Hicks v. Smith

330 S.W.2d 641, 1959 Tex. App. LEXIS 1745
CourtCourt of Appeals of Texas
DecidedDecember 11, 1959
Docket16050
StatusPublished
Cited by20 cases

This text of 330 S.W.2d 641 (Hicks v. Smith) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hicks v. Smith, 330 S.W.2d 641, 1959 Tex. App. LEXIS 1745 (Tex. Ct. App. 1959).

Opinion

MASSEY, Chief Justice.

This case is one in which Roger Smith, as plaintiff, sued the partners doing business as Hicks Construction Company to establish a contract and enforce performance thereunder on the part of the defendants. Trial was to a jury and upon answers of the jury which established the contract and its provisions, the trial court entered a judgment predicated upon jury findings coupled with other facts judicially found.

Appeal was taken from the adverse judgment by the defendants, based upon their contention that there was no evidence, or insufficient evidence, to show any consideration for the contract declared upon by the plaintiff, and that there was no evidence or, in any event, insufficient evidence to show that the parties had mutually agreed thereto.

Judgment affirmed.

The contract declared upon was essentially a modification of one previously existing between the parties. The defendants stood upon the original contract, the terms of which are not in dispute, but which, as between plaintiff and defendants, we believe would be subject to construction. The original contract between the parties was an oral one predicated upon a “base” contract in written form entered into between the defendants, as general contractor, with the City of Wichita Falls. To this contract plaintiff was not a party. By the contract between plaintiff and defendants, a part of the obligations assumed by the defendants *643 under the “base” contract was subcontracted and assumed by the plaintiff.

In said “base” contract the defendants had certain natural rights which they contracted not to assert against the City even should they have cause to do so. Specifically, as applied to this case, the right yielded up was that of contesting and refusing to comply with the determination of any question by a person specified as the “Engineer” as to the amount and quantity of the kinds of work the defendants were (primarily) obliged to perform under the “base” contract. Defendants’ agreement was that they would abide by the Engineer’s determination of all questions in relation to work performed under the contract, etc. In connection therewith the defendants were given the right under the “base” contract to claim additional compensation on account of any increase in the work as the result of any order or decision of the Engineer, the right to be secured and preserved through the filing, within thirty days after receipt of such an order, of a written protest. In resolution of such question, determination of the defendants’ rights, if any, would be through an arbitration.

It will readily be seen that the plaintiff, under and by reason of his original oral contract with the defendants, received no rights as against the City of Wichita Falls in the event of some decision by the Engineer which in his opinion was not within the provisions of the “base” contract, or, in turn, under his original contract with the defendants. This is so because no provision of the “base” contract contemplated any such right on the part of any subcontractor. We must, therefore, give some consideration to what the situation would pose in the matter of rights, if any, of the plaintiff against the defendants should the Engineer make a determination and direct that certain work be performed by the defendants in the execution on the part of the “base” contract which defendants had subcontracted to the plaintiff, if and in the event the plaintiff might contend such was not within the contemplation of either the “base” contract or his original contract with the defendants. In such a case it would appear that the defendants, even should they share plaintiff’s belief and interpretation, would be obliged to proceed in accordance with the Engineer’s decision. Of course, they could preserve any right to complain and to contend on their own behalf for a greater compensation than that they had agreed to accept when they entered into the “base” contract. But what of the rights, if any, of their subcontractor, the plaintiff, especially when there was a complete absence of agreement by plaintiff and defendants as to plaintiff’s rights in the event of such contingency ?

Such was substantially the situation which resulted in this suit by plaintiff against the defendants. A substantial part of the contract made between plaintiff and the defendants (by which plaintiff assumed part of the obligations of the defendants under their “base” contract with the City) required the plaintiff to drive piles as the foundation for the erection of a structure or structures. In the “base” contract it was estimated that the piles would be driven approximately twenty-five (25) feet into the ground to a firm foundation therefor. After being so driven it would be necessary that some part of the ends remaining above ground be cut off in such way that the tops would be even with one another in simplification of subsequent structural work. The contract further provided that some “test piles” would be driven prior to determination of the proper length of piles. From the information thus secured, piling of the proper length would be used.

In arriving at the contract between plaintiff and defendants, the parties, knowing how many locations there would be at which piles would be driven, and hence knowing the number of piles, estimating the depth into the ground each would be driven, and also estimating the length which would be necessary to be “topped *644 off” of each pile, agreed upon a calculable figure as plaintiff’s consideration. Plaintiff would receive from the defendants, as consideration, a certain amount for each foot of piling driven into the ground, and a certain amount for each foot of piling “cut off”.

Upon beginning the work under the contract, the “test piles” were driven. Plaintiff was very disappointed to find that bedrock was reached when the test piles had been driven only approximately nine (9) feet into the ground. Understandably, this meant that instead of computing his compensation under the contract on the basis of driving each pile approximately twenty-five (25) feet, it would be computed on only a little better than one-third that number of feet. The “Engineer”, who had the right of determining all questions in relation to the work, at least in so far as the defendants were concerned and under the “base” contract between defendants and the City, then made a decision as contemplated under said “base” contract. He directed that thirty-five (35) foot lengths of piling be purchased and used, and that each of said long lengths be cut into three sections, about twelve feet long or slightly less, and the sections driven. Compliance was requisite in order to constitute a performance of the pile driving portion of the “base” contract. If plaintiff proceeded to perform in accordance with the Engineer’s directions, it meant not only that the amount he expected to. receive from the defendants would be drastically reduced, due to the fact that piles would be driven only about nine (9) feet into the ground rather than the approximate twenty-five (25) feet anticipated, but his work in the accomplishment was most appreciably increased due to the fact that he would have to cut long piling into sections, then treat the raw ends of the sections cut with creosote before driving them as piles.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hunt v. Meridian Security
Fifth Circuit, 2024
Billy W. McDaniel v. Christopher E. McKeown
Court of Appeals of Texas, 1997
Reilly v. Rangers Management, Inc.
727 S.W.2d 527 (Texas Supreme Court, 1987)
Beck v. Lawler
422 S.W.2d 816 (Court of Appeals of Texas, 1967)
EASTMAN OIL WELL SURVEY COMPANY v. Hamil
416 S.W.2d 597 (Court of Appeals of Texas, 1967)
Mercantile National Bank at Dallas v. Hudgens
412 S.W.2d 364 (Court of Appeals of Texas, 1967)
Latham v. Dement
409 S.W.2d 429 (Court of Appeals of Texas, 1966)
Farry v. Landreth
404 S.W.2d 620 (Court of Appeals of Texas, 1966)
Parks v. Benson Co., Builders
393 S.W.2d 700 (Court of Appeals of Texas, 1965)
Arden Engineering Co. v. E. Turgeon Construction Co.
197 A.2d 743 (Supreme Court of Rhode Island, 1964)
Rio Refrigeration Co. v. Thermal Supply of Harlingen, Inc.
368 S.W.2d 128 (Court of Appeals of Texas, 1963)
Kirkwood & Morgan, Inc. v. Roach
360 S.W.2d 173 (Court of Appeals of Texas, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
330 S.W.2d 641, 1959 Tex. App. LEXIS 1745, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hicks-v-smith-texapp-1959.