Arden Engineering Co. v. E. Turgeon Construction Co.

197 A.2d 743, 97 R.I. 342, 1964 R.I. LEXIS 85
CourtSupreme Court of Rhode Island
DecidedFebruary 25, 1964
DocketEx. No. 10561
StatusPublished
Cited by17 cases

This text of 197 A.2d 743 (Arden Engineering Co. v. E. Turgeon Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arden Engineering Co. v. E. Turgeon Construction Co., 197 A.2d 743, 97 R.I. 342, 1964 R.I. LEXIS 85 (R.I. 1964).

Opinion

*343 .

Joslin, J.

This action of assumpsit was heard by a justice of the superior court sitting without a jury and resulted in a decision for the plaintiff in the amount of $18,536.57. The case is here on the defendant’s bill of exceptions, the only exceptions pressed 'being those to the decision and to an evidentiary ruling. Exceptions neither briefed nor argued are deemed to be waived.

The declaration is in three counts. The first count alleges that plaintiff had contracted with the state for the installation of heating and ventilating equipment in a building being constructed for the state by defendant as general contractor; that defendant’s contract required it to provide *344 insurance against loss 'by fire or boiler explosion covering the interests of all prime contractors, including plaintiff, engaged in work on the project; that plaintiff’s contract did not require it to carry that type of insurance; that a boiler explosion occurred; and that the damage resulting therefrom was repaired by plaintiff at defendant’s written authorization and upon its promise to pay therefor, which payment has not been made.

The second count differs materially only in its failure to refer to an obligation of defendant to provide insurance coverage and alleges therein that defendant’s promise to pay the cost of the repairs was in writing. The third count contains the common counts.

The defendant pleaded the general issue.

It appears from the evidence that both defendant and plaintiff contracted with the state, the former to construct certain new buildings at the Rhode Island College of Education in North Providence, and the latter to do the heating and ventilating work in connection with that construction. In each contract there was a provision that plaintiff should “be solely responsible for the heating system,” and should “make good any damage caused by temporary use.” (italics ours) Both plaintiff and defendant in their respective contracts were required to carry fire insurance with extended coverage “upon the entire structure on which the work of this contract is to be done * *

On January 26, 1958 after the boiler installed by plaintiff had become operational and while temporary heat was being supplied to the project, an explosion occurred in the boiler causing substantial damage to it as well as to the surrounding general area.

Thereafter several conferences took place attended by authorized representatives of each of the parties, their insurance agents, representatives of the state, and others, to discuss the restoration of temporary heat, maintenance of *345 building progress, and repair of the damage. At one of these conferences the insurance agent for defendant stated that for an additional premium a policy could be issued which would cover the loss which had already taken place. Such a policy was in fact issued, the state paying the premium thereon. Subsequent to its issuance the state’s representative suggested to defendant that it instruct plaintiff to make the repairs, whereupon defendant wrote plaintiff as follows:

“February 10, 1958
“Arden Engineering Company
“60 Taylor Drive
“Rumford, Rhode Island
“Re: R. I. College of Education
Providence, R. I.
“Gentlemen:
“On the basis of verbal authorization received from the Division of Architecture and Engineering, you are hereby directed to proceed with the repairs to the boiler damaged on January 26, 1958 and any necessary repairs to Boiler #2.
“You will be required to submit an invoice in triplicate showing the cost of making these repairs, so that the bill can be forwarded to the insurance company. “Please bear in mind that any work in connection with your contract for connecting up Boiler #2 is not to be included in this billing for repairs.
“Labor and material charges should be checked at least weekly with our superintendent and cost clerk at the site for verification to the insurance company.
“Very truly yours,
“E. TURGEON CONSTRUCTION CO., INC.
“By [signed] Edward P. Turgeon
“Edward P. Turgeon, Treasurer”

It further appears that at these conferences plaintiff’s position was that it was not prepared to make repairs to the boiler unless so authorized by defendant and that it made the repairs in reliance upon its letter of February 10, 1958.

*346 The trial justice found for plaintiff on the first two counts of its declaration, concluding that there was an implied contract obligating defendant to pay for the repairs. The defendant does not contend that the trial justice overlooked or misconceived any evidence, but bases its exceptions on ■errors of law.

It contends that there was a material variance between the pleadings and the proof, there being no evidence supportive of the allegation in the second count of a written promise to pay. The trial justice considered that allegation as surplusage which defendant says is error. Implicit in its argument, though not briefed, is a possible further contention that if no recovery can be had on the second count because of a failure of proof as to the promise to pay being in writing, then and in such instance recovery cannot be had on the first count because of a possible lack of evidence to support the allegation in that count that defendant was required to provide insurance coverage for damage resulting from a boiler explosion under its contract with the state.

The principle of variance does not require such rigorous adherence as to require proof of each allegation to the letter. Proof of the substance will suffice, and so long as the testimony substantially supports the allegations the variance is not material. Menzoian v. Johnson, 57 R. I. 196, 200. The instant case was tried by both parties on the issue of the legal consequences flowing from defendant’s written authorization to plaintiff to repair the boiler. That authorization is annexed to the declaration and made a part of it.

The defendant did not ask for a bill of particulars seeking information as to the form, nature, or content of the written promise to pay declared upon in the second count. Nor can it be said, and indeed defendant does not. claim, that it was either surprised or misled by the evidence offered by plaintiff or by its failure to offer testimony as to a writ-; *347 ten promise. In these circumstances there is not that kind of material failure of proof as requires a finding that error inhered in the decision of the trial justice treating plaintiff’s allegation of a written promise in the second count as surplusage. D’Onofrio v. First National Stores, Inc., 68 R. I.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conlin v. Greyhound Lines, Inc.
384 A.2d 1057 (Supreme Court of Rhode Island, 1978)
Rhode Island Hospital Trust National Bank v. Israel
377 A.2d 341 (Supreme Court of Rhode Island, 1977)
RI HOSPITAL TRUST NAT. BANK v. Israel
377 A.2d 341 (Supreme Court of Rhode Island, 1977)
Jewel Company of America, Inc. v. George
373 A.2d 1200 (Supreme Court of Rhode Island, 1977)
PROVIDENCE & WORCESTER COMPANY v. Exxon Corp.
359 A.2d 329 (Supreme Court of Rhode Island, 1976)
State v. Sprague
331 A.2d 399 (Supreme Court of Rhode Island, 1975)
Chase v. Blackstone Distributing Co.
294 A.2d 392 (Supreme Court of Rhode Island, 1972)
Hopkins v. Equitable Life Assurance Society of the United States
270 A.2d 915 (Supreme Court of Rhode Island, 1970)
Smith v. DeFusco
267 A.2d 725 (Supreme Court of Rhode Island, 1970)
Tefft v. Tefft
253 A.2d 601 (Supreme Court of Rhode Island, 1969)
Spouting Rock Beach Association v. Garcia
244 A.2d 871 (Supreme Court of Rhode Island, 1968)
Glass-Tite Industries, Inc. v. Spector Freight Systems, Inc.
230 A.2d 254 (Supreme Court of Rhode Island, 1967)
Burns v. Burns
229 A.2d 294 (Supreme Court of Rhode Island, 1967)
DiMaio v. Del Sesto
228 A.2d 861 (Supreme Court of Rhode Island, 1967)
Industrial National Bank v. Isele
227 A.2d 203 (Supreme Court of Rhode Island, 1967)
Toole v. May-Day Realty Corp.
223 A.2d 545 (Supreme Court of Rhode Island, 1966)
Cinq-Mars v. Travelers Insurance Company
218 A.2d 467 (Supreme Court of Rhode Island, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
197 A.2d 743, 97 R.I. 342, 1964 R.I. LEXIS 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arden-engineering-co-v-e-turgeon-construction-co-ri-1964.