Stag Industrial Holdings, LLC v. Black Swan Holdings, LLC.

Massachusetts Appeals Court·Decided January 31, 2024·No. 22-P-1078·Unpublished

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

22-P-1078

STAG INDUSTRIAL HOLDINGS, LLC

vs.

BLACK SWAN HOLDINGS, LLC.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

The defendant, Black Swan Holdings, LLC (Black Swan),

appeals from a Superior Court judgment awarding the plaintiff,

Stag Industrial Holdings, LLC (Stag Industrial), damages in an

action on a guaranty executed by Black Swan. Black Swan

disputes the award of liquidated damages and the award of

posttermination damages stemming from a tenant's obligations

under a lease. We affirm.

Background. Stag Industrial, here the commercial landlord,

brought this action in the Superior Court against Black Swan to

enforce an unconditional guaranty by Black Swan of the

obligations of RADG Holdings, LLC (RADG), the tenant under a

commercial lease of premises 1 in Gaffney, South Carolina

1 The leased premises included a parcel of land and a large warehouse of about 227,000 square feet.

(premises). RADG stopped paying the rent due under the lease in July 2020. Stag Industrial then sued RADG in South Carolina to recover past-due rent and unpaid taxes.

On March 21, 2021, a default judgment entered against RADG in the South Carolina action in an amount equal to the unpaid rent through March 2021 and unpaid property taxes for 2020. Stag Industrial then terminated RADG's lease on March 25, 2021. On April 20, 2021, Stag Industrial filed a complaint in the Suffolk Superior Court against Black Swan, pursuant to the guaranty. 2 On June 23, 2021, Black Swan was defaulted. It is undisputed that Black Swan was properly served, did not answer the complaint, and did not attempt to remove the default or contest liability. Instead, Black Swan's sole challenge was to the damages claimed by Stag Industrial.

While Stag Industrial terminated RADG's lease in March 2021, RADG did not vacate the premises until November 2021. Due to deferred maintenance and damage, Stag Industrial had to make extensive repairs to the premises, at a significant cost, to be able to market and relet the premises to another potential tenant.

2 Stag Industrial is a Massachusetts limited liability company with its principal place of business in Boston. The guaranty states that the "Guarantor [Black Swan] consents to and agrees that the courts of The Commonwealth of Massachusetts shall have personal jurisdiction over the Guarantor for any action brought on this Guaranty."

On March 9, 2022, Stag Industrial elected to invoke the liquidated damages remedy under sections 9.2(c)(i) and (iii) of the lease. 3 This provision required RADG's payment of "all sums provided for in th[e] Lease" plus "an amount equal to the sum of all of the Rent and other sums due hereunder and payable with respect to the twelve . . . month period next following the date of termination." 4

3 The liquidated damages clause of the lease stated in relevant part:

"If this Lease is terminated due to an Event of Default, then Tenant covenants, as an additional cumulative obligation after termination, to pay forthwith to Landlord at Landlord's election made by notice to Tenant at any time after termination, as liquidated damages a single lump sum payment equal to the sum of (i) all sums provided for in this Lease to be paid by Tenant and not then paid at the time of such election, plus either (ii) the present value . . . of the excess of all of the Rent reserved for the residue of the Term over all of the fair market rent reasonably projected by Landlord to be received on account of the Premises during such period, which Rent from reletting shall be reduced by reasonable projections of vacancies and by Landlord's Reletting Expenses described above to the extent not theretofore paid to Landlord, or (iii) an amount equal to the sum of all of the Rent and other sums due hereunder and payable with respect to the twelve . . . month period next following the date of termination. Because Landlord's damages resulting from Tenant's default and subsequent termination are difficult to ascertain as of the Date of this Lease, the parties agree that the foregoing agreed-to sum represents a reasonable forecast of Landlord's expected damages as a result of Tenant's breach and early termination."

4 At oral argument, counsel for Stag Industrial confirmed that the twelve-month period ran from March 25, 2021, to March 24, 2022. Black Swan does not contest this time frame.

On May 24, 2022, and June 2, 2022, a Superior Court judge held an evidentiary hearing on Stag Industrial's request for an assessment of damages. 5 As noted supra, Black Swan did not challenge the default or otherwise raise any liability defenses under its guaranty. 6 Accordingly, the judge found that Black Swan, by virtue of the default, was "liable under the Unconditional Guaranty to pay all of RADG's obligations under or related to the Lease, including past due rent, other monies due under the Lease due to RADG's default, liquidated damages, and [Stag Industrial's] reasonable attorneys' fees and litigation expenses."

The judge determined that Stag Industrial was entitled to recover the sum awarded in the South Carolina action in the amount of $578,793.75 plus interest. 7 He also found that Stag Industrial was entitled to the cost of removing debris and refuse left inside the premises by RADG, which amounted to $149,700. Furthermore, the judge found that RADG failed to make

5 For a period of "more than six months," Stag Industrial moved for extensions of time to file its motion for an assessment of damages. 6 The Superior Court judge did not make any factual findings regarding Black Swan's liability under the guaranty. See Marshall v. Stratus Pharms., Inc., 51 Mass. App. Ct. 667, 670- 671 (2001) ("Upon default . . . the factual allegations of a complaint are accepted as true for purposes of establishing liability" [citation omitted]). 7 This sum is equal to the unpaid rent through March 2021 and unpaid property taxes for 2020 and bears interest from the date of judgment at a rate of 7.25 percent per year.

repairs 8 to the premises as required under the lease 9 and, therefore, Stag Industrial was entitled to the costs of maintenance and repair work, recoverable under the lease and the unconditional guaranty, in the amount of $554,990.46. Finally, the judge found that between April 2021 and March 2022, RADG failed to pay rent totaling $656,718.72, utility costs totaling $76,952.81, and property taxes totaling $127,435. The lease called for a late fee of 5 percent and interest of 1.5 percent per month on all rent and additional rent, which totaled $43,055.33 and $63,321.59, respectively.

In finding that Stag Industrial was entitled to damages pursuant to the lease's liquidated damages remedy, the judge found that Stag Industrial acted within a reasonable timeframe in making its election of the remedy. 10 More importantly, he found that the liquidated damages clause was reasonable and did not constitute a penalty. 11 The judge found this amount to total $656,718.72.

Free access — add to your briefcase to read the full text and ask questions with AI

Stag Industrial Holdings, LLC v. Black Swan Holdings, LLC., (Mass. Ct. App. 2024).

Stag Industrial Holdings, LLC v. Black Swan Holdings, LLC. (Stag Industrial Holdings, LLC v. Black Swan Holdings, LLC.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Manganaro Drywall, Inc. v. Penn-Simon Construction Co.
260 N.E.2d 182 (Massachusetts Supreme Judicial Court, 1970)
American Mechanical Corp. v. Union MacHine Co. of Lynn, Inc.
485 N.E.2d 680 (Massachusetts Appeals Court, 1985)
Kendall v. Selvaggio
602 N.E.2d 206 (Massachusetts Supreme Judicial Court, 1992)
McCone v. New England Telephone & Telegraph Co.
471 N.E.2d 47 (Massachusetts Supreme Judicial Court, 1984)
Balles v. Babcock Power Inc.
70 N.E.3d 905 (Massachusetts Supreme Judicial Court, 2017)
Fabre v. Walton
802 N.E.2d 1030 (Massachusetts Supreme Judicial Court, 2004)
TAL Financial Corp. v. CSC Consulting, Inc.
844 N.E.2d 1085 (Massachusetts Supreme Judicial Court, 2006)
NPS, LLC v. Minihane
886 N.E.2d 670 (Massachusetts Supreme Judicial Court, 2008)
Marshall v. Stratus Pharmaceuticals, Inc.
749 N.E.2d 698 (Massachusetts Appeals Court, 2001)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)