Eckert-Fair Construction Company v. Flabiano

342 S.W.2d 629, 1960 Tex. App. LEXIS 1907
CourtCourt of Appeals of Texas
DecidedDecember 9, 1960
Docket15687
StatusPublished
Cited by6 cases

This text of 342 S.W.2d 629 (Eckert-Fair Construction Company v. Flabiano) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eckert-Fair Construction Company v. Flabiano, 342 S.W.2d 629, 1960 Tex. App. LEXIS 1907 (Tex. Ct. App. 1960).

Opinion

THOMAS, Justice.

This is a building and construction contract case. Appellant Eckert-Fair Construction Company, Inc., was the general contractor for the erection of the Library and Administration Building, of Kilgore College, at Kilgore, Texas. Mike Flabiano, doing business as the American Terrazzo Company, was the subcontractor to install the terrazzo floor work specified in Section 24 of the General Specifications.

Appellant, as plaintiff below, sued its subcontractor and alleged that the appellee failed to perform his subcontract in the following respects: (1) to the satisfaction of the architect; (2) to the satisfaction of the appellant; (3) in a good and workmanship manner; (4) in accordance with the Specifications. Particularizing under 3 and 4, appellant detailed some eight instances in which the appellee failed to perform the work in accordance with the Specifications. Appellant further alleged that because of appellee’s failure the terrazzo floor of the building cracked, crumbled and disintegrated and as a result thereof the architect decided that the work had to be replaced in a manner in accordance with the Specifications and in a manner satisfactory to the architect; that appellee refused to correct the defective work, and that appellant was compelled to, and did, tear out the defective work and caused it to be done over again in such manner as would conform to the contract and would satisfy the requirement of the architect-engineer; that in doing so appellant actually and necessarily expended the sum of $13,028.73 for which he sued after crediting the unpaid balance due on appellee’s contract.

Appellee denied specially that he had failed to perform his subcontract as alleged by appellant. He alleged that wherever he varied from the letter of the General Specifications such was done with the consent and agreement of the architect-engineer and appellant; that the terrazzo floor in question was built according to the plans and specifications and to the satisfaction of the architect-engineer and of the appellant; that after he had completed the terrazzo work it cracked for reasons other than the performance of the appellee, but because of an upheavel or shifting in the foundation upon which appellee had to lay the floor; that the foundation was not part of the work required to be done by the appellee; that the floor laid by appellant after it had removed the floor constructed by appellee also had cracked in substantially the same manner as the floor originally installed by the appellee, and that the architect-engineer had accepted that floor.- Finally, appellee, by cross-action, sued for the unpaid balance due on his contract together with attorney’s fees.

The case was tried to a jury which returned into court its answers to special issues submitted to them. The jury found that appellee did perform the work in accordance with the plans and specifications, or as varied by agreement, in each of the particulars complained of by the appellant. Furthermore, the jury found (using the numbers of the special issues); 7. That appellee did lay the terrazzo floor to the complete satisfaction of the inspectors and supervisors of the architect-engineer; 8. That he did furnish the material for and *631 complete the work of laying the terrazzo floor to the complete satisfaction of the architect, Preston M. Geron; 9. That ap-pellee completed the work of laying the terrazzo floor to the complete satisfaction of appellant; 12. That the damages complained of by the appellant were caused by soil conditions existing under the building in which the terrazzo floors were constructed; 13. That the damages complained of were caused by defects in the concrete slab over which the terrazzo floors were laid, which occurred after the terrazzo floors were completed.

By the express terms of the subcontractor appellee agreed to furnish all necessary tools, apparatus, labor and material and perform all work required to construct and complete all terrazzo work per Section 24 of the Specifications for the Library and Administration Building, Kilgore College, Kilgore, Texas, in accordance with plans and specifications and addenda prepared by Preston M. Geron, Architect-Engineer. All conditions of the contract between Kilgore College Board of Trustees and appellant were “Made a part of” the subcontract. The subcontract also specifically provided: “(a) By this contract the subcontractor agrees to complete the above mentioned items to the complete satisfaction of the inspectors and supervisors of the architect-engineer * * * ”. “ * * * (b) the subcontractor agrees to furnish such material and complete his work * * * to the complete satisfaction of the Contractor and the Architect.”

By its first four points of appeal (all of which we must overrule) appellant contends that it was entitled' to judgment notwithstanding the verdict because the work done by appellee was rejected and its removal and replacement ordered by decisions of the architect and his inspectors, as well as by appellant, as unsatisfactory, which decisions were binding on appellee in the absence of pleading and proof that they were arbitrary or unreasonable. This requires a construction of the provisions of the subcontract that appellee’s work was to be done to the complete satisfaction of appellant, the architect and his inspectors.

There is no provision of the subcontract making the decisions of the architect or appellant final and binding. On the contrary, Art. 40 of the General Specifications provides that only “the architect’s, decisions, in matters relating to artistic effect, shall be final, if made within the terms of the Contract Documents”; otherwise, unless expressly provided “all the Architect’s decisions are subject to arbitration”. It is not contended that any decision relating to “artistic effect” is involved. The arbitration procedure outlined in the Specifications was not invoked by either party even though it was agreed therein “that the decision of the arbitrators shall be a condition precedent to any right of legal action that either party may have against the other.” However, no point is made that appellant cannot maintain its suit or ap-pellee his cross-action. There are no provisions of the Contract Documents regarding the effect of decisions of the contractor or the architect’s inspectors.

In Black v. Acers, Tex.Civ.App., 178 S.W.2d 152, 154, Writ of Error Refused, this court considered a case which was practically the reverse of this one. There the contractor agreed the house should be “built to meet requirements of the Federal Blousing Administration”, and it was undisputed that all F.H.A. requirements had been met and its construction supervisors on the job had approved the house. However, a jury found that the contractor failed to build the house according to plans and specifications in certain respects. The trial court, notwithstanding the verdict, entered judgment for the contractor, sustaining the defense that since the F.H.A. had certified the house as built met its requirements, the effect of the certification was to constitute such agency the final arbiter in all matters touching performance of the contract. In an opinion by Justice Young, we reversed and rendered judgment for the owner against the contractor. Although we recognized *632 that the parties might bind themselves to abide by the decisions, certifications, etc., of an architect or third person the opinion quoted with approval from 54 A.L.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Escajeda v. Cigna Insurance Co. of Texas
934 S.W.2d 402 (Court of Appeals of Texas, 1996)
Nordin Construction Company v. City of Nome
489 P.2d 455 (Alaska Supreme Court, 1971)
Delhi Pipeline Corporation v. Lewis, Inc.
408 S.W.2d 295 (Court of Appeals of Texas, 1966)
Rogers v. Stimson Contracting Company
373 S.W.2d 548 (Court of Appeals of Texas, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
342 S.W.2d 629, 1960 Tex. App. LEXIS 1907, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eckert-fair-construction-company-v-flabiano-texapp-1960.