Sutton Corp. v. Metropolitan District Commission

667 N.E.2d 838, 423 Mass. 200, 1996 Mass. LEXIS 163
CourtMassachusetts Supreme Judicial Court
DecidedJuly 16, 1996
StatusPublished
Cited by16 cases

This text of 667 N.E.2d 838 (Sutton Corp. v. Metropolitan District Commission) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sutton Corp. v. Metropolitan District Commission, 667 N.E.2d 838, 423 Mass. 200, 1996 Mass. LEXIS 163 (Mass. 1996).

Opinion

Lynch, J.

Sutton Corporation (Sutton) brought this action against the Metropolitan District Commission (MDC) in April, 1982, for damages relating to site preparation work done on the replacement of the General Lawrence Bridge (bridge) in Medford.1 A master was appointed under Mass. R. Civ. P. 53, as amended, 386 Mass. 1237 (1982), who issued a report containing extensive findings of fact and rulings of law. A Superior Court judge adopted the master’s report in its entirety and awarded Sutton $255,504.61 plus $346,903.72 in interest. The MDC appealed from the judgment; Sutton cross appealed. The Appeals Court reversed the decision of the Superior Court. Sutton Corp. v. Metropolitan Dist. Comm’n, 38 Mass. App. Ct. 764 (1995). We granted Sutton’s application for further appellate review and now affirm the decision of the Superior Court.2

[202]*202A. Facts. We recite the significant facts as found by the master.3 Sutton bid for and was awarded a contract with the MDC to conduct site preparation as part of the replacement of the bridge. As part of its contract, Sutton was responsible for the installation of sand drains on the site of the bridge. Sutton contracted with Vibrofiotation Foundation Company for the use of Vibroflotation’s patented system of sand drain installation utilizing the “Dutch Bailor” method, which was one of the methods sanctioned in the contract specifications.4

Sutton agreed to charge $3 per linear foot for a total of 141,362 linear feet of sand drains. Sutton estimated that it would take approximately twenty minutes to install each of 1,570 sand drains over a period of thirty-five working days for a total cost of $424,086.

Sutton began installing trial sand drains on April 13, 1981, and immediately encountered a multitude of problems. Use of the “Dutch Bailor” method, as designed, resulted in sand drains that did not meet contract specifications. In attempts to explain these problems, on-site observers hypothesized that either the clay material in one of the layers of the soil was overcompacted or the clay in another layer contained more gravel than anticipated. Everyone agreed that the conditions at the site were unusual and that the resulting sand drains were unacceptable. On April 24, 1981, after two weeks of [203]*203failed attempts to improve the situation, Sutton stopped installing sand drains.5

By a letter dated April 27, 1981, Sutton advised the MDC that it had encountered a “changed condition” within the scope of G. L. c. 30, § 39N (1994 ed.), and requested permission to use a substitute system for compacting the soil. Sutton conducted some successful tests of the substitute “wick drain” system (which were paid for by the MDC), but ultimately the MDC declined to authorize its use.6 Eventually, Sutton resumed work using a highly-modified Dutch Bailor system. With the new system, Sutton was able to install sand drains acceptable to the MDC, but only at much greater cost and time than anticipated.7

As a result of the sand drain installation, a significant amount of “spoils material” accumulated on the site.8 Because the spoils material did not meet contract specifications for ground cover, the MDC required Sutton either to mix it with other material to bring it within contract specifications or to move the material offsite and replace it with soil that complied with the contract. Sutton asked instead to move the material to the preload area, another portion of the construction site. The MDC declined. Sutton then chose to remove the spoils material and replace it with “gravel borrow,” for a total cost of $153,094.

[204]*204B. Changed condition. Sutton first argues that it is entitled to an equitable adjustment under the changed conditions provision of the contract. The Superior Court judge adopted the master’s rulings that: (1) there was a “changed condition” within the meaning of G. L. c. 30, § 39N; and (2) Sutton satisfied the procedural requirements for an equitable adjustment claim under the “changed conditions” provision of the contract.9 The MDC argues, first, that there was no changed condition. In the alternative it argues that, even if there was a changed condition, Sutton’s claims are barred because they fall under the purview of the “extra work” provision of the contract (Article XVIII) and Sutton failed to follow the detailed procedural prerequisites for such a claim.10 It was on this latter ground that the Appeals Court reversed the deci[205]*205sion of the Superior Court and ruled in the MDC’s favor. 38 Mass. App. Ct. at 760.

We begin with the general rule that “contractor’s invocation of remedies available under either the contract or applicable statutes such as G. L. c. 30, § 39N, must be addressed by the public agency in good faith. Glynn v. Gloucester, 9 Mass. App. Ct. [454, 460-461 (1980) (Glynn I)].” Glynn v. Gloucester, 21 Mass. App. Ct. 390, 397 (1986) (Glynn II). Here, Sutton followed the procedures set out in § 39N (and incorporated in the contract as part of Article XIX); once Sutton discovered what it believed to be a changed condition, it ceased operations and notified the MDC by letter seeking an equitable adjustment. The MDC does not dispute that Sutton fulfilled the procedural prerequisites of § 39N.

The master found that, in the course of the sand drain installation, Sutton had experienced a “Type II” changed condition, because “the site conditions [were] substantially in conformance with the contract documents, but the installation system specified did not perform as anticipated.”11 The Ap[206]*206peals Court ruled that the master’s conclusion was “incorrect as matter of law” because it relied on the failure of the installation system rather than the soil conditions, Sutton Corp. v. Metropolitan Dist. Comm’n, supra at 767 n.2, but went on to conclude that “Sutton experienced a changed condition under § 39N, since the [master’s] subsidiary findings support the conclusion that the actual soil conditions differed radically from those described in the contract plans.” Id.

We agree that Sutton experienced a changed condition within the meaning of the statute, but for slightly different reasons than either the master or the Appeals Court. The Appeals Court correctly criticizes the master’s report for improperly focusing on the performance of the equipment, not the actual physical conditions, as required by the statute. G. L. c. 30, § 39N. But the Appeals Court improperly focuses on the description of the conditions set out in the contract plans. Id. Where the actual subsurface conditions differ substantially from those conditions “ordinarily encountered and generally recognized as inherent in work of the character provided for in the plans and contract documents,” G. L. c. 30, § 39N, there is a changed condition under the meaning of the statute, whether or not the conditions differ from the contract specifications. Thus, contrary to the MDC’s assertions, the Federal “Type II” changed condition is explicitly part of Massachusetts law, as demonstrated by both the text of the statute and regulations promulgated pursuant to the statute.12

[207]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

N-Tek Construction Services, Inc. v. Hartford Fire Insurance Co.
47 N.E.3d 435 (Massachusetts Appeals Court, 2016)
Old Colony Construction, LLC v. Southington
Supreme Court of Connecticut, 2015
Commonwealth v. Forte
14 N.E.3d 900 (Massachusetts Supreme Judicial Court, 2014)
XL Specialty Insurance v. Massachusetts Highway Department
31 Mass. L. Rptr. 147 (Massachusetts Superior Court, 2013)
Awuah v. Coverall North America, Inc.
843 F. Supp. 2d 172 (D. Massachusetts, 2012)
C & I Steel, LLC v. Travelers Casualty & Surety Co. of America
876 N.E.2d 442 (Massachusetts Appeals Court, 2007)
Lily Transportation Corp. v. Royal Institutional Services, Inc.
832 N.E.2d 666 (Massachusetts Appeals Court, 2005)
Secretary of Administration & Finance v. Labor Relations Commission
749 N.E.2d 137 (Massachusetts Supreme Judicial Court, 2001)
West Valley Corp. v. City of Worcester
8 Mass. L. Rptr. 672 (Massachusetts Superior Court, 1998)
North Star Service, Inc. v. New England Sports Management Corp.
7 Mass. L. Rptr. 491 (Massachusetts Superior Court, 1997)
Commonwealth v. Johnson Insulation
682 N.E.2d 1323 (Massachusetts Supreme Judicial Court, 1997)
Sutton Corp. v. Metropolitan District Commission
6 Mass. L. Rptr. 255 (Massachusetts Superior Court, 1996)
Peabody N.E., Inc. v. Town of Marshfield
6 Mass. L. Rptr. 473 (Massachusetts Superior Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
667 N.E.2d 838, 423 Mass. 200, 1996 Mass. LEXIS 163, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sutton-corp-v-metropolitan-district-commission-mass-1996.