Wolfe v. SPEED FAB-CRETE CORPORATION INTERNAT'L

507 S.W.2d 276, 1974 Tex. App. LEXIS 1995
CourtCourt of Appeals of Texas
DecidedMarch 8, 1974
Docket17480
StatusPublished
Cited by13 cases

This text of 507 S.W.2d 276 (Wolfe v. SPEED FAB-CRETE CORPORATION INTERNAT'L) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wolfe v. SPEED FAB-CRETE CORPORATION INTERNAT'L, 507 S.W.2d 276, 1974 Tex. App. LEXIS 1995 (Tex. Ct. App. 1974).

Opinion

OPINION

BREWSTER, Justice.

This is a suit for damages for breach of a building contract.

The parties will be referred to here as they were in the trial court.

The plaintiff, Speed Fab-Crete Corporation International, entered into a written contract with the defendant, Betty K. Wolfe, which provided in part as follows:

“SPEED FAB-CRETE CORPORATION INTERNATIONAL will furnish labor and material to do the following specified work as shown on plans drawn up by SPEED FAB-CRETE CORPORATION. Work shall be done in accordance with the nationally accepted and approved methods and techniques known as the SPEED FAB-CRETE system . . . . ” (Emphasis ours.)

Provisions of the contract followed outlining the various parts of the building that the plaintiff was to build. The building was to be used as a drive-in restaurant.

The following provision was contained in the contract reference to the roof system that plaintiff was to place on defendant’s building:

“ROOF SYSTEM: Roof structure shall be of pre-cast concrete set on concrete beams as shown on plans. Three ply built-up roof mopped over ¾" fibre glass insulation board. Porch roof shall have three ply roof mopped to concrete deck. Three 4" X 4" downspouts on rear of building. There shall be approximately 130 lineal feet of mansard roof facia on top of building as shown on plans. The mansard roof shall be constructed of 24 gage paint grip metal screwed on to an angle iron super structure and properly mounted to the concrete roof.” (Emphasis ours.)

The written contract did not state one way or another whether there were to be placed any columns within the building to aid in supporting the concrete roof that the contract called for to be placed on the building by the plaintiff.

However, it is undisputed that the plans for the building that were drawn up by Speed Fab-Crete Corporation International, as provided for in the first paragraph of the contract that is set out above, did call for three columns to be placed within the building for the purpose of aiding in the support of the roof. Two of these columns were to be within walls and would not be visible after completion of the building, and the other column was to be located in what Mrs. Wolfe called her “cook line.”

The plaintiff began construction of the building and at one point of construction Mrs. Wolfe observed some steel plates being placed at certain points on the concrete floor. She made inquiry as to what these plates were for and was advised that the three columns for support of the roof would be placed at those points. She then contacted Dave Bloxom, the president of the plaintiff corporation, advising him that she did not want any columns inside the building.

It is undisputed that the plaintiff stood ready, willing and able to continue with the building if allowed to place the three columns in it that were shown in the plans. The plaintiff’s president admitted that the roof could be placed on the building without the columns, but that to do so would *278 increase his costs considerably. Plaintiff insisted on erecting the building with the three columns shown in the plans placed in it. Mrs. Wolfe refused to permit the plaintiff to proceed under those circumstances and got another contractor and he finished the building.

Speed Fab-Crete Corporation then filed this suit seeking to recover damages for a breach of the contract, plus attorney’s fees on the theory that attorney’s fees are provided for in the contract between the parties.

Mrs. Wolfe filed a cross-action alleging that plaintiff had breached the contract by refusing to build the building without the inside columns in it and sought to recover $2,500.00 from plaintiff alleging that her building costs were increased that much by plaintiff’s breach.

Later plaintiff filed a motion for summary judgment and the trial court did render a partial summary judgment decreeing that defendant was liable on plaintiff’s cause of action and that plaintiff was not liable on defendant’s cross-action.

The record shows that the trial court granted this partial summary judgment in plaintiff’s favor on the theory that the evidence showed as a matter of law that the plaintiff did not breach the contract upon the occasion in question, and that the undisputed evidence offered did show that Mrs. Wolfe breached the contract in two respects, namely: (1) she stopped plaintiff from performing the contract and from erecting the building as provided for in the contract and plans that were therein referred to; and (2) she failed to make the required payments on the contract as the work progressed that were therein provided for.

At a later hearing a jury trial was held and submitted to the jury were issues as to the amount of damages sustained by plaintiff and issues as to what would be a reasonable fee for plaintiff’s attorney; (a) for handling the case through the trial court; (b) for handling it to the Court of Civil Appeals; and then (c) for handling it to the Supreme Court.

Based on the partial summary judgment and on the jury verdict the trial court rendered judgment for plaintiff and against Mrs. Wolfe for $14,372.00 damages, plus $1,600.00 for attorney’s fees if there is no appeal, $1,950.00 for attorney’s fees if appealed to the Court of Civil Appeals and $2,000.00 if it is appealed to the Supreme Court.

This appeal is by Mrs. Wolfe from that decree.

Mrs. Wolfe agreed in the contract to pay to plaintiff $20,000.00 for furnishing the labor and materials therein agreed upon. The $14,372.00 in damages that were awarded plaintiff in the judgment was arrived at by deducting from the $20,000.00 contract price the sum of $5,628.00, which sum the jury had found was the usual and fair cost of the materials and labor necessary and remaining to be furnished by plaintiff to complete the contract in question. The use of this measure of damages is not questioned on this appeal.

Mrs. Wolfe contends in her first three points of error that the trial court erred in granting the partial summary judgment because (1) there was a fact issue as to whether or not the contract plans and specifications provided for columns in the interior of the building to support the roof; (2) there was a fact issue as to whether or not Speed Fab-Crete Corporation International breached the contract; and (3) because there was a fact issue as to whether or not there was a mutual abatement of the contract.

We overrule these three points.

The following is from 13 Tex.Jur.2d, Contracts, Sec. 116, p. 276: “. . . if one instrument is made a part of another by reference, both instruments must be read and construed together.” And the following is from 13 Tex.Jur.2d, Contracts, Sec. 117, at p. 278: “Under the doctrine of incorporation by reference, anoth *279 er contract or instrument may properly constitute part of a written agreement. In such a case, both agreements must be read and construed together.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sandy R. Duncan v. Woodlawn Manufacturing, LTD
479 S.W.3d 886 (Court of Appeals of Texas, 2015)
Raymond James & Associates, Inc. v. Bowman
196 S.W.3d 311 (Court of Appeals of Texas, 2006)
Godwin White & Gruber PC v. Deuschle
87 F. App'x 338 (Fifth Circuit, 2004)
In Re C H News Company
133 S.W.3d 642 (Court of Appeals of Texas, 2003)
in Re: C & H News Co.
Court of Appeals of Texas, 2003
Bethel v. Norman Furniture Co., Inc.
756 S.W.2d 6 (Court of Appeals of Texas, 1988)
Porter v. Irvine
658 S.W.2d 711 (Court of Appeals of Texas, 1983)
Ledisco Financial Services, Inc. v. Viracola
533 S.W.2d 951 (Court of Appeals of Texas, 1976)
Olivares v. Porter Poultry & Egg Co.
523 S.W.2d 726 (Court of Appeals of Texas, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
507 S.W.2d 276, 1974 Tex. App. LEXIS 1995, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wolfe-v-speed-fab-crete-corporation-internatl-texapp-1974.