Thomas O'Connor & Co. v. City of Medford

448 N.E.2d 1276, 16 Mass. App. Ct. 10, 40 A.L.R. 4th 988, 1983 Mass. App. LEXIS 1332
CourtMassachusetts Appeals Court
DecidedMay 13, 1983
StatusPublished
Cited by19 cases

This text of 448 N.E.2d 1276 (Thomas O'Connor & Co. v. City of Medford) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas O'Connor & Co. v. City of Medford, 448 N.E.2d 1276, 16 Mass. App. Ct. 10, 40 A.L.R. 4th 988, 1983 Mass. App. LEXIS 1332 (Mass. Ct. App. 1983).

Opinion

Dreben, J.

In 1967, the plaintiff, a general contractor, entered into a contract with the city of Medford (city) for the construction of a high school. The project took longer than anticipated, and the plaintiff claimed that deficiencies in the plans and other actions by the city disrupted the plaintiff s construction schedule, thereby causing the plaintiff substantial additional costs. The city urges several grounds for reversal of a judgment, based in large part on the findings of a master, awarding $1,658,317.36 in damages to the plaintiff.

The most significant issue raised by the city is the claim that damages may not be awarded in excess of the amount appropriated for the contract under G. L. c. 44, § 31. We hold that the statute does not apply to this action and that, with the exception of an item of damages relating to the plaintiff s profits, the judgment is to be affirmed.

1. Applicability of G. L.c. 44, § 31. Pointing to the fact that the damage award, when added to previous payments to the contractor, was in excess of the sums appropriated *12 for the entire project, the city argues that the plaintiff’s claim is barred. The following language of c. 44, § 31, as appearing in St. 1946, c. 358, § 23, is relied upon: “No department financed by municipal revenue, or in whole or in part by taxation, of any city or town, except Boston, shall incur a liability in excess of the appropriation made for the use of such department, each item recommended by the mayor and voted by the council in cities . . . being considered as a separate appropriation ...” (emphasis supplied).

The question here is whether an award of damages against the city for a breach of contract is a “liability incur[red]” within the meaning of the statute. We have found no Massachusetts authority dealing directly with this question. In two cases alluding to the problem, a Federal court and this court indicated some doubt as to whether appropriation statutes would apply to an award for a breach of contract or to a compromise of an alleged breach. See County of Middlesex v. Gevyn Constr. Corp., 450 F.2d 53, 54-55 (1st Cir. 1971), cert. denied, 405 U.S. 955 (1972) (discussing G. L. c. 34, § 14 and c. 35, § 32); Northgate Constr. Corp. v. Fall River, 12 Mass. App. Ct. 859, 861 (1981) (discussing G. L. c. 44, § 31C).

Other cases construing § 31 (and a similar statute applying to the city of Boston) make clear that its “purpose ... is to provide central municipal control over irresponsible municipal spending,” Lawrence v. Falzarano, 380 Mass. 18, 24 (1980), and to “limit the powers of public officials in making contracts,” Dyer v. Boston, 272 Mass. 265, 274 (1930). A contractor with a municipality is bound by these limitations and must make his contracts with reference thereto. Ibid. Lawrence v. Falzarano, supra at 24, and cases cited. The statute applies to additional work under a contract, and it is not enough that the initial contract meets the statutory requirements. Dyer v. Boston, supra at 274. Duff v. Southbridge, 325 Mass. 224, 227-229 (1950). See also G. L. c. 44, § 31C (certification that there is an appropriation applies not only to contracts but also to changes in or addition to the work to be performed under a contract). *13 A contractor may proceed no further than the work “covered by an appropriation.” Arthur R. Murphy, A.I.A., & Associates v. Brockton, 364 Mass. 377, 380 (1973). Marlborough v. Cybulski, Ohnemus & Associates, 370 Mass. 157, 160 (1976).

There is, however, a distinction between claims under a contract and damages for a wrongful breach of that contract. While the contractor on a public construction contract must follow the procedures spelled out in the contract and cannot by labeling his claims a breach of contract unilaterally accrue expenses, Glynn v. Gloucester, 9 Mass. App. Ct. 454, 460 (1980), some claims do fall outside the contract, and because of the municipality’s conduct constitute a “true breach.” Id. at 461. United States v. Utah Constr. & Mining Co., 384 U.S. 394, 404-405, 412-413 (1966). Where that occurs, we do not think the term “incur a liability” was intended to shield a municipality from liability for its wrongful actions. Cf. Dealtry v. Selectmen of Watertown, 279 Mass. 22, 28 (1932) (construing G. L. c. 40, § 53).

Once the conditions of G. L. c. 44, § 31, and other statutes relating to municipal contracts have in good faith been met and complied with, we think the “well settled” rule “that a city which is a party to a contract may be held liable to respond in damages,” Lawrence v. Falzarano, 380 Mass. at 28, should apply. General Laws c. 44, § 31, relates to municipal finance and is not, we think, intended to extend the doctrine of municipal immunity so as to leave contractors entirely without remedy for breach of contract in the absence of an appropriation. 1

*14 The few authorities that we have found elsewhere which address statutory and constitutional appropriation and revenue provisions lend support to our conclusion. See, e.g., Houston v. United Compost Serv. Inc., 477 S.W.2d 349, 356 (Tex. Civ. App. 1972) (constitutional requirement that no debt be created without provision for a tax therefor applies to an obligation imposed by contract but not to one imposed by law for breach of a valid contract); DeKalb County v. Georgia Paperstock Co., 226 Ga. 369, 371 (1970) (obligation for breach of contract not “debt” within meaning of constitutional provision); Bates & Rogers Constr. Co. v. Board of Commrs., 274 F. 659, 663-665 (N.D. Ohio 1920) (statutes requiring preliminary estimates and certification of funds not applicable to actions for breach of contract); Spitcaufsky v. State Highway Commn., 349 Mo. 117, 122-127 (1941) (constitutional and statutory requirements for municipal contracts do not protect commission from breach of its own valid contract). But see Lindekugel & Sons v. S.D. St. Highway Commn., 87 S.D. 32, 35, 39 (1972), where under a constitutional provision that “[n]o indebtedness shall be incurred . . . and no warrant shall be drawn . . . except in pursuance of an appropriation for the specific purpose first made” (emphasis supplied), an action for breach of contract was dismissed because there was no appropriation for such a claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth v. Douglas
86 Mass. App. Ct. 404 (Massachusetts Appeals Court, 2014)
City of Lynn v. Lynn Police Ass'n
899 N.E.2d 106 (Massachusetts Appeals Court, 2009)
Southbridge Associates II, LLC v. Town of Southbridge
21 Mass. L. Rptr. 31 (Massachusetts Superior Court, 2006)
J.C. Higgins Co. v. Bond Bros.
791 N.E.2d 367 (Massachusetts Appeals Court, 2003)
Perseus of N.E., MA, Inc. v. Commonwealth
706 N.E.2d 681 (Massachusetts Supreme Judicial Court, 1999)
Govoni v. Town of Acushnet
5 Mass. L. Rptr. 120 (Massachusetts Superior Court, 1995)
Sutton Corp. v. Metropolitan District Commission
652 N.E.2d 627 (Massachusetts Appeals Court, 1995)
Reynolds Bros. v. Town of Norwood
414 Mass. 295 (Massachusetts Supreme Judicial Court, 1993)
Village of Chefornak v. Hooper Bay Construction Co.
758 P.2d 1266 (Alaska Supreme Court, 1988)
Gardner v. City of Peabody
499 N.E.2d 1220 (Massachusetts Appeals Court, 1986)
Datacomm Interface, Inc. v. Computerworld, Inc.
489 N.E.2d 185 (Massachusetts Supreme Judicial Court, 1986)
DataComm Interface v. COMPUTERWORLD, INC. ADELSON
489 N.E.2d 185 (Massachusetts Supreme Judicial Court, 1986)
Glynn v. City of Gloucester
487 N.E.2d 230 (Massachusetts Appeals Court, 1986)
Joseph E. Bennett Co. v. Commonwealth
486 N.E.2d 1145 (Massachusetts Appeals Court, 1985)
Thomas O'Connor & Co. v. City of Medford
482 N.E.2d 877 (Massachusetts Appeals Court, 1985)
Pitts v. Halifax Country Club, Inc.
476 N.E.2d 222 (Massachusetts Appeals Court, 1985)
City of Worcester v. Granger Bros.
474 N.E.2d 1151 (Massachusetts Appeals Court, 1985)
Disposal v. City of Revere
1983 Mass. App. Div. 245 (Mass. Dist. Ct., App. Div., 1983)

Cite This Page — Counsel Stack

Bluebook (online)
448 N.E.2d 1276, 16 Mass. App. Ct. 10, 40 A.L.R. 4th 988, 1983 Mass. App. LEXIS 1332, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-oconnor-co-v-city-of-medford-massappct-1983.