Parks v. Benson Co., Builders

393 S.W.2d 700
CourtCourt of Appeals of Texas
DecidedJuly 16, 1965
Docket16636
StatusPublished
Cited by17 cases

This text of 393 S.W.2d 700 (Parks v. Benson Co., Builders) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parks v. Benson Co., Builders, 393 S.W.2d 700 (Tex. Ct. App. 1965).

Opinion

MASSEY, Chief Justice.

In this case the material defendant was a cross-plaintiff. Neither he nor the plaintiff was satisfied. All parties appealed.

Jim Parks, plaintiff below, was a paint sub-contractor. The defendant Benson Company, Builders, was a general contractor; Student Housing, Inc., also a defendant, was the owner for whom Benson Company erected a building. The Benson Company, hereinafter termed as defendant, had a contract to erect a dormitory in Arlington, Tarrant County, Texas. This defendant entered into a contract with plaintiff to do the painting necessary on the dormitory. The agreed consideration therefor was $22,643.00. Plaintiff’s agreement was to paint the building exterior with two coats of paint and the interior with one coat, save columns in the interior which were to be given two coats. There were other obligations of the plaintiff which we may disregard.

Plaintiff engaged labor and purchased materials and proceeded. The defendant’s general superintendent was a Mr. Bob Bales.

On or about April 17, 1963 plaintiff billed the defendant on the basis of a 90% job completion (as applied to the $22,643.-00 contract), for which he was then entitled to be paid 90% (of said total amount) less a 10% “retainer” — according to his understanding of the agreement. This meant that he billed the defendant for $20,378.70, less “retainer” of $2,037.87, or a total amount due of $18,340.83 with expectation he would be paid the last stated figure. Bob Bales understood that such was the agreement, for he “okeyed” the bill upon satisfying himself (as defendant’s superintendent) that plaintiff had actually performed his contract to the extent of a 90% completion.

The defendant felt it wise to pay only 75%, or $16,982.00. This was the amount paid. Additional contracts were entered into between Bales, acting for defendant, and the plaintiff. Of these there were three, the first in the amount of $250.00, the second in the amount of $1,234.80, and thi third in the amount of $143.00. In addition plaintiff delivered 18 cans of paint to the defendant, at a charge of $29.70.

This resulted in a total amount claimed by the plaintiff of $24,300.50, less the amount of $16,982.00 paid thereon, with a balance claimed of $7,318.50. (Under a jury finding that $250.00 was the amount remaining to be expended to complete the contract by plaintiff at time his work ceased, the amount of plaintiff’s judgment was $7,068.50.)

As performance under the contract neared completion some inspectors for the defendant looked over plaintiff’s work. A dispute arose at the time, in that the inspectors contended that plaintiff was obligated to paint the interior walls of the dormitory with two coats of paint. Seemingly, the dispute was resolved upon proof by plaintiff that his bid was on the basis of only one coat. When the “acceptance” of defendant came from Houston (through its superintendent, Bales) it had a provision for two coats. Pursuant to a long distance telephone conversation between Bales and an authorized official in the defendant’s home office the signed instrument had been changed in ink to show only one coat. A meeting of the minds of the parties did not take place until this was done.

During course of the trial, a part of the defendant’s theory of defense to the plaintiff’s suit was that there had been a failure on the part of plaintiff to paint the interior *702 with two coats of paint. Defendant so plead. The proof utterly destroyed the defense.

At a time when, according to plaintiff, his performance under the original contract was more than 95% Completed, Bales was removed as superintendent. In his place defendant employed p. Mr. Cone. About the time Cone became superintendent, inspectors for defendant visited the “job site” and a disagreement between them and the plaintiff occurred in that they pointed out certain work they desired to be done. They were obviously of the opinion that plaintiff would either treat it as work falling within the contractual provisions, or would supply it at no cost as an accommodation. Plaintiff insisted it was not covered by the contract. If performed by him, he made it known that an additional payment would be demanded. The agents for the defendant were most unhappy. They returned to the home office where they discussed plaintiff’s work in general. They agreed between themselves that it was unsatisfactory. They informed the new superintendent, Cone. Apparently Cone allowed plaintiff to work two or three days thereafter, but then confronted him with the defendant’s dissatisfaction. Part of the discussion concerned plaintiff’s refusal to put a second coat of paint on the interior of the dormitory. In any event, pursuant to this discussion and under authority conferred by his principal, Cone offered to “buy” the balance of plaintiff’s contract for $4,000.00. Had plaintiff agreed to make such a deal he would have received $3,318.-50 less than he claimed under the primary contract plus the three subsidiary transactions and the price charged for the 18 cans of paint. On trial plaintiff claimed that at the time of the aforesaid discussion his work was at least 98% completed, but that Cone refused any further performance of the contract and “terminated” his work in all respects.

Whether the discussion about the $4,-000.00 “purchase” of the remainder of plaintiff’s contract amounted to an offer in compromise by the defendant is a matter of dispute between the parties. Plaintiff contends that it was not, while defendant claims that it was. There is no question but that the trial court agreed with the defendant, for he ordered that testimony thereupon be excluded from the jury. The court granted the defendant’s motion in limine when the offer of evidence was made outside the presence of the jury— from the lips of plaintiff. Then, after the jury was brought in and trial proceeded, the plaintiff — voluntarily and not in response to any question — testified that when he left the job the defendant “offered me $4,000.-00”.

When this occurred — on cross-examination — the attorney for the defendant continued with a few questions which he hoped would minimize the harm he believed had been caused, but at the earliest reasonable opportunity brought the matter before the court. He moved for a mistrial — not only because of the error, but because the plaintiff had committed intentional error in violating the court’s order sustaining defendant’s motion in limine. The plaintiff was questioned. He stated that he did not understand that the court had directed that he not testify about the offer of Cone. Holding its ruling in abeyance the court proceeded, though indicating to defendant’s counsel his willingness to instruct the jury to disregard the improper testimony. Counsel decided that to so instruct the jury would likely do even further damage to the defendant’s case — and declined to move for such instruction. Ultimately' the court overruled the motion for mistrial.

The jury#returned a verdict for the plaintiff. In its motion for new trial defendant assigned the reception by the jury of Cone’s offer in compromise as reversible error. No affidavit of any juror was attached to defendant’s motion. The plaintiff countered with an opposing motion. Thereto he attached, as an exhibit, a statement of one of the jurors to the effect that the juror did not recall that there was any testimony concerning an offer of compro *703

Free access — add to your briefcase to read the full text and ask questions with AI

Related

in Re Santiago Delgado
Court of Appeals of Texas, 2009
Columbia Medical Center of Las Colinas v. Bush Ex Rel. Bush
122 S.W.3d 835 (Court of Appeals of Texas, 2003)
Texas Farmers Insurance Co. v. Stem
927 S.W.2d 76 (Court of Appeals of Texas, 1996)
Allstate Insurance Co. v. Evins
894 S.W.2d 847 (Court of Appeals of Texas, 1995)
Beutel v. Paul
741 S.W.2d 510 (Court of Appeals of Texas, 1987)
Masco International, Inc. v. Stokley
567 S.W.2d 598 (Court of Appeals of Texas, 1978)
Metal Structures Corp. v. Plains Textiles, Inc.
470 S.W.2d 93 (Court of Appeals of Texas, 1971)
Jackson v. Paulsel Lumber Company
461 S.W.2d 161 (Court of Appeals of Texas, 1970)
Beck v. Lawler
422 S.W.2d 816 (Court of Appeals of Texas, 1967)
Burney v. Ibarra
415 S.W.2d 517 (Court of Appeals of Texas, 1967)
Roby Industries, Inc. v. Maxwell Electronics Corp.
409 S.W.2d 559 (Court of Appeals of Texas, 1966)
Latham v. Dement
409 S.W.2d 429 (Court of Appeals of Texas, 1966)
H. B. Zachry Co. v. Ceco Steel Products Corp.
404 S.W.2d 113 (Court of Appeals of Texas, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
393 S.W.2d 700, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parks-v-benson-co-builders-texapp-1965.