Ford Motor Company v. DAVIS BROTHERS. INC.

369 S.W.2d 664, 1963 Tex. App. LEXIS 2176
CourtCourt of Appeals of Texas
DecidedJune 28, 1963
Docket3802
StatusPublished
Cited by15 cases

This text of 369 S.W.2d 664 (Ford Motor Company v. DAVIS BROTHERS. INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ford Motor Company v. DAVIS BROTHERS. INC., 369 S.W.2d 664, 1963 Tex. App. LEXIS 2176 (Tex. Ct. App. 1963).

Opinion

COLLINGS, Justice.

Davis Brothers, Inc., brought this suit against Ford Motor Company. Plaintiff alleged that it had a contract with defendant to do certain painting work for an agreed price of $27,000.00; that after plaintiff made preparations to do the entire job and had completed a portion of the work, the parties entered into a new agreement whereby plaintiff agreed to a termination of the original painting contract in consideration of which defendant agreed to pay plaintiff its cost incurred thereon and its anticipated profits; that defendant failed and refused to pay as agreed. Plaintiff asserted that by reason of the facts alleged it was entitled to recover upon its sworn account and for *666 reasonable attorney’s fees pursuant to Art. 2226, Vernon’s Ann.Tex.Civ.St. or, in the alternative, the reasonable value of the services performed and labor and material furnished on the basis of quantum meruit.

The case was tried before a jury which found (1) that appellant’s employees agreed to pay plaintiff for the work done and expense incurred in connection with the paint job in consideration of plaintiff surrendering his rights under the original contract; (3) that appellant’s employees had apparent authority to make such agreement; (4) that $3,000.00 would reasonably and fairly compensate plaintiff for services performed and expense incurred in connection with the paint job up to the time of making the agreement, and (6) that $900.00 would be reasonable as attorney’s fees for services rendered by plaintiff’s attorney. Judgment was entered for plaintiff against the defendant on the verdict in the sum of $3,900.00. Ford Motor Company has appealed.

Appellant, Ford Motor Company, urges points contending that there was no evidence to support the submission of special issue No. 1 or the answer of the jury thereto; that the court erred in overruling appellant’s motion for an instructed verdict; that the answer to special issue No. 1 was against the great weight and preponderance of the evidence, and that the court erred in submitting special issue No. 1 because it did not restrict the jury’s consideration to a purported agreement with any particular employee but left the jury free to speculate. These points are overruled.

Appellee, Davis Brothers, Inc., is a paint contracting firm and it is undisputed that it entered into a contract with Ford Motor Company to do certain painting at its Dallas Assembly Plant. The contract contemplated some spray painting. It was shown that appellee began making arrangements for equipment, workmen and materials to do the job, including a special kind and texture of paint, drop cloths, the purchase of spraying equipment and the renting of scaffolding and other extra equipment. Appellee started the job and its employees worked one night spray painting the portion of appellant’s plant used as its Lincoln car garage. After the nights-work it was apparent that there had been a considerable amount of paint “fall out”'- and Mr. Guard of appellant’s Dallas plant contacted Mr. J. C. Davis, President of appellee company, and complained. He-requested Davis to visit the premises and' discuss the matter, and a discussion ensued between Mr. Davis for appellee and Mr. Guard, Mr. James F. Black, appellant’s-General Plant Engineer and Mr. Parker Howe, the Plant Engineer for Ford Motor Company. Davis admitted that there was-a considerable amount of paint “fall out”' and that it was one of the worst messes he had seen in a long time. He further testified, however, that the excessive paint fall out resulted because the spray guns-were new and not properly adjusted; that he advised appellant’s representatives that upon proper adjustment there would be no-reoccurrence of such fall out; that the spray guns were thereafter adjusted and successfully used on other jobs without excessive paint fall out; that the fall out was not of such a nature that it could not be cleaned up so that the final result would be a good and workmanlike job; that in fact appellee did satisfactorilly clean up the paint from appellant’s floor by washing it with naptha or benzene. Davis testified that he had not been unduly worried about what happened; that he informed appellant’s representatives that he would like to go ahead with the job; that he had been doing work like that for thirty years and occasionally somebody would get a gun out of adjustment but that such a situation could be remedied; that what happened was an accident and there was never any reason to be greatly concerned. Davis testified that he told appellant’s employees that the job could go ahead and be completed on time. Davis further testified that appellant’s representatives wouldn’t listen to him; that they wanted him to *667 cease work and insistently requested that the contract he discontinued. In this connection appellant’s employee and representative, Howe, stated that Ford would not permit Davis to continue the spraying. Davis testified that because of the request of appellant’s representative Black that no more work be done on the contract, he, Davis agreed to give up the job if he were paid for all the expenses he had been out and the work that he had done up to that time; that Black agreed that he would pay appellee all such expenses and for such work and that Davis agreed to surrender the right of appellee to continue under the contract. Davis testified that Black instructed him to make out a bill and go to Mr. Fitz, who was appellant’s treasurer or comptroller at the plant, and said: “We will send you a check”; that as he understood it the bill to be prepared was to cover the amount of work he had done plus the expenses incurred in starting the job; that the bill prepared by him included items of $750.00 and $225.00 which represented the labor and material for the work done; that other items were for expense incurred. Davis testified that he relied on Black’s statement and took his equipment off of the job; that he then submitted his bill to Fitz as agreed but that appellant failed and refused to pay.

Appellant admits that the parties negotiated concerning a discontinuation of the painting contract and that appellee did leave the job, but contend that the negotiations did not result in the new contract claimed and relied upon by appellee; that there is no evidence that such a contract was entered into. As basis of, and authority for, its position appellant relies upon the principle of law set out in Restatement of the Law of Contracts, Section 32, that:

“An offer must be so definite in its terms, or require such definite terms in acceptance, that the promises and performances to be rendered by each party are to be reasonably certain.”

Appellant contends that there was no discussion by the parties of any specific amount to be paid by appellant or any standard for arriving at the amount of any such payment and, therefore, neither the offer nor the acceptance were definite and no contract could result from the negotiations. We cannot agree with this contention. In our opinion the evidence supports the conclusion that Davis agreed to surrender his right to continue the contract in consideration of appellant’s agreement through Black to pay for the work done and expenses incurred in connection with the paint job. The evidence also supports the finding that appellant’s employees had apparent authority to make the agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lynx Exploration and Production Co. v. 4-Sight Operating Co.
891 S.W.2d 785 (Court of Appeals of Texas, 1995)
City of Fort Worth v. GENE HILL EQUIPMENT CO.
761 S.W.2d 816 (Court of Appeals of Texas, 1988)
Coastal Plains Development Corp. v. Tech-Con Corp.
531 S.W.2d 143 (Court of Appeals of Texas, 1975)
Jackson v. Paulsel Lumber Company
461 S.W.2d 161 (Court of Appeals of Texas, 1970)
Eisenbeck v. Buttgen
450 S.W.2d 696 (Court of Appeals of Texas, 1970)
Pines California, Inc. v. Miller
446 S.W.2d 91 (Court of Appeals of Texas, 1969)
Beck v. Lawler
422 S.W.2d 816 (Court of Appeals of Texas, 1967)
Burney v. Ibarra
415 S.W.2d 517 (Court of Appeals of Texas, 1967)
Mercantile National Bank at Dallas v. Hudgens
412 S.W.2d 364 (Court of Appeals of Texas, 1967)
Roby Industries, Inc. v. Maxwell Electronics Corp.
409 S.W.2d 559 (Court of Appeals of Texas, 1966)
Latham v. Dement
409 S.W.2d 429 (Court of Appeals of Texas, 1966)
H. B. Zachry Co. v. Ceco Steel Products Corp.
404 S.W.2d 113 (Court of Appeals of Texas, 1966)
Bendalin v. Delgado
397 S.W.2d 889 (Court of Appeals of Texas, 1965)
Parks v. Benson Co., Builders
393 S.W.2d 700 (Court of Appeals of Texas, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
369 S.W.2d 664, 1963 Tex. App. LEXIS 2176, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ford-motor-company-v-davis-brothers-inc-texapp-1963.