Longview Construction & Development, Inc. v. Loggins Construction Co.

523 S.W.2d 771, 1975 Tex. App. LEXIS 2701
CourtCourt of Appeals of Texas
DecidedMay 8, 1975
Docket801
StatusPublished
Cited by17 cases

This text of 523 S.W.2d 771 (Longview Construction & Development, Inc. v. Loggins Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Longview Construction & Development, Inc. v. Loggins Construction Co., 523 S.W.2d 771, 1975 Tex. App. LEXIS 2701 (Tex. Ct. App. 1975).

Opinion

MOORE, Justice.

This is a suit brought by a prime contractor against a sub-contractor for damages for breach of contract. Plaintiff Loggins Construction 1 of Tyler, Texas, brought the suit to recover damages alleged to have resulted from defendant Long-view Construction and Development, Inc.’s breach of its sub-contract with Log-gins to perform certain excavation and earth work in conjunction with construction of a football stadium for Stephen F. Austin University of Nacogdoches, Texas. 2 *774 The case was tried before a jury and judgment was rendered in favor of Loggins for the sum of $49,255.00, based on the jury’s finding that Longview failed to complete the work and failed to substantially perform its contract. Longview duly perfected this appeal.

We affirm in part and reverse and render in part.

The evidence shows that Loggins Construction Company, as general contractor, contracted with Stephen F. Austin University to construct the stadium. One of the component parts of the project was site clearing and certain dirt work encompassing (1) clearing, grading, and filling the site, (2) stripping and stockpiling the top soil, (3) making a 20-foot excavation for the football field, (4) spreading sand on the football field, (5) construction on the east and west sides of the field of two earth mounds, called “berms,” upon which bleachers, walks, concession stands and a press box were to be constructed, and (6) some grading and filling on two parking lots.

Longview Construction and Development, Inc., was the successful bidder on the foregoing work and contracted with Loggins to do the work for the sum of $101,000.00.

The pertinent parts of the sub-contract are as follows:

“FIRST: The SUB-CONTRACTOR agrees to furnish all labor, materials, insurance, taxes, tools and equipment to perform all work necessary to complete the,
Site Clearing — (No Burning of Trees
or Brush)
Strip Top Soil & Stockpile
Machine Excavation, Fill & Select Fill to Subgrade
Spread Sand Fill at Football Field (Sand by LCC) for the above named structure, according to plans, specifications, and addendum No’s 1 & 2 heretofore furnished by above named architect, and to the full satisfaction of said architect.
?|c j(i ⅜ # j}« ⅜
“EIGHTH: In consideration whereof, the said CONTRACTOR agrees that he will pay to the said SUB-CONTRACTOR in monthly payments, the sum of $101,000 for said materials and work, said amount to be paid as follows: Ninety per cent (90%) of all labor and material which has been placed in position by said SUB-CONTRACTOR to be paid on or about the 15th of the following month, based on estimate submitted to CONTRACTOR by SUB-CONTRACTOR no later than the last day of the month, except the final payment which the said CONTRACTOR shall pay to the said SUB-CONTRACTOR within 30 days after the SUB-CONTRACTOR shall have completed his work to the full satisfaction of the said architect or owner.”

The plans and specifications provided that the football field and surrounding area were to be excavated below ground level and the soil was to be piled on each side to serve as a foundation for the bleachers. The specification provided that the soil was to be excavated and stacked at a certain specified grade.

Longview commenced work on the project on or about January 1, 1972. By September 20, 1972, the football field and parking lots had been cleared and excavated, and the slopes on both sides of the field had been constructed. Relying upon the conclusion of its foreman, Mr. Sipes, Long-view determined that the sub-contract had been completed and informed Loggins of the completion. Upon inspection of the work, Ray Loggins, President of Loggins, determined that the work was not satisfactory and did not conform to the plans and specifications because the slopes on both the front and back sides contained too much soil and were not constructed on the *775 grade level required by the specifications. Loggins testified that the subgrade on parking lots A and B and other areas was not excavated to the level required by the plans and specifications because it was too high in some areas and too low in others. Two surveyors, Chris Marek and Frank Mitchell, who worked on the job for a registered engineer employed by Loggins, corroborated Loggins’ testimony. They testified that neither the slopes nor the excavated areas were on grade at the time Longview left the job. Mitchell stated that he told Longview’s Mr. Sipes that the slopes were not on the required grade and he replied that he “just couldn’t do it.”

Ray Loggins requested Longview to return and complete the job, but Longview maintained that the job was completed according to the plans and specifications and refused to return. Since Loggins was unable to get another contractor to complete the work on a bid basis, he hired Simon Traylor & Son to'complete the job on an hourly basis. The evidence shows that in order to complete the job, Traylor & Son were required to remove from one to three feet of soil from the slopes constructed by Longview. In order to meet the requirement of the plans and specifications, approximately 30,000 yards of soil had to be removed. The removal of the soil from the upper part of the slopes required the use of specialized equipment making the work more expensive. It took approximately five months to complete the work. According to Ray Loggins, the total cost to complete the job according to the plans and specifications amounted to the sum of $63,976.58. His testimony as to the amount paid Simon Traylor & Son was corroborated by numerous cancelled checks.

After the project was completed, Log-gins brought this suit against Longview seeking to recover (1) the sum paid Simon Traylor & Son to complete the subcontract, (2) the value of the time and equipment used by Loggins to complete the contract, and (3) for special damages as a result of a $250.00 per day penalty assessed against Loggins by the owner for delay in completing the contract. Long-view answered with a general denial and filed a cross-action in the nature of a sworn account alleging that it had completed its sub-contract and praying for a recovery of the balance due on the sub-contract in the amount of $20,395.58.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coulier v. United Airlines, Inc.
110 F. Supp. 3d 730 (S.D. Texas, 2015)
Henning, Kenneth v. OneWest Bank FSB
405 S.W.3d 950 (Court of Appeals of Texas, 2013)
Narvaez v. Wilshire Credit Corp.
757 F. Supp. 2d 621 (N.D. Texas, 2010)
American Title Co. of Houston v. Bomac Mortgage Holdings, L.P.
196 S.W.3d 903 (Court of Appeals of Texas, 2006)
Dorsett v. Cross
106 S.W.3d 213 (Court of Appeals of Texas, 2003)
Dorsett, William Grant v. Nancy Swanson
Court of Appeals of Texas, 2003
R.C. Small & Associates, Inc. v. Southern Mechanical, Inc.
730 S.W.2d 100 (Court of Appeals of Texas, 1987)
State v. Buckner Construction Co.
704 S.W.2d 837 (Court of Appeals of Texas, 1985)
Roy E. Thomas Construction Co. v. Arbs
692 S.W.2d 926 (Court of Appeals of Texas, 1985)
Texas Power & Light Co. v. Barnhill
639 S.W.2d 331 (Court of Appeals of Texas, 1982)
Jeffery v. Neville
620 P.2d 1218 (Montana Supreme Court, 1980)
Miracle Candle Co. v. International Paper Co.
600 S.W.2d 365 (Court of Appeals of Texas, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
523 S.W.2d 771, 1975 Tex. App. LEXIS 2701, Counsel Stack Legal Research, https://law.counselstack.com/opinion/longview-construction-development-inc-v-loggins-construction-co-texapp-1975.