D. Federico Co. v. New Bedford Redevelopment Authority

399 N.E.2d 1103, 9 Mass. App. Ct. 141, 1980 Mass. App. LEXIS 1004
CourtMassachusetts Appeals Court
DecidedFebruary 6, 1980
StatusPublished
Cited by14 cases

This text of 399 N.E.2d 1103 (D. Federico Co. v. New Bedford Redevelopment Authority) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D. Federico Co. v. New Bedford Redevelopment Authority, 399 N.E.2d 1103, 9 Mass. App. Ct. 141, 1980 Mass. App. LEXIS 1004 (Mass. Ct. App. 1980).

Opinion

Kass, J.

Decision in this case turns on whether the plaintiff, a construction company, was bound by its contract to *142 make a particular form of demand before bringing suit. Judgment was entered for the plaintiff on a master’s report and, save for modifications with respect to payment of interest, we affirm that judgment.

Most of the facts are not in dispute. The defendant, the New Bedford Redevelopment Authority (NBRA), invited bids for site work in connection with an urban renewal project, largely involving construction of storm drains, sanitary sewers, water mains, curbs, sidewalks and new pavement in the streets. The bid form carried a category of work described as “Maintenance and Protection of Traffic,” which appeared as line item 36 on the bid form and on subsequent job requisition forms. That item contemplated putting up appropriate wooden barricades, flashing barricades, wooden signs marked “Danger,” and the assignment of traffic policemen. The plaintiff was the low bidder and entered into a construction contract on November 4, 1974, which expressly incorporated all the line items in the bid form.

We turn now to the master’s subsidiary findings, which are binding upon us unless they are clearly erroneous, mutually inconsistent, contradictory or vitiated in view of the controlling law. Michelson v. Aronson, 4 Mass. App. Ct. 182, 190 (1976). John F. Miller Co. v. George Fichero Con-str. Corp., 7 Mass. App. Ct. 494, 495 (1979). The master found that the plaintiff completed the work covered by the contract in December, 1976; that it did maintain and protect traffic in the work area, a residential area in New Bed-ford covering four blocks; that the plaintiff had not waived payment for traffic maintenance and protection; and that the defendant has refused to pay for that work.

It is the position of the NBRA that whatever right the plaintiff may have had to payment for traffic maintenance and protection (the amount allocated to that work by line item 36 in the contract was $31,000) was lost because the plaintiff did not present the dispute to the NBRA within ten days after its commencement. 1

*143 Concerning interpretation of the contract, this court can, of course, draw its own conclusions independently of those of the master. Peters v. Wallach, 366 Mass. 622, 626 (1975). Middlesex Neurological Associates, Inc. v. Cohen, 3 Mass. App. Ct. 126, 130 (1975). Bills v. Nunno, 4 Mass. App. Ct. 279, 283 (1976). See also Urban Transp., Inc. v. Mayor of Boston, 373 Mass. 693, 694 n.l (1977) (judge may reject master’s conclusions of law); Poskus v. Braemoor Nursing Home, Inc., 6 Mass. App. Ct. 896 (1978). Although the master found that the plaintiff, during the course of the contract, had demanded and been refused payment on account of maintenance and protection of traffic, the plaintiff made no written requisition for the line item in the contract. As requisitions proceeded, that category of work stayed in the breakdown of amounts to be paid, an implicit acknowledgement by the NBRA of the plaintiff’s reservation of right to draw down construction payments on account of it. Thus, the dispute concerning payment of line item 36 did not mature until the job was finished, and the NBRA had made it abundantly clear that it was going to resist paying for traffic protection and maintenance.

At that point, it was an exercise in futility by the plaintiff to file notice of a dispute with the NBRA. “Although performance of a particular act by one party is contractually specified to be precedent to the arising of an obligation in another, the prior act need not be performed where it would be a hollow gesture sure to be disregarded by the other party.” Trustees of Boston & Maine Corp. v. Massa *144 chusetts Bay Transp. Authy., 367 Mass. 57, 61-62 n.2 (1975), and cases cited. See by analogy Pupecki v. James Madison Corp., 376 Mass. 212, 218 (1978), which states the familiar rule that although, in order to maintain a derivative suit, a shareholder must make a demand on the directors that they cause the corporation to file the action, the requirement does not apply if it appears that demand would be futile.

At the time the plaintiff pressed its claim, the contract was still open in that the NBRA had not made a final payment on the contract or obtained a release from the plaintiff, as provided in § 108(2) (a) of the contract, relating to final payment. The NBRA cannot on the one hand hold the matter open 2 and on the other hand claim that the plaintiff acted too late. Giving a practical reading to the contract, Clark v. State St. Trust Co., 270 Mass. 140, 153 (1930); Fay, Spofford & Thorndike, Inc. v. Massachusetts Port Authy., 7 Mass. App. Ct. 336, 344 (1979), the plaintiff is entitled to payment for line item 36, the item for maintenance and protection of traffic.

After the master filed his report, the defendant requested a fair summary of the evidence. Rule 49(7) of the Superior Court (1974). The master made a summary of the evidence which the defendant moved to strike in part. Simultaneously, defense counsel filed an affidavit as to what he considered a fair summary of the evidence furnished by a principal witness for the plaintiff, accompanied by a motion to affirm the defendant’s version of the evidence. Those motions were denied by the Superior Court judge. We have examined the affidavit of defense counsel and agree with the judge, let alone finding an abuse of discretion. Indeed, the summary of evidence furnished by defense counsel, even had it been substituted for that of the master, would not alter our view of the meaning of the disputed contract. The remaining objections made by NBRA to the master’s report *145 attempt to establish inconsistencies among the master’s subsidiary findings, but we do not share the view that those findings are inconsistent as to facts we consider material.

Had the NBRA desired to strike maintenance and protection of traffic from the scope of the work, it should have done so at the time it entered into the construction contract. Contractors are held to strict accord with their undertakings, Albre Marble & Tile Co. v. Goverman, 353 Mass. 546, 549 (1968), and it is not too much to ask the same standard of conduct from public agencies.

This leaves us to consider the appropriate interest which should be paid on those amounts we have decided were wrongfully withheld from the plaintiff. General Laws c. 30, § 39G, as amended through St. 1972, c.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Massachusetts Highway Department v. Perini Corp.
947 N.E.2d 62 (Massachusetts Appeals Court, 2011)
J.C. Higgins Co. v. Bond Bros.
791 N.E.2d 367 (Massachusetts Appeals Court, 2003)
Merit Oil of Massachusetts, Inc. v. Baer
12 Mass. L. Rptr. 249 (Massachusetts Superior Court, 2000)
Sutton Corp. v. Metropolitan District Commission
667 N.E.2d 838 (Massachusetts Supreme Judicial Court, 1996)
Cheschi v. Boston Edison Co.
654 N.E.2d 48 (Massachusetts Appeals Court, 1995)
Sutton Corp. v. Metropolitan District Commission
652 N.E.2d 627 (Massachusetts Appeals Court, 1995)
Orix Credit Alliance, Inc. v. Brandon Co.
1993 Mass. App. Div. 69 (Mass. Dist. Ct., App. Div., 1993)
Acme Plastering Co. v. Boston Housing Authority
490 N.E.2d 445 (Massachusetts Appeals Court, 1986)
Thomas O'Connor & Co. v. City of Medford
448 N.E.2d 1276 (Massachusetts Appeals Court, 1983)
A. Bonfatti & Co. v. Town of Rockport
429 N.E.2d 75 (Massachusetts Appeals Court, 1981)
Pyburn v. Fishery Products, Inc.
426 N.E.2d 1169 (Massachusetts Appeals Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
399 N.E.2d 1103, 9 Mass. App. Ct. 141, 1980 Mass. App. LEXIS 1004, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-federico-co-v-new-bedford-redevelopment-authority-massappct-1980.