G., H. & S. A. R'y Co. v. Henry & Dilley

65 Tex. 685, 1886 Tex. LEXIS 729
CourtTexas Supreme Court
DecidedJune 25, 1886
DocketCase No. 2040
StatusPublished
Cited by46 cases

This text of 65 Tex. 685 (G., H. & S. A. R'y Co. v. Henry & Dilley) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G., H. & S. A. R'y Co. v. Henry & Dilley, 65 Tex. 685, 1886 Tex. LEXIS 729 (Tex. 1886).

Opinion

Willie, Chief Justice.

The appellant’s assignments of error question the judgment of the court below, only so far as it allows to Henry & Billey the sum of $32,737.50 for one hundred and nine thous- and one hundred and twenty-five cubic yards of hard rock hauled and embanked for the railway company, and ten per cent, upon that sum as a bonus for the early completion of the work. If the allowance of the principal sum above stated is correct, there is no doubt as to the right of the appellees to the ten per cent, bonus, as the whole work contracted for was completed within such time as entitled them to the additional amount claimed, under the terms of the agreement.

The right to the principal sum depends upon whether the amount of rock hauled and embanked by the appellee is to be determined by measuring the excavation from which it was taken, or the embankment of which it formed part, after being hauled. The appellant [688]*688contends that the former, and the appellees that the latter, should be estimated. The proof shows that the rock embanked will measure fifty per cent, more than before it is quarried, and this difference amounts to the one hundred and nine thousand one hundred and twenty-five cubic yards upon an estimate of the entire solid rock work done by the appellees under their contract.

The court accepted the views of the appellees, and, hence, its judgment in their favor for the hauling and embanking of the one hundred and nine thousand one hundred and twenty-five cubic yards of rock, and the ten per cent, bonus thereon. The contract, itself, does not state in terms as to whether the pit or the embankment is to be resorted to in making the measurement. It purports to attach as part thereof some specifications, by which the work is to be performed, and these specifications provide, among other things, that “the measurement of quantities will usually be made in the cuts, or pits, from which the material has been taken.”

The contract further provides, as follows: “The quantities and and amounts of the several kinds of work performed under this contract shall be determined by the chief engineer, or by an assistant engineer acting under his direction; and his determination shall be conclusive upon both parties.”

The appellant contends that the specifications, as above quoted, fix the manner of making the estimates; and, if not, that the contract, itself, leaves this to the decision of the chief engineer, or his assistant. And these officers, having made their estimates by measuring the excavations, they have thereby determined this to be the meaning of the contract, and the appellees are bound by this decision. It is further urged by the company that the usage of itself and other companies, in the light of which usage the contract must be interpreted, has always been to measure the excavation, and not the embankment, in settling with contractors; and the appellant further relies upon the fact, that Henry & Dilley settled with it upon estimates based upon a measurement of the pits, and thereby ratified the action and decision of the engineers.

A question, preliminary to the consideration of these defences, arises upon an objection taken by the appellees to the right of the company to make them under the general denial—the only answer filed by it to the petition. "We-think that so far as the defences founded upon the award of the engineer, the provisions of the specifications, and the usage of railway companies are concerned, they could properly be urged under a general denial, as applied to the allegations of the petition. The petition set forth the contract, including [689]*689the agreement as to what the engineer should decide; it sets forth his decision, but alleges that it is not based on such measurement of the rock as appellees are entitled to, under their contract, and such as is usual and customary under like contracts.

A denial of these allegations put the plaintiffs below upon proof of their contract, and of the failure of the engineer to comply with it in making the measurement, and of the usage alleged by them. Evidence that no such contract was made, or that the engineer was-, authorized by its terms to determine how the measurement should be made, or that the specifications, which the petition alleged were part of the contract, provided that the measurement should not be of the embankment, as claimed in the petition, but of the pits, or that the usage was contrary to what it was averred in the petition to be, would be in denial of its allegations, and admissible under the general denial. But, if the defendant proposed to show that, admitting-the allegations to be true, the plaintiffs had ratified and endorsed the action and estimates of the engineer, by accepting and settling by them with the company, without reservation or protest, this would amount to a plea of confession and avoidance, and was not admissible upon the only answer set up by the defendant to the petition. Had objection to this evidence been made, it should have been excluded.

It is proper, however, to add, that the proof received by the court upon this question does show that, upon making thefinal settlement, the chief engineer told the appellees that if his men had made a mistake, or errors in measurement, it should be corrected. The estimates were, therefore, accepted with this reservation, and were not ratified by the contractors.

We think the evidence shows, with sufficient certainty, and without contradiction, that the estimates were furnished to the contractors, although they were not attached to the contract. It is true that Mr. Dilley, one of the contractors, says that he never saw them until within a month or two of the time when the contract was completed. But it further appears that he was not the person who supervised the work, or who staid upon the ground when it was being performed. His partner, Henry, did this, and he was the person most likely to be in possession of the paper. It was not found among his papers when they were turned over to Mr. Dilley; but this does not, of course, furnish satisfactory proof that he had never had this particular paper. On the contrary, it is hardly probable that contractors, who were to receive several hundred thousand dollars, provided certain work to be done by them conformed to specifications to be furnished them, [690]*690and who might lose large sums if it did not, would undertake the performance of the work in utter ignorance of these specifications. It is difficult for belief to be accorded to a thing so utterly improbable, especially when not .sustained by positive testimony. Major Com verse states, positively, that the specifications were delivered to Henry & Dilley. These, together with blank forms of contracts, were furnished them to use with their sub-contractors, and that these, thus used, were the ones introduced, on the trial, by the appellant company. This positive testimony is strengthened by the statement of one of the sub-contractors, who told Dilley that there were, or had been, specifications. Opposed to these and other convincing proofs that one of the contractors, at least, had been furnished with the specifications, is the mere negative testimony to the effect that the other contractor had not seen them, and did not know that his partner had.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Southern Land Development Co.
385 S.W.2d 552 (Court of Appeals of Texas, 1964)
Smith v. Barnett
373 S.W.2d 762 (Court of Appeals of Texas, 1963)
Johnson v. American Can Company
361 S.W.2d 451 (Court of Appeals of Texas, 1962)
Hooks v. Cook
345 S.W.2d 592 (Court of Appeals of Texas, 1961)
Eckert-Fair Construction Company v. Flabiano
342 S.W.2d 629 (Court of Appeals of Texas, 1960)
City of San Antonio v. Meader
326 S.W.2d 557 (Court of Appeals of Texas, 1959)
Haddad v. Bagwell
317 S.W.2d 781 (Court of Appeals of Texas, 1958)
Couey v. Arrow Coach Lines, Inc.
288 S.W.2d 192 (Court of Appeals of Texas, 1956)
Morrison v. St. Anthony Hotel, San Antonio
274 S.W.2d 556 (Court of Appeals of Texas, 1955)
Super-Cold Southwest Co. v. First Baptist Church of Corsicana
219 S.W.2d 569 (Court of Appeals of Texas, 1949)
Black v. Acers
178 S.W.2d 152 (Court of Appeals of Texas, 1943)
Reed v. Markland
173 S.W.2d 346 (Court of Appeals of Texas, 1943)
Austin Bridge Co. v. Teague
152 S.W.2d 1091 (Texas Supreme Court, 1941)
City of San Antonio v. McKenzie Construction Co.
150 S.W.2d 989 (Texas Supreme Court, 1941)
Austin Bridge Co. v. Teague
149 S.W.2d 674 (Court of Appeals of Texas, 1941)
Martin Bros. v. State
146 S.W.2d 782 (Court of Appeals of Texas, 1940)
Gifford-Hill & Co. v. Jones
99 S.W.2d 656 (Court of Appeals of Texas, 1936)
American Surety Co. of New York v. Shaw
69 S.W.2d 47 (Texas Commission of Appeals, 1934)
Leon v. Gulf Production Co.
35 S.W.2d 1101 (Court of Appeals of Texas, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
65 Tex. 685, 1886 Tex. LEXIS 729, Counsel Stack Legal Research, https://law.counselstack.com/opinion/g-h-s-a-ry-co-v-henry-dilley-tex-1886.