-0283
StatusUnpublished

This text of N.E. Bridge Contractors, Inc. v. City of Lawrence. (N.E. Bridge Contractors, Inc. v. City of Lawrence.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
N.E. Bridge Contractors, Inc. v. City of Lawrence., (Mass. Ct. App. 2023).

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

22-P-283

N.E. BRIDGE CONTRACTORS, INC.

vs.

CITY OF LAWRENCE.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

The plaintiff, N.E. Bridge Contractors, Inc. (NEB), brought

this action against the defendant, the city of Lawrence (city),

alleging that NEB had a contract with the city to complete

bridge repairs and NEB fulfilled its obligations under the

contract, but that the city refused to pay NEB for all materials

and labor. NEB sought damages for (1) $324,177.50 for

additional materials not included in the stated contract price,

and (2) $18,441.38, which reflected the difference between the

stated contract price of $326,410 and the amount the city paid

NEB, $307,968.62. In an amended order on cross motions for

summary judgment, a Superior Court judge (motion judge) granted

summary judgment in the city's favor on the $324,177.50 for

additional materials but concluded that there were genuine

issues of material fact as to the $18,441.38 balance. After a jury-waived trial, a different Superior Court judge (trial

judge) concluded that the city committed a breach of contract by

not paying NEB the $18,441.38 balance. Both parties appealed.

We affirm, but remand for recalculation of prejudgment interest.

Background. This appeal arises out of the city's

invitation for bids "to make some scour repairs" around the base

of a bridge pier. The invitation to bid included both detailed

drawings of the project and estimated quantities of materials

needed to perform the work. Bidders were asked to provide

prices for clearing the site, mobilization, and the following

estimated quantities of materials: eleven cubic yards of

concrete, nine hundred tons of riprap, and one thousand tons of

modified rockfill. Before the bid deadline of November 30,

2006, NEB submitted a bid of $286,410. On May 7, 2008, the city

entered into a contract with NEB to perform the work.

The contract included several provisions regarding the

scope of NEB's services and how the parties would handle changes

to the scope of those services. Under the scope of services

provisions, NEB's work "consist[ed] of straightening out a

section of steel sheeting and filling a void . . . underwater in

the Merrimack River with modified fill, riprap and tremie

concrete" using "[t]he quantities of material . . . estimated in

the [s]chedule of [p]rices." Paragraph 3 of the contract stated

that "[t]he above tasks and items [were] not intended to be all

2 inclusive" and included the following provisions for additions

or deletions to NEB's scope of services:

"The [c]ity may add to or delete any items, provided that any added items are of a similar nature, and provided that the total cost of such work does not exceed the total cost as specified in [p]aragraph 8 hereof. [NEB] shall undertake such work only upon the direction of the [c]ity. All directives and changes thereof in conformance with this [a]greement shall be in written form, prepared and signed by the [c]ity and accepted and countersigned by [NEB] or his authorized representatives. Any added tasks or items which are not agreed to be within the [s]cope of [s]ervices by both the [c]ity and [NEB], or which will incur costs beyond the total cost specified in [p]aragraph 8, shall be handled in accordance with [p]aragraph 13 hereof."1

Paragraph 13 stated that if NEB provided services "not to the

satisfaction of the [c]ity, the [c]ity [could] request that

[NEB] refurnish services at no additional cost" or "purchase

services in substitution," and that the city could deduct the

cost of substituted services or the nonperformance of services

from the contract price. In addition, the contract incorporated

by reference the Massachusetts Highway Department's Standard

Specifications for Highways and Bridges, and those

specifications recited the requirements of G. L. c. 30, § 39N.

Under G. L. c. 30, § 39N, all contracts subject to G. L. c. 149,

§ 44A, or G. L. c. 30, § 39M, must set forth the procedure for

1 Likewise, paragraph 12 provided that any changes in the scope of services, "including any increase or decrease in the amount of [NEB's] compensation or any change in the work schedule, which are mutually agreed upon by and between the [c]ity and [NEB], shall be incorporated in written amendments to this [a]greement."

3 addressing differing subsurface or latent physical conditions

and specify that requests for equitable adjustments due to those

conditions be made in writing.

The contract also included several provisions regarding

compensation. "The [c]ity agree[d] to pay [NEB] the

compensation specified in Schedule B, Compensation and Method of

Payment, . . . which shall constitute complete compensation for

all services rendered and for such reimbursable expenses as

authorized per paragraph 9." By paragraph 9, "[t]he [c]ity

agree[d] to reimburse [NEB] only for those direct costs incurred

by [NEB] pursuant to the performance of work under this

[a]greement as set forth and authorized within Schedule B."

Schedule B provided that payment was "not to exceed $286,410."

Around the time the parties entered into the contract, NEB

requested a price increase of $40,000, noting that there had

been a significant increase in the cost of supplies, materials,

and fuel since it bid on the project over one year prior. The

city approved the $40,000 increase, bringing the contract price

to $326,410. The increase was memorialized in a written change

order signed by the parties at various times in May through July

of 2008.

Thereafter, two disputes arose between the parties. The

first dispute, which concerned NEB's claim that it used

4 $324,177.50 in additional materials,2 was resolved on summary

judgment. We recite the facts pertinent to that dispute in the

light most favorable to NEB. See HSBC Bank USA, N.A. v. Morris,

490 Mass. 322, 326-327 (2022). When NEB began its work, its

divers encountered a larger void than the one depicted on the

detailed project drawings, and it "became apparent" to NEB that

"additional quantities of certain materials specified in the

[c]ontract would be required in order to perform the work." On

or around July 22, 2008, NEB filled the void using 154 cubic

yards of cement, an overrun of 143 cubic yards of cement,

without obtaining a written change order. NEB also used an

additional 170.54 tons of riprap. NEB's president, John

Waitkus, submitted an affidavit stating that a city engineer and

a representative of the city's authorized field engineer, Fay,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Costonis v. Medford Housing Authority
176 N.E.2d 25 (Massachusetts Supreme Judicial Court, 1961)
Glynn v. City of Gloucester
401 N.E.2d 886 (Massachusetts Appeals Court, 1980)
Kendall v. Selvaggio
602 N.E.2d 206 (Massachusetts Supreme Judicial Court, 1992)
Lowell Housing Authority v. PSC International, Inc.
692 F. Supp. 2d 180 (D. Massachusetts, 2010)
T.W. Nickerson, Inc. v. Fleet National Bank
924 N.E.2d 696 (Massachusetts Supreme Judicial Court, 2010)
Celco Construction Corp. v. Town of Avon
26 N.E.3d 202 (Massachusetts Appeals Court, 2015)
Fergus v. Ross
79 N.E.3d 421 (Massachusetts Supreme Judicial Court, 2017)
Ryan v. Boston Housing Authority
77 N.E.2d 399 (Massachusetts Supreme Judicial Court, 1948)
Sutton Corp. v. Metropolitan District Commission
667 N.E.2d 838 (Massachusetts Supreme Judicial Court, 1996)
Perseus of N.E., MA, Inc. v. Commonwealth
706 N.E.2d 681 (Massachusetts Supreme Judicial Court, 1999)
Iannacchino v. Ford Motor Co.
451 Mass. 623 (Massachusetts Supreme Judicial Court, 2008)
Parks v. Johnson
703 N.E.2d 728 (Massachusetts Appeals Court, 1998)
Dagastino v. Commissioner of Correction
754 N.E.2d 150 (Massachusetts Appeals Court, 2001)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
N.E. Bridge Contractors, Inc. v. City of Lawrence., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ne-bridge-contractors-inc-v-city-of-lawrence-massappct-2023.