Black v. Acers

178 S.W.2d 152
CourtCourt of Appeals of Texas
DecidedNovember 26, 1943
DocketNo. 13442.
StatusPublished
Cited by10 cases

This text of 178 S.W.2d 152 (Black v. Acers) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Black v. Acers, 178 S.W.2d 152 (Tex. Ct. App. 1943).

Opinions

Appellant's suit against defendant contractors was based upon an alleged failure to build a house according to plans and specifications; and the jury answers were favorable to plaintiff, fixing damages in the sum of $1,500. Thereafter, defendants' motion non obstante veredicto was heard and sustained, followed by judgment that plaintiff take nothing, and this appeal. Jury findings were, in effect, that A. E. Acers had failed to construct the dwelling and improvements at 3453 Amherst Street in substantial compliance with plans and specifications, and to meet Federal Housing Administration requirements, in that foundation, driveway and approach thereto were not constructed according to specifications and not properly reinforced; that the downspouts and gutters shown in plans and specifications were not eliminated therefrom by agreement; that plaintiff was damaged by failure of defendant Acers to *Page 153 construct the improvements according to plans and specifications, or to meet F.H.A. requirements; that the difference in the reasonable cash market value of the house and improvements in question (a) as constructed at the time of completion, and (b) if the same had been completed according to plans and specifications was $1,500; that before plaintiff and wife had executed their written instrument of acceptance, defendant Acers represented to plaintiff that said house had been constructed according to plans and specifications, which representation was false but believed in and relied upon by plaintiff at the time; that neither plaintiff nor wife, at any time before execution of the instrument of acceptance, had full knowledge of aforesaid defects in construction, and were induced to sign the acceptance because of defendants' said representation; and that A. E. Acers and J. H. Garrett were partners in the work.

In August, 1938, plaintiff submitted to Acers blue prints or plans for a dwelling on his Amherst lot, under which the latter's bid or contract price was $5,300. Typed specifications were drafted and signed pursuant thereto, the arrangement being subject to a Federal Housing loan then applied for. This agency suggested several changes, reducing the cost, which was agreed to along with a bid by Acers of $4,800; and a construction loan in amount of $4,400 was approved by F.H.A. The improvements were completed in November, plaintiff's letter of acceptance obtained by Acers, and the F.H.A. guaranteed loan of $4,400 was taken up by a third party. The instant suit, setting forth in detail above mentioned specifications, alleging substantial failure to perform same, and defective workmanship in various particulars, was filed in October, 1939, and damages were claimed in amount of $2,500.

An introductory paragraph of what may be termed the "Black-Acers Building Contract," provides: "The following specifications are intended to cover in a general way all materials and labor necessary for the erection and completion of a Brick six room Cottage built to meet requirements of the Federal Housing Administration."; and in subsections touching "excavation," "footing and piers," "cement walks, steps, driveways, etc.," these specifications included such expressions as "to meet" or "to comply with" F.H.A. requirements. Stamped on one set of plans and specifications in evidence were the words, "Property of Federal Housing Administration. These documents are to be kept on job at all times, otherwise inspections cannot be made." As construction progressed, F.H.A. inspectors regularly visited the job, duly filing office reports of compliance inspections, all supervised by Arch Baker, chief architect, whose endorsement appears on the certificate finally approving the construction. No claim of fraud or bad faith is made concerning inspections on part of F.H.A. representatives, including this certificate of Mr. Baker, its supervising architect. Appellees' assertion of a complete defense to plaintiff's cause of action is predicated upon above quoted terms of the contract, aided by the undisputed facts just stated, as will be shortly discussed.

On the other hand, if not precluded by contract provisions (the plans and specifications), it is manifest from the record that fact questions were raised on all issues submitted to the jury and by them answered in plaintiff's favor. Relative to a substantial compliance by the contractors with building plans and details, plaintiff's witness, Chas. T. Hansen, experienced in house-moving and reinforcing foundations, testified at length. However, the gist of his narrative was that some month or two before trial (October, 1942), he had been employed by plaintiff to uncover three concrete piers set by Acers under a front corner of said dwelling, in order to determine, if possible, the cause of numerous cracks in outside walls, pulling of brick away from windows, and conspicuous breaking of plaster on inside walls and ceilings; that he excavated to a depth of more than seven feet and found one pier loose in the excavation, falling down of its own weight when exposed, another pier breaking as it was being removed from the hole; that plans called for a one-half inch steel rod through the center and entire depth of each pier, but that such rod extended only halfway; in one instance protruded from side of the pier some eight inches; further, that the plans required a flare at base of each pier to width of 16 inches, whereas, their diameter was 10 inches throughout; the witness here stating:

"Q. Now then, Mr. Hansen, look at those plans, Plaintiff's Exhibit No. 1 and, taking into consideration those plans and the specifications that you have already read, did the piers that you took out from under this house at 3453 Amherst Street meet the requirements of those plans and specifications? A. No, sir. *Page 154

"Q. Will you state to the Court and jury in what manner they failed to meet the requirements of those plans and specifications? A. For two reasons: One was the steel shown here on the plans, shows reinforcing to run to the bottoms of those pilings, and they ran halfway; secondly, it showed it to be flared or under-reamed at the bottom to a width of 16 inches, or a diameter, of which it wasn't when I dug them up."

Over some 100 pages of the statement of facts, this witness testified to his findings and repair work done on above occasion; a corner of the house being lifted three-fourths of an inch to secure uniform level; that he had put in a new pier and concrete footing, and that plaintiff's trouble had been caused by settlement of foundation on all sides. Hansen's estimate of the reasonable cost of repairs to accord with plans and specifications was between $1,545 and $1,595. When the instrument of acceptance was signed, plaintiff testified that he had no knowledge of the alleged defects in construction, though he knew that F.H.A. had finally approved the work.

Above outline of testimony, without more, constitutes sufficient basis for all jury findings, aside from contract provisions, the proper construction of which is concededly the controlling issue for our determination. Aforesaid specifications provide that plaintiff's dwelling shall be built "to meet requirements of the Federal Housing Administration," such phrase being repeatedly used in the writing; and appellees contend that the effect thereof was the mutual designation of F.H.A., through its representatives, to supervise construction of the house, whose judgment that building requirements had been met was final in absence of fraud or bad faith. The rule thus sought to be invoked has application to contracts wherein the parties have bound themselves to abide by decisions of the architect or other person entrusted with authority of superintendence. City of San Antonio v. McKenzie Const. Co., 136 Tex. 315

Free access — add to your briefcase to read the full text and ask questions with AI

Related

NL Industries, Inc. v. GHR Energy Corp.
934 F.2d 580 (Fifth Circuit, 1991)
Liquid Energy Corp. v. Trans-Pan Gathering, Inc.
758 S.W.2d 627 (Court of Appeals of Texas, 1988)
Lake LBJ Municipal Utility District v. Coulson
692 S.W.2d 897 (Court of Appeals of Texas, 1985)
Longview Construction & Development, Inc. v. Loggins Construction Co.
523 S.W.2d 771 (Court of Appeals of Texas, 1975)
Delhi Pipeline Corporation v. Lewis, Inc.
408 S.W.2d 295 (Court of Appeals of Texas, 1966)
Eckert-Fair Construction Company v. Flabiano
342 S.W.2d 629 (Court of Appeals of Texas, 1960)
Morrison v. St. Anthony Hotel, San Antonio
274 S.W.2d 556 (Court of Appeals of Texas, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
178 S.W.2d 152, Counsel Stack Legal Research, https://law.counselstack.com/opinion/black-v-acers-texapp-1943.