Galveston, Harrisburg & San Antonio Railway Co. v. Johnson

11 S.W. 1113, 74 Tex. 256, 1889 Tex. LEXIS 930
CourtTexas Supreme Court
DecidedJune 7, 1889
DocketNo. 6188
StatusPublished
Cited by36 cases

This text of 11 S.W. 1113 (Galveston, Harrisburg & San Antonio Railway Co. v. Johnson) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Galveston, Harrisburg & San Antonio Railway Co. v. Johnson, 11 S.W. 1113, 74 Tex. 256, 1889 Tex. LEXIS 930 (Tex. 1889).

Opinion

Gaines, Associate Judge.

This suit was brought by appellee to recover of the appellant corporation a balance alleged to be due upon a contract for grading a part or its road. The petition, after setting forth the execution and terms of the contract, alleges that the plaintiff complied in all respects with its stipulations as to five sections of the road and admits a full payment therefor by defendant except in two particulars. It is averred that by the terms of the agreement the plaintiff was to receive for rock embankment thirty cents per cubic yard, to be actually measured in the embankment, and for overhaul ” on the material in the embankment two cents per cubic yard per hundred feet, to be estimated by the same measurement. By overhaul ” we understand is meant the distance in excess of one hundred feet that the material was transported. The [259]*259petition admits a partial payment for the rock embankment and for the overhaul on that work.

The defendant pleaded a general denial, and also denied specially that under a proper construction of the contract it was liable to plaintiff in any amount beyond that which had been paid. There were other matters alleged in defense that will be considered in another part of the •opinion.

We think the determination of the case in this court depends upon the construction of the written agreement between the parties. There is but little conflict in the evidence. The facts upon the main issues are undisputed. The testimony shows that the rock embankments were made almost wholly from the material taken from the'cuts, and that after being placed in the embankment the cubic contents of the embankment was about fifty per cent more than the contents of the excavation from which it was taken; for example, when the excavation in solid rock measured 6000 feet the embankment made with the rock taken from it would measure 9000 feet.

The plaintiff claimed that under the terms of the contract in estimating his compensation both for the enbankment itself and for the overhaul of the rock which composed it the actual measurement of the ■embankment was to be taken; while on the other hand defendant claimed that he was to be paid by excavation measure. If thé defendant’s construction of the contract is correct, then it is not disputed that the plaintiff has been fully paid. If, however, the construction claimed by plaintiff be the true one, the evidence shows beyond controversy that he is entitled to the full amount claimed in his petition and awarded him by the verdict of the jury. The testimony of the only witness introduced by defendant as to the quantity of the embankments would have given .him more than he claimed, if he was to be paid by the actual measurement of the rock embankments.

The following is the stipulation in the contract as to the compensation to be paid for the work:

“And the party of the second part (appellant) hereby covenant and agree that whenever in the opinion of their chief engineer this contract shall have been wholly completed by the party of the first part (appellee) they will pay in currency for the performance of the same in full for material and labor as follows, to wit: Barth work, per cubic yard, 23 cents; solid rock, per cubic yard, $1.22-|-; loose rock, per cubic yard, 90 cents; compact gravel, per cubic yard, 35 cents; side hill, excavating rock, per cubic yard, 90 cents; clearing and grubbing, $16 per acre; rock embankment, per cubic yard, 30 cents; average overhaul, 2 cents per yard per 100 feet; freehaul, 100 feet; overhaul outside right of way to include actual haul, 2 cents per yard per 100 feet; 100 feet of embankment free ■dirt. * * *
[260]*260“The above price for excavation includes delivery into banks where the extreme haul does not exceed 2000 feet. Where the haul exceeds 100 feet the price for haul on average overhaul, 2 cents per cubic yard per 100 feet. The extreme haul, however, shall not exceed 2000 feet.”

If this stood alone we think there could be no question that in estimating the amount to be paid for the rock embankment it should be fixed by the number of cubic yards in the embankments themselves. But the contract refers to certain specifications as being annexed to it and as constituting a part of the agreement. In point of fact no specifications were annexed to the written agreement. The plaintiff testified that he never saw any specifications, and that he knew of none. On the other-hand James Converse, who was the chief engineer of the defendant corporation and its superintendent of construction, and who executed the contract on its behalf, testified that the contract and specifications were fully discussed between him and plaintiff at and before the execution of the contract, and that at the time he delivered him a copy of the specifications. The specifications were printed, and as he testified were made a part of all the construction contracts of the company. The specifications introduced in evidence contained this provision:

“ The measurements of quantities will usually be made in the cuts or pits from which the material has been taken. When quantities are determined by a measurement of embankments the engineer will estimate the actual quanity, and no allowance will be made for shrinkage. If required by the engineer, rock shall be piled for measurement by the contractor.”

In order the better to dispose of the assignments of error, we will first consider what, in the the light of the undisputed facts, is a proper construction of the contract, treating the specifications as a part of the agreement. The uncontroverted testimony shows that for the first month or two after plaintiff began the work the embankments then constructed were actually measured, and that the estimates were made and paid for upon the basis of that measurement. Subsequently Converse directed his subordinates in making the estimates to allow only for the contents of the excavations, and all subsequent estimates were made upon that basis. All succeeding payments were made upon the basis of excavation measurement, but also a deduction was made therefrom of the excess in the previous payments. We think the evidence shows beyond controversy that while the latter estimates were made upon the basis of the cubic contents of the excavations from which the rock was taken, in point of fact the excavations were not measured, and that their contents were arrived at by measuring the embankments themselves, and by deducting from the quantity so’ ascertained thirty-three and one-third per cent. This was shown by the book of the engineer who made the estimates, which was introduced in evidence. The testimony of Converse tends to [261]*261show that the excavations were measured, but in the light of all the evidence it is apparent that he is testifying as to the basis upon which the estimates were made, and not as to the manner in which the contents of the excavations were ascertained. It does not appear that he witnessed the actual measurement of any part of the work. We think, therefore, that it may be assumed as an uncontroverted fact that the embankments and not the excavations were actually measured. Recurring then to the language quoted from the contract, it is to be noted that rock embankment is the only embankment mentioned in the specification of prices. It is possible, therefore, that the provision in the specifications that “the measurement of quantities will usually be made in the cuts or pits from which the material has been taken ” was not intended to apply to the rock embankment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amend v. Light
443 S.W.2d 877 (Court of Appeals of Texas, 1969)
Southland Royalty Co. v. Pan American Petroleum Corp.
378 S.W.2d 50 (Texas Supreme Court, 1964)
City of Houston v. McCarthy
340 S.W.2d 559 (Court of Appeals of Texas, 1960)
Moore v. Wimberley
304 S.W.2d 709 (Court of Appeals of Texas, 1957)
Superior Oil Co. v. Stanolind Oil & Gas Co.
240 S.W.2d 281 (Texas Supreme Court, 1951)
Henshaw v. Texas Natural Resources Foundation
216 S.W.2d 566 (Texas Supreme Court, 1949)
Gray v. Shaunfield
212 S.W.2d 873 (Court of Appeals of Texas, 1948)
Slay v. Mary Couts Burnett Trust
180 S.W.2d 480 (Court of Appeals of Texas, 1944)
Lone Star Gas Co. v. X-Ray Gas Co.
164 S.W.2d 504 (Texas Supreme Court, 1942)
Martin Bros. v. State
146 S.W.2d 782 (Court of Appeals of Texas, 1940)
Taylor-Fichter Steel Const. Co. v. Curtis
144 S.W.2d 285 (Court of Appeals of Texas, 1940)
Farrell v. Drumm Floral Co.
125 S.W.2d 606 (Court of Appeals of Texas, 1939)
Schoenfeld v. Puy
58 S.W.2d 574 (Court of Appeals of Texas, 1933)
Rio Bravo Oil Co. v. Weed
50 S.W.2d 1080 (Texas Supreme Court, 1932)
Dines Bldg. Co. v. Cherry
49 S.W.2d 913 (Court of Appeals of Texas, 1932)
Lido Oil Co. v. W. T. Waggoner Estate
31 S.W.2d 154 (Court of Appeals of Texas, 1930)
Kent v. Ryan
20 S.W.2d 1099 (Court of Appeals of Texas, 1929)
Southwest Nat. Bank v. Employers' Indemnity Corp.
12 S.W.2d 189 (Texas Commission of Appeals, 1929)
Curry v. Texas Co.
8 S.W.2d 206 (Court of Appeals of Texas, 1928)
Livingston Oil Corp. v. Waggoner
273 S.W. 903 (Court of Appeals of Texas, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
11 S.W. 1113, 74 Tex. 256, 1889 Tex. LEXIS 930, Counsel Stack Legal Research, https://law.counselstack.com/opinion/galveston-harrisburg-san-antonio-railway-co-v-johnson-tex-1889.