City of Houston v. United Compost Services, Inc.

477 S.W.2d 349, 3 ERC 1774, 3 ERC (BNA) 1774, 1972 Tex. App. LEXIS 2706
CourtCourt of Appeals of Texas
DecidedFebruary 10, 1972
Docket15791
StatusPublished
Cited by8 cases

This text of 477 S.W.2d 349 (City of Houston v. United Compost Services, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Houston v. United Compost Services, Inc., 477 S.W.2d 349, 3 ERC 1774, 3 ERC (BNA) 1774, 1972 Tex. App. LEXIS 2706 (Tex. Ct. App. 1972).

Opinion

BELL, Chief Justice.

Appeal from a judgment in favor of ap-pellee by which it recovered from appellant the sum of $2,093,669.95 as damages growing out of the breach by appellant of a contract with appellee under which appel-lee agreed to construct and operate a garbage composting plant. The case was submitted to the jury on three theories of recovery. The first theory was breach of a valid contract by appellant, and the second, and alternative, theory was a contract implied in law. The third asserted estoppel to deny the validity of the contract. The jury’s answers to all controlling fact issues submitted were answered favorably to ap-pellee.

Appellant assigns twenty-five points of error. They deal with, in the aggregate, all theories of recovery. We will discuss only those relating to recovery on the theory of breach of contract because we have reached the conclusion that the judgment is supported on a basis of the breach of a valid contract by appellant.

On June 3, 1964, the City Council finally passed an ordinance calling a special election to be held June 27, 1964, at' which a proposition concerning a proposed ordinance authorizing a contract for disposal of garbage by composting or other effective methods for a period of not to exceed twenty years would be submitted to the qualified voters.

The preamble to the ordinance, which was expressly made a part of the ordinance, recited that the principal terms of the contract would be as follows:

1. It would be for a term not to exceed 20 years.

2. The contractor would be unconditionally obligated to receive a stated minimum of garbage each day, or at other agreed times, and to dispose of same by composting or by some other agreed method found to be effective, and the City would be obligated to make such garbage available at an agreed location or locations.

3. The City would make no capital investment in the facilities to be utilized by the contractor.

4. The City would pay the contractor a fixed agreed price per ton for each ton disposed of in accordance with the contract.

5. The contractor would be required to furnish a performance bond to be approved by the City Council in an amount found by the City Council to be sufficient to indemnify the City for any failure of the contractor to perform satisfactorily.

The ordinance then provided the following proposition should be submitted:

“Shall the City Council of the City of Houston adopt the proposed ordinance authorizing the negotiation of a contract for the disposal of garbage by composting or other effective method for a term not to exceed twenty years ?”

The ordinance designated the locations of the polling places and the person who should be the judge at each place.

It is provided that the ordinance would constitute the election order and the City Secretary was directed to post a copy at each polling place and at the City Hall for not less than 20 days before the election and to cause same to be published on the same day in each of two consecutive weeks in a newspaper of general circulation that had been regularly published in Houston for one year before the date of the ordinance, the first publication to be not less than fourteen days prior to the date of the election.

*352 It is undisputed that the directions immediately above noted with regard to the posting and publication of the ordinance were fully carried out. Publication was in both the Houston Post and Houston Chronicle. In addition a proclamation of the Mayor calling the election and reciting the proposition above quoted, which had been authorized by the ordinance, though not required, was published in the above named newspapers. Voting machines were to be used in holding the election.

Following the election which approved the proposition submitted the City officials negotiated a contract with appellee that was executed March 24, 1965, after having first advertised for bids. The contract was then ratified by the City Council by ordinance. The contract obligated appellee to construct the plant and facilities at its own expense. The plant was to be capable of composting from 300 to 330 tons of garbage per day through employment of the aerobic process. The plant was to be operated in a nuisance-free manner. The City was to pay monthly a specified fee per ton for garbage composted and was to deliver or pay for a minimum tonnage of 1800 tons per week. The plant was to be completed within 12 months following the approval of plans and specifications. The plans and specifications were approved by ordinance August 24, 1965. Failure to complete within said period would subject appellee to a daily penalty of $100 per day. The City claimed a delay of 82 days and exacted a penalty of $8200. It seems not to be contested that the plant was substantially completed in March 1967, so that “shakedown” operations provided for in the contract could and did begin. The operations contemplated that as soon as the plant was “substantially” completed the City, on request of the contractor, would deliver on not less than 24 hours’ notice any tonnage of garbage and residential trash the contractor desired to be used for the purpose of testing the equipment and for a “shakedown” of the plant. After the shakedown had been satisfactorily completed the contractor was to notify the City and request a “Test Run” program. During the test run period between 300 and 330 tons of garbage and trash were to be delivered by the City each day for six consecutive business days and such refuse was to be completely processed in full compliance with the contract. The contract provided that “if the contractor shall not successfully complete said test run within 6 months after the scheduled completion date, this contract may be terminated by the City, at its option, at any time thereafter.”

Shakedown operations began in early 1967. In March 1967 an attempt to complete a test run -was unsuccessful. A second test run was made during April 19-27, 1967. On April 27, appellee wrote the Director of Public Works that the test run had been successful. On April 28 the Director of Public Works wrote appellee a letter stating the “recently completed test run was not successfully completed in accordance with the terms of the contract.” The portions of the contract which allegedly had not been complied with dealt generally with the obligation of appellee to operate a nuisance-free plant and not violate any valid law. We do not notice the details of the provision because the City is really contending that the plant emitted odors that penetrated the area outside of the plant and were so extensive as to constitute a nuisance. The letter also stated since appellee had stated the last test run was successful, the City intended “that day” to file a declaratory judgment suit to ascertain the rights of the parties. The suit was filed on April 28, 1967. On April 28, appellee wrote the Mayor stating it had learned through the news media of the unilateral action of the City in refusing to deliver garbage pending judicial determination of the rights of the parties. The letter, while asserting that appellee claimed a successful test run had been made and the contract was in full force and effect, stated that without waiving any claims appel-lee was thereby notifying the City of completion of shakedown runs and requested the City to fix a test run program. De

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scown v. City of Alpine
271 S.W.3d 380 (Court of Appeals of Texas, 2008)
Emily Grace Scown v. the City of Alpine, Texas
Court of Appeals of Texas, 2008
Perseus of N.E., MA, Inc. v. Commonwealth
706 N.E.2d 681 (Massachusetts Supreme Judicial Court, 1999)
Village of Chefornak v. Hooper Bay Construction Co.
758 P.2d 1266 (Alaska Supreme Court, 1988)
Thomas O'Connor & Co. v. City of Medford
448 N.E.2d 1276 (Massachusetts Appeals Court, 1983)
Triton Oil & Gas Corporation v. EW Moran Drilling Co.
509 S.W.2d 678 (Court of Appeals of Texas, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
477 S.W.2d 349, 3 ERC 1774, 3 ERC (BNA) 1774, 1972 Tex. App. LEXIS 2706, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-houston-v-united-compost-services-inc-texapp-1972.