Reed v. Markland

173 S.W.2d 346, 1943 Tex. App. LEXIS 491
CourtCourt of Appeals of Texas
DecidedJune 10, 1943
DocketNo. 2514.
StatusPublished
Cited by9 cases

This text of 173 S.W.2d 346 (Reed v. Markland) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reed v. Markland, 173 S.W.2d 346, 1943 Tex. App. LEXIS 491 (Tex. Ct. App. 1943).

Opinion

HALE, Justice.

This is a suit for damages on account of the breach of a sales agreement. On June 24, 1941, the United States Government entered into a contract with L. P. Reed for the construction of an airport to be located near Waco, Texas. In connection therewith, Reed desired to purchase certain asphalt paving materials prepared and mixed in accordance with the specifications contained in the construction contract, and to that end he entered into a written sales agreement with Ii. L. Mark-land on November 21, 1941. By the terms of the sales agreement, Markland undertook at his own expense to provide a standard hot asphalt plant of 1,500 pounds batch capacity to be located in Waco, to furnish and apply the tack coat on .the surfaces to be paved at the airport, to prepare and mix approximately 27,000 tons of paving materials as called for in the contract therein referred to, and deliver the same at the worksite, deliveries to begin not later than December, 8, 1941, and to continue thereafter at an average of 300 tons per working day until completion, and in consideration thereof Reed agreed to pay $3.35 per ton for such materials.

In his original trial petition Markland pleaded verbatim the sales agreement declared upon and alleged that at the time the same was entered into he was the owner of an extensive asphalt mixing plant then located in Corsicana, approximately sixty miles distant from Waco; that he immediately dismantled his plant at Cor-sicana, moved it to Waco where it was re-assembled and set up in compliance with the sales agreement, constructed an adequate laboratory and completely equipped it, employed technical experts and laborers,, purchased and had removed to his plant large quantities of asphalt, gravel, sand and other materials necessary to the production and delivery required under the-agreement, and on December 6, 1941, began the application of the tack coat on the surfaces to be paved; that on or about December 8, 1941, he had completed his plant, complied with his part of the agreement up to that date, and stood ready, able and willing to discharge all further obligations resting upon him thereunder; that in the alternative, if his plant was not completed before December 8, 1941, it was completed and he was ready to begin deliveries before Reed was ready to receive the same; and that, after complete compliance by him with his part of the agreement, Reed notified him by letter on December 11, 1941, he would not accept deliveries of the materials contracted for, thereby breaching the agreement, to plaintiff’s damage in the sum of $25,000, for which amount he sued.

Reed answered with special demurrers and exceptions, a general denial and affirmatively pleaded that the sales agreement sued upon was corollary to his construction contract with the government; that under certain pleaded terms contained in the government contract, plaintiff’s asphalt mixing plant was subject to the inspection and approval of United States Engineers; that on December 10, 1941, Lieutenant Kirk of the United States Engineers (hereinafter referred to as the engineer) inspected plaintiff’s plant and found it was not up to the standard required in the government contract, but was defective in that (1) the plant was not of 1,500 pounds batch capacity, (2) there were no tell-tale *349 indicators on the aggregate scales, (3) the pug mill was not equipped with a spray bar, and (4) the engineer required plaintiff to' furnish the factory rated capacity of his pug mill; that the engineer and defendant waived the right to then cancel the sales agreement with plaintiff on account of such defects but waited until December 19, 1941 when, by reason of the failure of plaintiff to comply with the requirements of the engineer, his plant was rejected; and that the failure of plaintiff to provide a plant in keeping with such requirements constituted a breach on his part of the sales agreement.

In his first supplemental petition, Mark-land denied his plant was subject to the inspection or approval of the United States Engineers under the terms of the sales agreement, but alleged, in the alternative, that if it was, then the first and only inspection made thereunder was on December 10, 1941, at which time the engineer found the plant met the requirements of the government contract except in two particulars, viz.: (1) There were no telltale indicators on the scales, and (2) there was no spray bar over the pug mill; that the engineer directed the installation of tell-tale indicators, which was immediately done, and the engineer waived the installation of the spray bar; that notwithstanding the approval of his plant by the engineer, Reed notified him, on December 11, 1941, of his intention not to receive delivery of the asphalt mix, thereby breaching the sales agreement; and that, if the engineer did reject his plant or make objections thereto as alleged by defendant, then such objections were fictitious, arbitrary and false and were made as the result of such gross mistake and failure to exercise an honest judgment as to amount to bad faith, and were so made at the instance of and in collusion with defendant. Each party thereafter filed additional trial pleadings which in their entirety cover 78 pages in the transcript.

The jury found on special issues that plaintiff provided a standard hot asphalt plant of 1,500 pounds batch capacity in Waco by December 8, 1941 and before the rún-ways at the airport were ready to receive asphalt; when the engineer inspected plaintiff’s plant on December 10, 1941, the same was in all material respects in compliance with the requirements of the United States Government, and at that time the engineer did not refuse to approve the plant, his only requirement being that plaintiff install tell-tale indicators, which requirement was thereafter met within a reasonable time and before the engineer rejected the plant; defendant had notified plaintiff at a time when defendant did not have his run-ways ready to receive asphalt and before the engineer rejected the plant that plaintiff would not be permitted to perform his part of the agreement; the engineer told plaintiff on December 10, 1941, it was not necessary to install a spray bar unless it was found to be necessary later during the operation of the plant and he thereafter failed to request plaintiff to install said spray bar before the rejection of the plant by him; the pug mill of plaintiff’s plant had a capacity to mix 1,500 pounds of asphalt mixture in one batch, plaintiff knew such capacity and informed the engineer thereof; the act of the engineer in rejecting the plant after the tell-tale indicators were installed, his act in rejecting the plant without requesting plaintiff to install a spray bar, and his act in rejecting the plant on the ground that plaintiff did not know its capacity, was each an arbitrary act on his part, and defendant conspired with the engineer in each of such arbitrary acts; and that plaintiff would have produced and delivered the asphalt paving mixture as provided for in his sales agreement at a cost to him of $2.89 per ton if his plant had not been rejected. Upon the verdict of the jury, the court rendered judgment in favor of plaintiff for the sum of $12,420 and defendant has appealed.

Appellant contends under the 25 points upon which his appeal is predicated that the court erred (1) in overruling his special demurrers and exceptions to the pleadings of appellee, (2) in overruling his objections to the admissibility of certain testimony, (3) in refusing his request for a peremptory instruction, and (4) in submitting and refusing to submit certain issues to the jury.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Day v. Garland Chrysler-Plymouth, Inc.
460 S.W.2d 272 (Court of Appeals of Texas, 1970)
Rothermel v. Duncan
365 S.W.2d 398 (Court of Appeals of Texas, 1963)
Sargent v. Williams
258 S.W.2d 787 (Texas Supreme Court, 1953)
Phipps v. Evans
255 S.W.2d 893 (Court of Appeals of Texas, 1953)
General Insurance v. Hughes
255 S.W.2d 193 (Texas Supreme Court, 1953)
Najera v. Great Atlantic & Pacific Tea Co.
207 S.W.2d 365 (Texas Supreme Court, 1948)
Felder v. Houston Transit Co.
203 S.W.2d 831 (Court of Appeals of Texas, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
173 S.W.2d 346, 1943 Tex. App. LEXIS 491, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reed-v-markland-texapp-1943.