Taylor-Fichter Steel Const. Co. v. Curtis

144 S.W.2d 285, 1940 Tex. App. LEXIS 763
CourtCourt of Appeals of Texas
DecidedJuly 5, 1940
DocketNo. 3609
StatusPublished
Cited by3 cases

This text of 144 S.W.2d 285 (Taylor-Fichter Steel Const. Co. v. Curtis) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taylor-Fichter Steel Const. Co. v. Curtis, 144 S.W.2d 285, 1940 Tex. App. LEXIS 763 (Tex. Ct. App. 1940).

Opinion

O’QUINN, Justice.

Appellant, Taylor-Fichter Steel Construction Company, Inc., was the principal contractor on the Neches River bridge on the Orange-Port Arthur highway. On the 16th day of August, 1937, appellant submitted the following offer in writing to appellees, Mark Curtis and S. G. Pam-philis, doing business as partners under the name of Associated Painting Contracting Company, to do, as sub-contractors, the work outlined herein and on the terms and conditions therein stated, for and under appellant as principal contractor, which offer appellees accepted:

“Associated Painting Contracting Co.
“P. O. Box 909
“Birmingham, Alabama.
“Dear Sirs:
“Subject to the approval of the State Highway Commission of the State of Texas and Jefferson County, Texas, and its Engineers, and of the P. W. A. of yourselves as sub-contractors, this letter will constitute an agreement between us for the field painting of the Neches River Bridge superstructure, P. W. A. Docket 8080-R.
“1: You are to furnish all materials (as outlined hereafter)., all tools and equipment, all rigging, all labor, all supervision, and all work and incidentals necessary to complete this field painting to the complete satisfaction of the State Highway Commission of the State of Texas and Jeffer--son County and the P. W. A. and their engineers and inspectors, all in accordance with specifications and contract for contract No. 2 superstructure.
“2: The touching up of field driven rivets is not included in your work nor is any cleaning occasioned by concrete operations nor scraping and cleaning of faulty shop coat. Where you are instructed by us to perform such work, you are to proceed with same and it is understood you will be paid for such work at actual cost plus 15%.
“3: Painting is to be performed by you in such manner and at such times and under such atmospheric conditions as specifically outlined in Article III of the Specifications to the satisfaction of the engineers and inspectors, and particular attention is directed to these requirements.
“4: All P. W. A. requirements and general conditions and special labor requirements, as contained in the specifica'tions and contract for contract #2 superstructure are to be considered as specifically written into this agreement and you are to comply with each and every one of them and they are to be an integral part of this agreement. Your attention is especially directed, although not limited to, pages 1 to 21 inclusive, 27 to 47 inclusive, 91 to 94 inclusive, 109 to 112 inclusive and 114 to 127 inclusive.
“5: We have arranged for the purchase of necessary paints and same will be delivered to you to the job ’site and you will be charged for these paints based upon the actual number of gallons of paint used by you at the following rates:
1st field coat at $2.25 per gallon
■2nd field coat at $2.00 per gallon
3rd field coat at $2.50 per gallon
“6: Workmen’s Compensation, public liability and property damage insurance are to be carried by you and certificates on prescribed forms are to be submitted.
“7: You are to furnish us without cost to us satisfactory completion bond.
“8: It is understood that you are to start this work at such times as field conditions permit and that you are to prosecute same as quickly as possible and in keeping with field conditions and so that your work will be completed within the time stipulated in the specifications or such extension of time as granted, by the engineers.
“9. Should any phase of your work be unsatisfactory, we reserve the right, upon issuance of ten days notice to you, to take over the completion of the entire field painting work in such manner as we see fit. Should this step become necessary, we shall have the right to take over and use for the completion of this work all rigging and tools which you have at the job site and no further payments will be made to you until the work is completed. Should the total cost under these circumstances be less than the amount of money owed you, the difference will be due you. Should, however, the total cost be in excess of the monies due you, you and your surety will be liable for this excess cost.
“10: It is understood that you will carry out this work with the use of labor which will in no way interfere with other labor being employed on this project by ourselves and other sub-contractors.
' "11: In consideration of the above, we agree to pay you the sum of Four and 45/100 ($4.45) Dollars per ton based on [287]*287final tonnage of metal work as determined by the State Highway Engineers. Payments will be made monthly on or before the 15th day of each month for 90%. of work completed during the preceding month. Final payment of 10% retained will be paid within 30 days after you have completed this work.
“This agreement, as stated above, is made with the understanding that it is subject to the approval of yourselves as sub-contractors by both the State Highway Commission of the State of Texas and Jefferson County and the P. W. A. Your acceptance of this letter will constitute an agreement between us.
“Yours very truly,
“Taylor-Fichter Steel Construction Co. Inc.”

This suit was filed by appellees against appellant, praying for the cancellation of this contract, and for $1,308.62 as the reasonable value of the field painting done by appellees on the bridge under the first clause of the contract; and for $2,037.72 as the reasonable value of the work done and material furnished by appellees under the second clause'of the contract; and for $730.88 as the value of certain personal property belonging to appellees alleged to have been converted by appellant; and $5,000 as exemplary damages for the willful conversion of appellees’ property. For cause of action, appellees alleged that the value of the work done under section 2 was to be paid for on the 1st day of the succeeding month, or within a reasonable time, and that appellant breached this clause of the contract by not making the payments as per the contract; and that appellant failed and refused to make payments for the work done under the first clause of the contract, as therein stipulated, thereby breaching the contract, and that, on such breach by appellant, on the 20th day of April, 1938, appellees declared the contract at an end as of that date, and on that date so notified appellant in writing, and that they ceased working under’ the contract. It was further alleged that appellant, on receipt of such notice, took over and proceeded to use on the job appellees’ rigging and tools, used by them on the job, which appellees say constituted a conversion. Appellees sued for the balance claimed by them for the work done on the bridge, and. for the value of their property on the alleged conversion, and for exemplary damages predicated on the alleged conversion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morgan v. Singley
560 S.W.2d 746 (Court of Appeals of Texas, 1977)
Fischer v. Richard Gill Co.
253 S.W.2d 915 (Court of Appeals of Texas, 1952)
Texas Associates, Inc. v. Joe Bland Const. Co.
222 S.W.2d 413 (Court of Appeals of Texas, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
144 S.W.2d 285, 1940 Tex. App. LEXIS 763, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taylor-fichter-steel-const-co-v-curtis-texapp-1940.