Pyburn v. Fishery Products, Inc.
This text of 426 N.E.2d 1169 (Pyburn v. Fishery Products, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
The plaintiff, Thomas Pyburn, instituted suit to enforce a lien under G. L. c. 254, §§ 5 and 11, for work performed under an oral contract with subcontractor Ross-con Corporation (Rosscon). The case was referred to a mas[506]*506ter.2 While hearings before the master were proceeding, Pyburn added a second count to his complaint, alleging breach of a written contract between himself and Rosscon and the project’s general contractor, Richard Martin Development Company (Martin). The master concluded that Pyburn was entitled to a lien under G. L. c. 254, § 1, and that Martin was not liable to Pyburn under the second count of the complaint. Over Pyburn’s objections, the court adopted the master’s report. Judgment was entered for the plaintiff on count one. Count two was dismissed against both Martin and Rosscon. Pyburn appeals from the judgment, but addresses his argument solely to the dismissal of count two of his complaint.
The defendants Martin and Rosscon entered into a written contract on August 8, 1973, under which the subcontractor Rosscon was to perform excavation and grading work on a building site.3 Pursuant to that contract Rosscon and Pyburn made an oral agreement that Pyburn would do grading on the site. Although Rosscon’s work was to have been completed by September 28, 1973, it remained unfinished on March 6, 1974, the date on which Pyburn and his attorney met with representatives of Rosscon and Martin to discuss the matter of the completion of Rosscon’s work. Pyburn, who had performed until November 2, 1973, had claimed a lien and commenced this suit in December, 1973. The master found that Pyburn’s charges to Rosscon were fair and reasonable and that on March 6 Rosscon was still in default of his contract with Martin and still owed Pyburn a balance of $10,280.4 The master found that “a valid and [507]*507enforceable agreement” was entered into on March 6 for thirty days’ work at a cost of $19,000, that Martin’s representative stated “he wanted the job done as expeditiously as possible . . . [and] that he wanted the Pyburn lien removed,” that Pyburn agreed to lift the lien, that it was agreed that “no equipment or subcontractors, other than Rosscon or Pyburn should be on the job,” that “Pyburn’s promise to [Martin] to work with Rosscon to finish the job was sufficient consideration to support the promise of [Martin] to pay Rosscon for the work,” and “that at the meeting of March 6 the parties also agreed that checks in payment should be made payable to ‘Pyburn and [Rosscon’s representative]’.” A memorandum containing the terms of the agreement, but not including the method of payment, was initialed by the parties.
The master then found that Martin committed a breach of that agreement on March 15 but concluded that the agreement did not “creat[e] any liability on the part of [Martin] to Pyburn,” or “includfe] any promise by [Martin] to pay the charges made by Pyburn to Rosscon for the work performed by Pyburn up to November 2, 1973.” We think the judge erred in not sustaining Pyburn’s specific objections to these general findings.
When a master’s report “‘shows upon its face all the subsidiary facts which the master . . . had in mind and upon which he based his . . . [general findings], . . . we are in no way bound by . . . [his general findings], and we must take these subsidiary findings together with the inferences that ought to be drawn from them and reach our own conclusion.’” Bills v. Nunno, 4 Mass. App. Ct. 279, 283-284 (1976), quoting from O’Brien v. Dwight, 363 Mass. 256, 281-282 (1973), and cases cited. Wormstead v. Town Manager of Saugus, 366 Mass. 659, 660 (1975). McNamara v. Westview Bldg. Corp., 4 Mass. App. Ct. 670, 671 (1976). Lemieux v. Rex Leather Finkhing Corp., 7 Mass. App. Ct. 417, 418 (1979). D. Federico Co. v. New Bedford Redev. Authy., 9 Mass. App. Ct. 141, 142 (1980). By the orders of reference, the master [508]*508was directed not to file a report of the evidence with his report but to disclose in his report his subsidiary findings of fact and his conclusions of fact and law based thereon. The report sets forth adequate subsidiary findings to make it reasonable to assume that the master complied with the order, and we are free to draw our own inferences from those findings. Jones v. Gingras, 3 Mass. App. Ct. 393, 395-396 (1975). Bennett v. Papetsas, 6 Mass. App. Ct. 568, 569-570 (1978). E. F. Semas Trucking, Inc. v. Mayor of Taunton, 7 Mass. App. Ct. 907, 908 (1979). On the face of the master’s subsidiary findings it is clear that the meeting of March 6 produced a contract between Martin and Pyburn under which Martin was bound to make payments to Pyburn and Rosscon, and Pyburn was bound to lift his lien and assist Rosscon in completing the construction work. Pyburn’s objection to the master’s conclusion that the contract did not create any liability of Martin to Pyburn should not have been overruled. “If . . . a master’s report discloses . . . the basis for a general finding and it is apparent thereby that the general finding is erroneous, a party aggrieved by the general finding is entitled to have his objection to the general finding sustained . . . .” Bills v. Nunno, supra, at 283, citing United States Fid. & Guar. Co. v. English Constr. Co., 303 Mass. 105, 111-112 (1939). See also Urban Transp., Inc. v. Mayor of Boston, 373 Mass. 693, 694 n.1 (1977), citing Central Tow Co. v. Boston, 371 Mass. 341, 342 n.3 (1976).
As to the master’s general finding that the March 6 agreement did not include a promise by Martin to pay the charges made by Pyburn to Rosscon for the work performed by Pyburn up to November 2, 1973, we find irresistible the conclusion that such a promise was made. We think this case is related to Massachusetts decisions allowing recovery for an oral promise to pay the debt of another, when the essence of the agreement containing such promise is to obtain a pecuniary benefit by the promisor from the promisee, and when such promise is merely incidental to obtaining that benefit. Hayes v. Guy, 348 Mass. 754, 756 (1965), citing Colpitts v. [509]*509L. C. Fisher Co., 289 Mass 232, 234 (1935).5 “[Agreements which will have the effect to discharge the debt of another, must be founded in a motive of interest, selfish in the promisor. The distinction is between a promise, the object of which is to promote the interest of another, and one in which the object is to promote the interest of the party making the promise .... [I]f the promisor is himself acquiring property or other pecuniary benefit, he is engaging not to pay the debt of another, but his own.” 3 Williston, Contracts § 472, at 432 (3d ed. 1960).6
Here Martin’s essential object was not to satisfy Rosscon’s obligation, but to secure the direct pecuniary benefits of Tyburn’s removal of the lien and assistance in completing the project. See Hayes v. Guy, supra; Merrill v. Kirkland Constr. Co., 365 Mass. 110 (1974); Laurence Albre Associates, Inc. v. Italian Catholic Cemetery Assn., 9 Mass. App. Ct. 922 (1980). Contrast Howard L. Baker Co. v. Meledones, 352 Mass. 485 (1967); M.J. Pirolli & Sons v. Mass. Equip. & Supply Corp., 9 Mass. App. Ct. 863 (1980).
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
426 N.E.2d 1169, 12 Mass. App. Ct. 505, 1981 Mass. App. LEXIS 1223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pyburn-v-fishery-products-inc-massappct-1981.