Manganaro Drywall, Inc. v. Penn-Simon Construction Co.

260 N.E.2d 182, 357 Mass. 653, 1970 Mass. LEXIS 876
CourtMassachusetts Supreme Judicial Court
DecidedJune 12, 1970
StatusPublished
Cited by22 cases

This text of 260 N.E.2d 182 (Manganaro Drywall, Inc. v. Penn-Simon Construction Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Manganaro Drywall, Inc. v. Penn-Simon Construction Co., 260 N.E.2d 182, 357 Mass. 653, 1970 Mass. LEXIS 876 (Mass. 1970).

Opinion

Quirico, J.

This is an appeal from an order allowing a motion for judgment on undisputed facts under G. L. c. 231, § 59, as amended through St. 1965, c. 491, § 1.

On April 16, 1968, Manganaro Drywall, Inc. (plaintiff), and Penn-Simon Construction Company (defendant) entered into a written contract under which the plaintiff was to^'perform certain work and furnish certain materials in connection with several buildings being constructed by the defendant. Transamerica Insurance Company (surety) was the surety on a performance and payment bond given by the defendant as security for the defendant’s performance of its contract to build the buildings in question and to "pay all persons who have contracts directly with Principal [defendant] for labor or materials furnished” in the construction of such buildings.

The plaintiff completed performance of its contract by September 1, 1968, and it claimed that a balance of $81,117.36 was due it by the defendant as of that date. On January 15, 1969, the plaintiff and the defendant entered into a written agreement which first recited that the defendant requested the plaintiff to reduce its claim to $78,117.36, to grant the defendant additional time to pay that amount, to waive interest thereon, and to refrain from suing the defendant or the surety to collect the balance. The agreement then provided (a) that the agreed balance was $78,117.36; (b) that it was due and owing on September 1, 1968, for work theretofore properly performed by the plaintiff; (c) that the defendant would pay the agreed balance in instalments of $10,000 on January 20, a like instalment on the fifteenth day of each month from February through July inclusive, and a final instalment of $8,117.36 on-. August 15, 1969; (d) that the plaintiff would refrain from demanding or suing for the balance "as long as pay *655 ments are made in accordance with” the agreed instalment payment schedule; and (e) that “[i]f Penn Simon fails to make any payment to Manganaro as set forth in paragraph 2 [reciting instalment payment schedule], the agreement of Manganaro to refrain from making demand or filing suit against Penn Simon and its surety will cease and the $78,117.36 or any unpaid portion thereof, plus interest on $78,117.36 at the rate of 6% per annum from September 1, 1968, will become immediately due and payable to Manga-naro” 1 (emphasis supplied).

The defendant made payments of $10,000 each under the agreement on or about January 24, February 25, March 28 and April 25, 1969; but it failed to pay the balance of $38,117.36. On June 26, 1969, the plaintiff started an action in contract against the defendant and its surety to recover under the written agreements of April 16, 1968, and January 15, 1969. Count 1 was against the defendant, and count 3 was against the defendant and its surety. Each count sought recovery of the $38,117 total of the four unpaid instalments plus interest on the sum of $78,117 from September 1, 1968. 1 2 The defendant and its surety filed identical answers consisting of a general denial plus pleas of payment and of the statute of limitations.

Thereafter on September 10, 1969, the plaintiff filed a motion alleging that there was no genuine issue of fact but only questions of law in the action and requesting the immediate entry of judgment pursuant to G. L. c. 231, § 59. The motion was accompanied by an affidavit of the plaintiff’s president alleging the facts summarized above and further alleging that the defendant owed the plaintiff “the sum of $38,117.36, plus interest on $78,117.36, at 6% from Septem *656 ber 1, 1968,” that “[t]he interest on $78,117.36 from September 1, 1968, through August 31, 1969, is $4,687.04,” and that “[t]he daily interest rate on $78,117.36 at 6% for the period after August 31, 1969, is $13.02.”

The defendant seasonably filed an affidavit signed by its counsel objecting to the motion for judgment on the ground that the “alleged agreement between the parties hereto . . . [is] unconscionable and void as contrary to public policy” because “although . . . defendant made payments of $40,000 to the plaintiff before the alleged default on the 15th day of May, 1969 installment, plaintiff now seeks ... to recover interest on the total amount of the original indebtedness of $78,117.36 retroactive to September 1, 1968 completely ignoring in the computation the payments totaling $40,000.” The defendant’s affidavit does not contradict the facts alleged in the plaintiff's affidavit. It demonstrates clearly that the case involves “no genuine issue of material fact but only [a] question of law.” G. L. c. 231, § 59.

The only question of law thus presented to the trial court was whether the provision of the contract for retroactive interest on the entire sum of $78,117.36 in the event of the defendant’s failure to pay any instalment when due was “unconscionable and void as contrary to public policy.” The trial court decided this question against the defendant by allowing the motion for judgment as to counts 1 and 3. On the record which was before him and is now before us, the ruling was correct.

When the parties signed their compromise agreement of January 15, 1969, containing the now disputed interest provision, the defendant admittedly had owed the plaintiff $78,117.36 since September 1, 1968, and the plaintiff contended that the correct amount was $81,117.36. The plaintiff was entitled to sue the defendant and its surety therefor immediately, and it was entitled to interest from September 1, 1968, on whatever principal amount was due. The defendant sought a reduction in the amount of the claim, protection against legal proceedings, and time within *657 which to pay the principal amount due without interest. The plaintiff agreed to all of these requests in return for which the defendant agreed to pay the principal amount in eight monthly instalments. If it had made the instalment payments as agreed, it would have paid no interest to the plaintiff. But the agreement by which the plaintiff made its concessions including the waiver of interest if the principal were paid in instalments as agreed contained the further provision for interest if the defendant failed to make any instalment payment. It said in clear terms that if the defendant failed to make any instalment payment “the $78,117.36 or any unpaid portion thereof, plus interest on $78,117.36 at the rate of 6% per annum from September 1, 1968, will become immediately due and payable” to the plaintiff. This was not an unconscionable potential price to be paid by the defendant in return for the concessions made by the plaintiff. We are not dealing with any alleged fraud, overreaching, or breach of any fiduciary relationship. The defendant was engaged in the construction of buildings costing almost $5,000,000. The plaintiff performed work and furnished materials worth over $250,000 thereon. There is nothing to indicate that the disputed provision concerning interest was not negotiated on an arms-length basis between two substantial business firms. If the defendant had paid the instalments of principal as agreed, the plaintiff would not then be allowed to recover for interest by claiming that the agreement by which it waived it was unconscionable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bridge Over Troubled Waters, Inc. v. Argo Tea, Inc.
220 F. Supp. 3d 213 (D. Massachusetts, 2016)
NPS, LLC v. Minihane
886 N.E.2d 670 (Massachusetts Supreme Judicial Court, 2008)
Blue Hills Office Park LLC v. J.P. Morgan Chase Bank
477 F. Supp. 2d 366 (D. Massachusetts, 2007)
Clean Harbors, Inc. v. John Hancock Life Insurance
833 N.E.2d 611 (Massachusetts Appeals Court, 2005)
Eastern Products Corp. v. Continental Casualty Co.
787 N.E.2d 1089 (Massachusetts Appeals Court, 2003)
GTE Products Corp. v. Broadway Electrical Supply Co.
676 N.E.2d 1151 (Massachusetts Appeals Court, 1997)
Ogden Haverhill Associates v. Waste Management
4 Mass. L. Rptr. 445 (Massachusetts Superior Court, 1995)
Graves Equipment, Inc. v. M. DeMatteo Construction Co.
489 N.E.2d 1010 (Massachusetts Supreme Judicial Court, 1986)
Lynch v. Andrew
481 N.E.2d 1381 (Massachusetts Appeals Court, 1985)
Stilian v. GTC Corp.
457 N.E.2d 677 (Massachusetts Appeals Court, 1983)
Weinstein v. Steigman
1983 Mass. App. Div. 288 (Mass. Dist. Ct., App. Div., 1983)
Roberts v. Grise
3 Mass. Supp. 201 (Massachusetts District Court, 1982)
Roberts v. Grise
1982 Mass. App. Div. 17 (Mass. Dist. Ct., App. Div., 1982)
Ro-Bar Realty, Inc. v. Warren Five Cents Savings Bank
1981 Mass. App. Div. 181 (Mass. Dist. Ct., App. Div., 1981)
Begelfer v. Najarian
409 N.E.2d 167 (Massachusetts Supreme Judicial Court, 1980)
Renda v. Goughberg
343 N.E.2d 159 (Massachusetts Appeals Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
260 N.E.2d 182, 357 Mass. 653, 1970 Mass. LEXIS 876, Counsel Stack Legal Research, https://law.counselstack.com/opinion/manganaro-drywall-inc-v-penn-simon-construction-co-mass-1970.