Roby Industries, Inc. v. Maxwell Electronics Corp.

409 S.W.2d 559, 1966 Tex. App. LEXIS 2259
CourtCourt of Appeals of Texas
DecidedNovember 4, 1966
Docket16798
StatusPublished
Cited by12 cases

This text of 409 S.W.2d 559 (Roby Industries, Inc. v. Maxwell Electronics Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roby Industries, Inc. v. Maxwell Electronics Corp., 409 S.W.2d 559, 1966 Tex. App. LEXIS 2259 (Tex. Ct. App. 1966).

Opinion

BATEMAN, Justice.

This suit was brought by Roby Industries, Inc., doing business as Intercontinental Plastics Manufacturing Company, against Maxwell Electronics Corporation for debt. As both parties appeal from the judgment rendered, we shall for convenience refer to them in this opinion as “Roby” and “Maxwell”.

Maxwell had contracted to furnish to the Federal Aviation Agency a quantity of electronic devices known as “transceivers” and also as “walkie-talkies”, each of which was a compact radio transmitter and receiver. Maxwell was equipped to manufacture the electronic equipment included in the device, but not the plastic case enclosing it. It made a written subcontract with Roby by which the latter agreed to manufacture a mold for the making of the plastic cases, and also to furnish the necessary quantity of cases therefrom. Item 1 of the subcontract obligated Roby to furnish 1500 of the plastic cases, according to a certain delivery schedule, at an agreed price of $.696 each, or a total of $1,044, which was subsequently enlarged by agreement to 1700 cases at a total price of $1,183.20. Item 2 obligated Roby to furnish the mold or “tooling” for the cases by May 15, 1963, for an agreed price of $9,625, later increased by agreement to $10,124.50. The subcontract further provided that time was of the essence as to all provisions thereof, and that in the event of deliveries after the scheduled delivery dates the prices of all items shall be reduced by one per cent for each calendar day of delay.

The subcontract also provided that Roby had the sole responsibility of designing the cases to the complete satisfaction of Maxwell, and that Roby would submit to Maxwell for approval all drawings, sketches and proposed specifications thereof. It further provided: “Seven days shall be allowed for such submission and approval in order to insure delivery of order on time. Should disapproval of submission delay final acceptance of prints and specifications within seven days, the delivery date of May 15 shall be extended by an equal amount of calendar days beyond the seven days originally specified, without penalty.” Also that if Maxwell’s inspection of a sample of material furnished to it disclosed defects in excess of a certain allowable percentage the entire lot may be rejected and returned to Roby “or 100% screened by Purchaser with cost of screening billed to the Seller.”

Roby sued on three alternative causes of action: (1) on sworn account in the sum of $33,920.34 plus a reasonable attorney’s fee of $7,500 under Vernon’s Ann. Civ.St. Art. 2226; (2) on quantum meruit in the sum of $33,920.34; and (3) on the written contract mentioned above Roby did not sue for attorney’s fee under Art. 2226 in connection with either its second or third alternative cause of action.

Maxwell, alleging that the mold and plastic cases were defective and delivered later than the time specified, invoked the provision of the contract for liquidated damages for the late delivery; also for its costs and expenses in connection with its inspection and screening of defective material furnished by Roby.

*561 It is not necessary for us to summarize all of the jury findings. The following are the material findings: (1) Roby substantially complied with the contract; but (2) was the cause of the delay in the manufacture and delivery of the plastic cases; (3) the written contract was not abandoned by the parties; (5) Roby did not deliver the plastic cases to Maxwell within a reasonable time, but (6) they were manufactured substantially according to the plans and specifications agreed upon, and (7) were reasonably suitable for the purposes for which they were manufactured; (8) $14,265 would reasonably and fairly compensate Roby for the material and services rendered to Maxwell for the mold and the cases; (9) $3,750 would reasonably compensate Roby for the services rendered to it in connection with the suit by its attorneys; (10-A) Maxwell approved or disapproved any submitted drawing of any perspective or piece part within seven days after the date of submission thereof; (12-A) Maxwell did not make or require any tooling changes after approval of the final drawings which caused Roby any delay in finishing the tooling; (18) Roby delivered the plastic cases fifty-two days in excess of the eight-week delivery schedule agreed upon; (21) defects in piece parts received by Maxwell from Roby exceeded the allowable percentage as prescribed in the contract; (21-A) Maxwell screened the piece parts delivered to it by Roby, and (21-B) expended $225 in doing so.

Contending that it appeared from the evidence without controversy that the completion of the mold under Item 2 of the subcontract was ninety days late, and the jury having found that there was a delay of fifty-two days in the delivery of the plastic cases, Maxwell moved that the court render judgment for Roby for $1,355.39, arrived at as follows:

Plastic cases, per amended contract.$ 1,183.20
Less 52 days delay at 1%. 615.26 Net due for cases .$ 567.94
Mold, per amended contract . 10,124.50
Less 90 days delay at 1%........ 9,112.05 Net due for mold. 1,012.45
$ 1,580.39
Less Maxwell’s screening expense. 225.00
$ 1,355.39

The trial court sustained this motion but added the $3,750 found by the jury to have been a reasonable attorney’s fee, making the total judgment $5,105.39.

Roby claims on appeal that the judgment is for an inadequate amount, and Maxwell claims on appeal that the judgment should not have included any attorney’s fee.

Roby’s first point of error on appeal is in reality two points. . In the first part thereof Roby contends that it was entitled to judgment for the $14,265 found by the jury in answer to Special Issue No. 8 as being the fair and reasonable value of the material and services rendered and furnished by it to Maxwell, plus the attorney’s fee of $3,750 found by the jury in answer to Special Issue No. 9, or a total of $18,015.

Of course, Roby had the right to sue on the three alternative causes of action. It has been said to be good practice to do so. Musick v. Pogue, Tex.Civ.App., 330 S.W.2d 696, 698. wr. ref. n. r. e. However, in that same case, where the evidence showed that there was an express contract between the parties, it was held that neither *562 party could shut his eyes to the terms thereof and claim under an implied contract a larger amount than he had agreed in his express contract to accept. Under such circumstances an implied contract cannot coexist with the express contract. See the authorities cited in Musick v. Pogue, supra, 330 S.W.2d at page 699; also Neblett v. McGraw & Brewer, 41 Tex.Civ.App. 239, 91 S.W. 309, no wr. hist., and 13 Tex.Jur.2d, Contracts, § 7, pp. 119-120. The jury found, in answer to Special Issue No. 3, that the written contract had not been abandoned. Therefore, we think the court properly disregarded the finding of $14,265 in response to Special Issue No. 8, which was obviously based on the alternative plea for quantum meruit. The first part of the first point of error is accordingly overruled.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rent to Own, LLC v. CR-FED Leasing, LLC
Court of Appeals of Texas, 2024
Bellair, Inc. v. Aviall of Texas, Inc.
819 S.W.2d 895 (Court of Appeals of Texas, 1991)
Lone Star Gas Co. v. Howard Corp.
556 S.W.2d 372 (Court of Appeals of Texas, 1977)
M. C. Winters, Inc. v. Cope
498 S.W.2d 484 (Court of Appeals of Texas, 1973)
City of Houston v. United Compost Services, Inc.
477 S.W.2d 349 (Court of Appeals of Texas, 1972)
Coon v. Schoeneman
476 S.W.2d 439 (Court of Appeals of Texas, 1972)
Electric Wire & Cable Co. v. Ray
456 S.W.2d 260 (Court of Appeals of Texas, 1970)
Eisenbeck v. Buttgen
450 S.W.2d 696 (Court of Appeals of Texas, 1970)
French v. Joseph E. Seagram & Sons, Inc.
439 S.W.2d 448 (Court of Appeals of Texas, 1969)
Woods v. Rustay, Martin
430 S.W.2d 543 (Court of Appeals of Texas, 1968)
Pigg v. International Hospitals, Inc.
421 S.W.2d 169 (Court of Appeals of Texas, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
409 S.W.2d 559, 1966 Tex. App. LEXIS 2259, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roby-industries-inc-v-maxwell-electronics-corp-texapp-1966.