Kidwell v. Baltimore & Ohio Railroad

11 Gratt. 676
CourtSupreme Court of Virginia
DecidedJuly 15, 1854
StatusPublished
Cited by18 cases

This text of 11 Gratt. 676 (Kidwell v. Baltimore & Ohio Railroad) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kidwell v. Baltimore & Ohio Railroad, 11 Gratt. 676 (Va. 1854).

Opinion

MONCURE, J.

after stating the case, proceeded:

The principal subject of controversy in this case is, the amount of compensation to which the appellant is entitled for the masonry of the two bridges made by him for the appellees. He charges nine dollars per perch for dressing, ranging and laying the stone, besides making other charges connected with the masonry; whereas the price stipulated in the contracts and allowed in the final estimates, for the entire masonry, is four dollars per perch for that of one of the bridges, and four dollars and ninety-four cents for that of the other. The difference between the amount charged by him, and the amount allowed in the final estimates, for the masonry, is upwards of thirty-five thousand dollars.

The appellant contends that the masonry required by the contracts was “rubble work,” whereas he was required by the appellees to do and .according^ did do “ranged rock work;” that though the contracts required that the stone should have “good natural beds,” and be “well bedded and bonded,” yet those terms should be construed in reference to all the surrounding circumstances, and especially in reference to the quarries in the neighborhood of the bridges, and the, nature and quality of the stone they afforded; that the stone of which the bridges were constructed had “good natural beds,” and might have been “well bedded and bonded,” within the meaning of the contracts, by the use of the hammer merely. That if the work required by the contracts to be done was worth four dollars and four dollars and ninety-four cents per perch, the work required by the appellees to be do.ne, and actually done, was, in the same proportion, worth nine dollars per perch; and that therefore *he is entitled to the latter price. On the other hand, the appellees contend that the stone of which the bridges were constructed had not “good natural beds,” and could not have been “well bedded and bonded,” within the meaning of the contract, by the use of the hammer merely; that they had a right to require, and only required, the work to be done according to the contracts, but as it could not be done with the stone which was used, they were willing that it might be done in the manner in which it was done; that the change in the manner of doing the work was no benefit to them, but an accommodation to the appellant, who was thereby enabled to do it on better terms than he could have done it according to the contracts; that he assented to the change, and did not complain of it to any of the engineers; that the work actually done was but “rubble work,” though of a superior quality, and was not worth more than the contract prices; and that therefore he is entitled only to the contract prices.

The evidence is very conflicting as to the meaning of the technical terms used in the contracts, the character of the work thereby required, and the character and value of the work actually done. It would be difficult for the court to decide upon this evi[353]*353dence without the aid of a commissioner or a jury: But it is unnecessary in this case to do so. The appellees presented to the appellant the alternative of doing the work according to their construction of the contracts, or of doing it as it actually was done; and he elected the latter. He knew that they considered him to be doing the work at the contract prices; and yet during the whole progress of the work, which continued for about two and a half years, he never gave them notice that he would claim a higher compensation. On the contrary, he received from time to time, without objection, the amounts awarded him *in the monthly estimates, though in all of them the work done was charged at the contract prices. Rdgerton, a resident engineer, proves that he had a conversation on the subject with the appellant soon after the work was commenced. The appellant í ‘frequently alluded to the character of the work as being superior to what he was required to do by the contract. He was repeatedly told, if he thought so, to discontinue the work until the question could be settled; to do no more until that matter should be finally settled.” Atkinson, the division engineer, proves that the appellant never complained to him that he was required to do the work in a different style from that required by the contracts; on the contrary, deponent being told that appellant was complaining to others, asked him if he had any complaint, and he answered very positively that he would never have any controversy with deponent. Batrobe, the engineer of location and construction, proves that if he had been apprised of any intention on the part of the appellant to demand extra compensation for his work, he would immediately have had a communication with him on the subject, and have taken measures to put an end to any such expectations. Deponent is satisfied that at the time the appellant got fairly under way with his job, which was in the summer of 1840, he the deponent could have procured the work to be done precisely in the style in which the appellant then proposed to do it, and has since done it, at a price not exceeding that of his contract.

Under all these circumstances, I am of opinion that whatever may be the true construction of the contracts, the appellant acquiesced in the construction placed upon them by the appellees, and is concluded by such acquiescence from claiming a higher compensation for the masons than the prices stipulated for in the contracts, and allowed in the final estimates. *1 am also of opinion that the final estimates are conclusive not only in regard to the masonry, but also in regard to all other items of the appellant’s claim, except two items of small amount, which will be hereafter noticed. The contracts expressly provided that when the work was completed and accepted, final estimates should be made by the agent of the company, of the quantity, character and value of the work agreeably to the terms of the contracts, which final estimates should be conclusive between the parties, unless reviewed and altered by the engineer of location and construction; and that the balance appearing to be due to the contractor should be paid to him upon his giving a release to the company of all claims or demands whatsoever, growing in any manner out of the agreement. The final estimates were made according to the contracts, and have not been reviewed and altered by the engineer of location and construction : Why then are they not conclusive? The counsel for the appellant contended that such provisions are against the policy of the .common law, and have a tendency to exclude the jurisdiction of the courts, which are provided by the government with ample means to entertain and decide all legal controversies. Story on Partn. I 215, and cases cited in the notes. The doctrine relied on refers to agreements to refer disputes to arbitration; such as a stipulation, usually inserted in articles of partnership, that disputes and controversies between the partners shall be referred to arbitrators named in the articles, or to be named by the respective partners. It may well be questioned whether the provisions of the contracts in this case for the final estimates come within the influence of the doctrine relied on. They seem to stand on higher ground than mere agreements for future reference; and to be substantial and irrevocable parts of the contracts in which they are embodied.

But waiving the decision of that *question, and conceding for the purposes of this case, that these provisions are in effect agreements for future reference, and are governed by the doctrine referred to, I am still of opinion that the final estimates are conclusive. “The maxim often quoted, says Russell on Arbitration 103, 104, 63 Law Libr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Virginia & Kentucky Railway Co. v. Heninger
67 S.E. 185 (Supreme Court of Virginia, 1909)
Chicago Athletic Ass'n v. Eddy Electric Mfg. Co.
77 Ill. App. 204 (Appellate Court of Illinois, 1898)
Norfolk & Western Railroad v. Mills & Fairfax
22 S.E. 556 (Supreme Court of Virginia, 1895)
Williams v. Chicago, Santa Fe & California Railway Co.
20 S.W. 631 (Supreme Court of Missouri, 1892)
Sweet v. . Morrison
22 N.E. 376 (New York Court of Appeals, 1889)
Knopf v. Richmond, F. & P. R. R.
8 S.E. 787 (Supreme Court of Virginia, 1889)
G., H. & S. A. R'y Co. v. Henry & Dilley
65 Tex. 685 (Texas Supreme Court, 1886)
River v. Adams
17 Va. 427 (Supreme Court of Virginia, 1867)
Iaege v. Bossieux
15 Va. 83 (Supreme Court of Virginia, 1859)
Baltimore & Ohio R. R. v. Polly, Woods & Co.
14 Va. 447 (Supreme Court of Virginia, 1858)
Bassett's Adm'r v. Cunningham's Adm'r
9 Gratt. 684 (Supreme Court of Virginia, 1853)

Cite This Page — Counsel Stack

Bluebook (online)
11 Gratt. 676, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kidwell-v-baltimore-ohio-railroad-va-1854.