D. Federico Co. v. New Bedford Redevelopment Authority (In re D. Federico Co.)

25 B.R. 822, 1982 Bankr. LEXIS 5438
District Court, D. Massachusetts·Decided November 23, 1982·No. Bankruptcy No. 79-2289-HL; Adv. No. A80-0619·Published·Cited by 6 cases

Opinion

FINDINGS AND RULINGS ON DAMAGES

HAROLD LAVIEN, Bankruptcy Judge.

This proceeding centers around a construction contract entered into between the plaintiff, D. Federico Company, Inc. (“Federico”), and the defendant, New Bedford Redevelopment Authority (“Authority”). Jurisdiction is based on 28 U.S.C. § 1471, an Order for Relief on behalf of the D. Federico Company, Inc. having been entered on September 18, 1980. The plaintiff, United States Fidelity and Guaranty Company (“U.S.F.G.”) is the surety on the payment and performance bonds naming the Authority as obligee and Federico as principal. It is uncontested that U.S.F.G., by virtue of its obligations under the bonds, has expended monies to complete the project. U.S. F.G. bases its standing on its right of equitable subrogation and its status as assignee of all Federico’s contract balances and claims. The defendant, City of New Bed-ford, has assumed the liabilities of the Authority in connection with the contract in issue by virtue of a Closeout Agreement executed by and between the Department of Housing and Urban Development and the Authority.

The plaintiff, Federico, a general contractor, held five public contracts with the defendant, Authority, as part of a substantial urban renewal program in the City of New Bedford. At issue in this case is Contract No. 5 of the South Terminal Urban Renewal Project, a contract for the reconstruction of the two earth-filled bulkhead piers, Homer’s Wharf and Leonard’s Wharf.

By agreement, the trial was bifurcated. The Court issued its opinion on liability in December of 1981.1 The damages trial began in April of 1982 after some preliminary hearings, and the trial was completed in July of 1982, with seven days of evidence in total.

On April 5, 1982, the parties stipulated to the retainages on the following items in the following amounts:

1) TOTAL RETAINAGE DUE AFTER APPROVAL OF ESTIMATE NO. 53 $160,064.53
2) RETAINAGE WITHHELD ON CHANGE ORDERS 2 & 3 31,587.11
3) AMOUNT OF ESTIMATE NO. 53 17,610.68
4) AMOUNT DUE LINE ITEM 33 SITE PREPARATION 43,095.00
5) AMOUNT DUE LINE ITEM 31 FIELD OFFICE 100.00
TOTAL BEING WITHHELD BY THE AUTHORITY $252,457.52

In addition to these amounts, the Court had determined in the liability section that $140,000 was due the plaintiff on line item 34, traffic and maintenance, and that the Authority was entitled to a credit of $1,552.26 for overpayments on Change Orders No. 2 and 3. The final total of $390,-905.26 was subject to any additional amount of damages awarded to the contractor and any offsets that the Authority might be entitled to under its counterclaim as previ[825] ously ruled on in the Court’s December 29, 1981 Memorandum. The parties further agreed that to the extent it was necessary, Ex. FD1 gave the varying interest rates under Mass.Gen.Laws ch. 30 § 39G.

On May 17,1982, well after the Court had made its findings in the liability trial, which defined and limited the issues to be heard in the damages trial; after several pre-trial hearings and after the trial on damages had begun, the Authority sought for the first time to amend its counterclaim and challenge eight line items in Ex. 6, Estimate No. 53, the Authority’s semi-final estimate of January, 1979. The Court denied the Authority’s motion to amend its counterclaim not only because at this belated date the trial had already commenced, but also on the theory that the parties had stipulated to the accuracy of the Authority’s semifinal estimate and that the plaintiff’s trial preparation had been completed on the basis that the issues open had been defined in the liability findings based on the Authority’s then set of counterclaims. Vargas v. McNamara, 608 F.2d 15 (1st Cir.1979); Johnston v. Holiday Inns, Inc., 595 F.2d 890 (1st Cir.1979); Span East Airlines v. Digital Equipment Corp., 486 F.Supp. 831 (D.Mass.1980). Therefore, the defendants were not allowed to offer evidence in conflict with the semi-final estimate.

RAYMOND CONCRETE PILE EXCAVATIONS

On the issue of the excavations, two things must be said before any consideration of the evidence on damages. First, we are dealing with an issue where neither party is entitled to be totally vindicated. The Court determined in the liability trial that the Authority had information that would have been helpful to the bidders, which disclosed in more detail the composition of the collapsed pier and therefore revealed the material which was likely to be encountered in the required excavation. On the other hand, the Court also found that had the contractor made a reasonably thorough low tide visual examination of the remains of the collapsed portion of the pier and its environs, the contractor would have observed everything that was in fact encountered in excavation including the likely existence of Raymond concrete piles. Second, the contractor’s bid made it clear that its examination might charitably be called superficial and it was in fact unaware of the Raymond concrete piles though even on its superficial examination, it was or should have been aware of everything else. Therefore, the only reason for not holding the contractor to its bid is that it would result in an unwarranted benefit to the Authority. The Authority was accordingly required to pay for the removal of the Raymond concrete piles that it would have been charged for had the Goodkind & O’Dea Engineering Report (Report) been made available.

As a matter of equity and in the context of this case where each party acted imprudently, I originally concluded that an appropriate measure of damages would be the reasonable bid that would have been made to remove the Raymond concrete piles.

Free access — add to your briefcase to read the full text and ask questions with AI

D. Federico Co. v. New Bedford Redevelopment Authority (In re D. Federico Co.), 25 B.R. 822, 1982 Bankr. LEXIS 5438 (D. Mass. 1982).

25 B.R. 822 (D. Federico Co. v. New Bedford Redevelopment Authority (In re D. Federico Co.)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Love v. Wiseman
N.D. California, 2020
Honey Dew Associates, Inc. v. M & K FOOD CORP.
81 F. Supp. 2d 352 (D. Rhode Island, 2000)
In Re White
88 B.R. 498 (D. Massachusetts, 1988)