Delhi Pipeline Corporation v. Lewis, Inc.

408 S.W.2d 295, 1966 Tex. App. LEXIS 2191
CourtCourt of Appeals of Texas
DecidedApril 28, 1966
Docket138
StatusPublished
Cited by27 cases

This text of 408 S.W.2d 295 (Delhi Pipeline Corporation v. Lewis, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delhi Pipeline Corporation v. Lewis, Inc., 408 S.W.2d 295, 1966 Tex. App. LEXIS 2191 (Tex. Ct. App. 1966).

Opinions

OPINION

SHARPE, Justice.

This appeal is from a judgment rendered in a jury trial for Lewis, Inc., appellee, plaintiff below, in the sum of $31,303.07, against Delhi Pipeline Corporation, defendant below. The parties will sometimes be referred to as “Lewis” and “Delhi”.

[297]*297Lewis sued for damages in the amount of $25,914.76 for alleged breach of oral and written contracts, the latter having been executed on October 3, 1963, and the former having been entered into shortly thereafter, all covering pipeline projects in Victoria County, Texas; for $50,000.00 as exemplary damages and $8,000.00 for attorney’s fees. By way of cross-action, Delhi sued for $4,932.45 due to alleged breach of contract by Lewis. Lewis is in the business of constructing pipeline systems and Delhi is a gas transmission company. It is undisputed that Lewis was an independent contractor and that Delhi terminated the contracts before completion of the work by Lewis.

The jury verdict established the amount of Lewis’ damages as follows: $17,451.00 for expenses incurred prior to termination of the contracts; $7,500.00 for loss of profit; $5,000.00 for attorney’s fees; and $15,000.00 for exemplary damages. The trial court granted Delhi’s motion for judgment non obstante veredicto and to disregard the jury findings concerning exemplary damages only and denied Lewis a recovery in such respect. The judgment allowed interest on the amount of $24,951.50 from October 17, 1963 to its date of entry on September 12, 1964.

Appellant Delhi urges 37 points of error which are briefed in six groups. Appellee Lewis urges 7 reply points, similarly briefed, and one counterpoint concerning the refusal of the trial court to award exemplary damages. The points will be discussed as grouped for briefing by the parties.

Under the first group of points (1-6), relating primarily to Special Issue 1, Delhi contends that the trial court should not have rendered judgment based upon such jury finding; that there is no evidence and it is factually insufficient to raise such issue and support the answer thereto; that the trial court should have granted judgment non obstante veredicto on the entire case pursuant to Delhi’s motion; and, in any event, should have granted a new trial.

Special Issue 1, its accompanying definition and the jury answer are as follows:

“Special Issue No. 1.
“Do you find from a preponderance of the evidence that under all the circumstances which existed on or prior to October 17, 1963, Plaintiff Lewis, Inc., was proceeding with due diligence on his contracts with Defendant Delhi Pipeline Corporation to install the pipelines in question ?
Answer ‘yes’ or ‘no’.
Answer: Yes.
“By the term ‘due diligence’ as used herein is meant such diligence as would be required for Plaintiff to complete the contracts in accordance with the terms and provisions of the contracts between Plaintiff and Defendant and the plans and specifications.”

Delhi’s argument under its first group of points is that Lewis had agreed to perform the work in a manner satisfactory to Delhi’s representative, Mr. C. P. Butler, and this was the real issue; that Lewis’ work was not satisfactory to Butler, and his dissatisfaction was conclusive on the question of performance and breach; that the question submitted by special issue 1 was immaterial ; that Lewis’ failure to plead, prove and secure a jury finding of bad faith on the part of Delhi’s representative is fatal to Lewis’ recovery; that, in any event, there is no evidence and it is factually insufficient to raise and support the jury finding on special issue 1 that Lewis was proceeding with due diligence. Lewis contends that the trial court correctly submitted the ultimate and controlling issue of diligent compliance with the contracts and that the jury answer is amply supported by evidence. We agree with Lewis.

Delhi 'relies upon the rule that, a contract may require that one party’s per[298]*298formance shall be to the satisfaction of the other party or, in some instances, to that of a designated third party such as an architect or engineer. See Atlas Torpedo Co. v. United States Torpedo Co., 15 S.W.2d 150 (Tex.Civ.App.1929, n. w. h.); Dixie Oil Co. v. McBurnett, 6 S.W.2d 83 (Tex.Com.App.1928, Judg.App.); Griffith v. Thomson, 244 S.W.2d 722 (Tex.Civ.App. 1951, n. w. h.); Golden State Mutual Life Insurance Co. v. Kelley, 380 S.W.2d 139 (Tex.Civ.App.1964, wr. ref., n. r. e.); Goodrum v. State, 158 S.W.2d 81 (Tex.Civ. App.1942, wr. ref., w. m.); City of San Antonio v. McKenzie Const. Co., 136 Tex. 315, 150 S.W.2d 989 (1941); Coppinger v. Republic Natural Gas Co. (10 Cir. 1948), 171 F.2d 4; Thompson-Starrett Co. v. La Belle Iron Works, (2 Cir. 1927), 17 F.2d 536. But that rule is operative only where it appears from express terms of the contract or from plain language therein that it was the intention of the parties that the determination of the person to whom the decision is entrusted would be final and conclusive; and such a provision is not to be implied. Black v. Acers, 178 S.W.2d 152 (Tex.Civ.App.1944, wr. ref.); Eckert-Fair Construction Company v. Flabiano, 342 S.W.2d 629 (Tex.Civ.App.1960, wr. ref., n. r. e.).

The sole provision concerning termination is found in the written contracts as follows:

“Contractor agrees to commence said work within - days from the date of this contract and to complete said work with due diligence and, in the event Contractor fails to commence said work within the time above specified or, having begun said work, abandons it or for any reason suspends or refuses to continue it for a period of five days (unless Contractor is prevented from continuing by reasons beyond his control), Company shall have the right to take over said work and complete it at Contractor’s expense.”

The provisions as to satisfaction of the representative of Delhi in certain particulars are contained only in the specifications which were incorporated by reference into the contracts. We agree with appellant that in such case we must consider the agreements made by the parties in the specifications along with those contained in the job contracts. Tower Contracting Co., Inc. v. Flores, 157 Tex. 297, 302 S.W.2d 396 (1957); 17A C.J.S. Contracts § 299, pp. 136-137. However, there is no provision in the specifications or the job contracts that the determination of dissatisfaction by Delhi’s representative would be final, binding or conclusive; neither is there a provision that such dissatisfaction would furnish a basis for Delhi to terminate the contracts. None of the provisions for termination by Delhi is shown to exist.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tribble & Stephens Co. v. RGM Constructors, L.P.
154 S.W.3d 639 (Court of Appeals of Texas, 2005)
Kneip v. Unitedbank-Victoria
734 S.W.2d 130 (Court of Appeals of Texas, 1987)
R.C. Small & Associates, Inc. v. Southern Mechanical, Inc.
730 S.W.2d 100 (Court of Appeals of Texas, 1987)
Delta Drilling Co. v. Cruz
707 S.W.2d 660 (Court of Appeals of Texas, 1986)
Lake LBJ Municipal Utility District v. Coulson
692 S.W.2d 897 (Court of Appeals of Texas, 1985)
Southern Steel Co. v. Consolidated Engineering Co.
677 S.W.2d 97 (Court of Appeals of Texas, 1984)
Hanger General Contractors v. Greater Swenson Grove Baptist Church
597 S.W.2d 32 (Court of Appeals of Texas, 1980)
Brown v. Payne-Ladewig, Inc.
568 S.W.2d 159 (Court of Appeals of Texas, 1978)
Longview Construction & Development, Inc. v. Loggins Construction Co.
523 S.W.2d 771 (Court of Appeals of Texas, 1975)
Koenning v. Manco Corporation
521 S.W.2d 691 (Court of Appeals of Texas, 1975)
Little v. Alto Ind. Sch. Dist. of Alto, Cherokee Cty.
513 S.W.2d 886 (Court of Appeals of Texas, 1974)
Wolfe v. SPEED FAB-CRETE CORPORATION INTERNAT'L
507 S.W.2d 276 (Court of Appeals of Texas, 1974)
Wilson v. Whitcher
477 S.W.2d 344 (Court of Appeals of Texas, 1972)
City of Houston v. United Compost Services, Inc.
477 S.W.2d 349 (Court of Appeals of Texas, 1972)
Brace v. Dante
466 S.W.2d 66 (Court of Appeals of Texas, 1971)
Tenneco Oil Company v. Padre Drilling Company
453 S.W.2d 814 (Texas Supreme Court, 1970)
OK Johnson Electric, Inc. v. HESS-MARTIN CORPORATION
464 P.2d 206 (Supreme Court of Kansas, 1970)
Seal v. Rogers
448 S.W.2d 722 (Court of Appeals of Texas, 1969)
Parkview General Hospital, Inc. v. Eppes
447 S.W.2d 487 (Court of Appeals of Texas, 1969)
Tenneco Oil Co. v. Padre Drilling Co.
445 S.W.2d 247 (Court of Appeals of Texas, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
408 S.W.2d 295, 1966 Tex. App. LEXIS 2191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delhi-pipeline-corporation-v-lewis-inc-texapp-1966.