Martin Bros. v. State

146 S.W.2d 782
CourtCourt of Appeals of Texas
DecidedDecember 31, 1940
DocketNo. 8955.
StatusPublished
Cited by6 cases

This text of 146 S.W.2d 782 (Martin Bros. v. State) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martin Bros. v. State, 146 S.W.2d 782 (Tex. Ct. App. 1940).

Opinion

BAUGH, Justice.

The parties will be designated as in the trial court.

The plaintiffs, road contractors, under permission granted by Resolution of the Legislature to do so, sued the State for $10,-950.64, on a contract for the construction of approximately 1'5 miles of State Highway in Liberty County. The claim asserted consisted of two items: One for $3,-090.64, claimed as due them, under the terms of the contract, for dirt moved by them in the construction of the road, for which the State refused to pay; and the other for $7,500 additional compensation *784 by way of damages for extra work made necessary because of changes made by the State Highway Engineer in.the plans and specifications upon which bids' were asked by the State, and after the contract was entered into. The changes so made by the engineer were alleged to have made the performance of the • contract by appellants more onerous and expensive than the original contract required. Trial was to a jury, but at the close of plaintiffs’ evidence, upon the State’s motion, a verdict was instructed against the plaintiffs and judgment rendered that they take nothing; hence this appeal.

The first item relates entirely to the actual quantities of dirt moved by the contractors in performing their contract. Two ■ classes of excavation were involved: “Common roadway excavation” and “Borrow,” —the latter being dirt necessary to be taken from drainage ditches and placed in the fill or roadway proper. In the plans and specifications for the job prepared by the Highway Engineer, and-furnished prospective bidders upon which to make their bids, the amount of “common roadway excavation” necessary to be made was estimated at 146,917 cubic yards; and that of “Borrow” at 46,220 cubic yards. Under their bid and the contract, the plaintiffs were to be paid 11 cents per cu. yd. for moving the former; and 14 cents per cu. yd. for moving the latter class of material. The job was completed and accepted by the State, and, according to the final estimate of the Highway Engineer, plaintiffs moved 155,-256 cu. yds. of “common” excavation and 43,940 cu. yds. of “Borrow”, for which they were paid at the contract price. Plaintiffs alleged, however, and offered evidence to show that they had in fact moved 177,476 cu. yds. of “common” and 47,940 cu. yds. of “Borrow”, for which they were entitled under the contract to be paid, making the sum claimed as still due them for actual work done under the contract on this item of $3,090.64.

The other item of $7,500 sustained by pleading and proof was that in the plans and specifications, drawn in detail by the Highway Engineer and furnished bidders as a b'asis for their bids, there were designated on the entire 15 miles of roadway, only 26 trees to be left between the roadway and the edge of the right of way, and these were specifically -located on the plans. It was shown that in response to a questionnaire required by the Highway Department to be filled out by the bidder, and treated ás a warranty, disclosing the character of machinery the bidder had, his ability to perform'such contract, and the manner in which he proposed to perform it, the plaintiffs recited and advised the Highway Department, which was the basis for their low bid on the project, that they would do the grading and drainage work with heavy machinery consisting of an elevated grader and drag line. After the contract was executed and 'plaintiffs had begun work, the Highway Engineer caused to be designated and marked 334 other trees situated alongside the roadway to be left and directed plaintiffs not to remove them. Because of their number and location on the right of way, it then became impossible for plaintiffs to use their heavy machinery in moving the dirt required to be moved, of which fact the Highway Engineer was apprized and well knew; and that because of such change of plans by the engineer, and to meet his instructions and demands plaintiffs were then compelled to do most of such work with plows and fresnoes drawn by mules, to remove dirt from around such trees so as not to injure them, thus necessitating more laborers and much heavier expense to the plaintiffs than the original plans and methods of work required or called for; and that as a result, because of the change made by the engineer, the plaintiffs were required to expend, in performing their contract, at least $7,500 more than would have been necessary had the plans and specifications been left as they were when the contract was made.

In addition to general and special exception's, and general and special denials, the State defended on the grounds that the matter of leaving or removing trees from the right of way came within the portion of the contract relating to grubbing and clearing the right of way contracted for by the acre and for which the plaintiffs had already been paid in full. Also that the contract provided that all disputes between the parties should be decided by the engineer whose decision would be final and binding; and, in effect, that the engineer having decided the matters here involved against the plaintiffs, they are without recourse or remedy.

The State Highway Department’s Standard Specifications attached to and made a *785 part of the contract contained, among numerous other provisions, the following:

“5.1. Authority of Engineer. The work will he done under the supervision of the Engineer, to his satisfaction, and in accordance with the contract, plans and specifications. The Engineer will decide all questions which may arise as to the quality or acceptability of materials furnished and work performed; the manner of performance and rate of progress of the work; the interpretation of the plans and specifications; and as to the acceptable fulfillment of the contract on the part of the Contractor. His decisions will be final and he will have executive authority to enforce and make effective such decisions and orders as the Contractor fails to carry out promptly.
“5.2. Engineer as Referee. The Engineer will act as referee in all questions arising under the terms of the contract between the parties thereto and his decisions shall he final and binding.”

These provisions thus become a part of the contract, and since plaintiffs, in so far as the first item above indicated is concerned, sued upon the contract they necessarily must be held to have affirmed it. If we properly understand the plaintiffs’ contention it is that this attempted delegation of such authority to the engineer is void because it undertakes to vest in him judicial authority.

It is now settled law, however, that such a provision in a building contract is valid and binding. As stated in 9 Am. Jur., § 36, p. 26: “It may be stated generally that any stipulation whereby the par-tías constitute an architect or engineer the final arbiter between themselves, as to any matter connected with the contract, makes the decision of the architect or engineer conclusive as to, such matter.”

This rule seems to be universally recognized, except, perhaps, in Indiana. See numerous annotations in 54 A.L.R. 1255 et seq.; supplemented by annotations in 110 A.L.R. 137 et seq.; 4 Tex.Jur., § 10, p. 718; 7 Tex.Jur., § 14, p. 554; Schoenfeld v. De Puy, Tex.Civ.App., 58 S.W.2d 574; McKenzie Const. Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

NL Industries, Inc. v. GHR Energy Corp.
932 F.2d 422 (Fifth Circuit, 1991)
Manes v. Dallas Baptist College
638 S.W.2d 143 (Court of Appeals of Texas, 1982)
State of Texas v. Martin Bros.
160 S.W.2d 58 (Texas Supreme Court, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
146 S.W.2d 782, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martin-bros-v-state-texapp-1940.