Haddad v. Bagwell

317 S.W.2d 781, 1958 Tex. App. LEXIS 2307
CourtCourt of Appeals of Texas
DecidedOctober 7, 1958
Docket5291
StatusPublished
Cited by7 cases

This text of 317 S.W.2d 781 (Haddad v. Bagwell) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Haddad v. Bagwell, 317 S.W.2d 781, 1958 Tex. App. LEXIS 2307 (Tex. Ct. App. 1958).

Opinion

WILLIAMS, Justice.

On December 17, 1949, plaintiffs Najib Haddad and wife, Julia Haddad, hereinafter referred to as “plaintiff” or “appellant,” entered into a contract in writing with defendant C. R. Bagwell, hereinafter referred to as “appellee”, as the Contractor, to construct a residence at 1600 North Mesa Avenue, El Paso, Texas. Haddad had theretofore verbally employed Ralph V. Davis and John P. Foster, architects, doing business as Davis & Foster, to draw the plans and specifications for said house, and to see that the house was constructed according to said plans. In February 1951 plaintiffs moved into their house, and faults in construction began to appear. Negotiations were had back and forth between the parties trying to adjust these differences, but, after all efforts in this regard failed, in April 1953 an agreement was signed by the plaintiffs and Bag-, well to arbitrate their differences. Plaintiffs selected O. H. Thorman as arbitrator; defendant Bagwell selected' Silvio' Prati; and these two, after much dickering and argument, selected Mr. Rowland Gilchrist. Mr. Gilchrist was not entirely satisfactory to defendant Bagwell because he lacked certain professional qualifications, but he was finally accepted. Final meeting of the arbiters was held on December 1, 1953, and all parties appeared in person or by their respective attorneys. As the result of this meeting, the following award (in brief) was, on December 1, 1953, signed by Thorman and Gilchrist; Prati, arbitrator for defendant Bagwell, declined to sign:

1. The contractor, C. R. Bagwell, did not construct the house in accordance with the plans and specifications.
2. Such defects are the responsibility of Bagwell.
3. The defects were occasioned by defective material and workmanship and failure of Bagwell to follow plans and specifications.
4. The liability and responsibility of Bagwell to Haddad for these defects is $12,652.80.
5. Bagwell is entitled to a credit of $1,.-069.57.
6. and 7. — (Not material here.)

On December 3, 1953, two days after the award was made, attorneys for Bag-well wrote a letter to plaintiffs’ attorneys, refusing to abide by said award for several reasons, one of which was that the arbitrators did not follow the terms of the arbitration agreement, etc.

On December 29, 1953, plaintiffs filed) suit against Bagwell in two parts: First, for enforcement of the arbitration award; and second, for his failure to comply strictly with the terms of the written agreement. The second count also contained an action against the architects, Davis & Foster, for failure to perform their contract to properly supervise the construction of the residence, etc. Among other things, the architects filed a motion for a summary judgment alleging the cause of action to be *783 upon an oral contract, rather than a written contract, and that therefore same was barred by the two-year statute of limitations, Vernon’s Ann.Civ.St. art. 5526. Plaintiff insisted, among other things, that the agreement between the architects and the plaintiffs was based and founded upon the contract in writing — to-wit, the one. above mentioned between the plaintiff and the contractor — and that his claim, therefore, was based upon a contract in writing and controlled by the four-year statute of limitations. The court rendered judgment for the architects on their motion for summary judgment, ordering that same be carried forward and incorporated in the final judgment for purposes of appeal. Thereafter, defendant Bagwell filed an amended pleading in which he alleged, among other things, that the arbitrators were guilty of gross mistake and partiality.

Trial was before-a jury on special issues and both parties filed motions for judgment, and the court entered judgment for the defendant, Bagwell, in the sum of $798.47 plus costs, same being based on specific findings of the jury, and the allowance of $1,000 owing by plaintiff to Bag-well. Some 27 issues were submitted to the jury. Issue No. 18 is the main bone of contention herein. It, and its answer, are as follows:

“Do you find and believe from a preponderance of the evidence that Arbitrators Thorman and Gilchrist, in assessing damages in their report, took into consideration all damages that they thought occurred to the Haddad residence, regardless of whether such damages were the result of the contractor’s failure to comply with the plans and specifications of the residence? Answer yes or no.
“We answer Yes.”

Plaintiff objected to the submission of this issue because an award of the board of arbiters may only be set aside because of “prejudice, fraud, or gross mistake, and therefore the question should not have been submitted.” They also made a motion at the proper time that said issue and its answer be disregarded by the court for the same reasons.

Appellant sets up four points of error, briefly as follows:

Point I.

The Court should not have submitted Special Issue Number Eighteen for the jury’s consideration for the reason that this suit was not an appeal from the arbitration award and the question as submitted was a direct and collateral attack upon the award of the arbitrators, not involving fraud, partiality, misconduct or such gross mistake as would imply bad faith or a failure on the part of the arbitrators to exercise an honest judgment.

Point II.

The court should have disregarded the jury’s answer to special issue No. 18 for the reasons stated above.

Point III.

The court erred in rendering judgment on the motion for summary judgment filed by the architects, Davis & Foster, because the evidence and the pleadings were to the effect that the cause of action was “based upon and founded upon a contract in writing, including, the general contract, plans and specifications,” prepared by the architects, and included-in the contract between plaintiff and Bagwell.

Point IV.

The court erred in rendering the summary judgment above referred to because the architects were estopped to plead the two-yeár statute of limitations.'

Points I and II are so interrelated that they will be discussed together. As can readily be seen, the plaintiff insists that the award of the board of arbiters was full and complete on its face, and *784 did not show “fraud, partiality, misconduct or such gross mistake as would imply bad' faith or' a failure on the part of the arbiters to' exercise an honest judgment.” Defendant Bagwell insists that the court did not err in disregarding the arbitration award and rendering judgment on the findings of the jury, including Special Issue numbered eighteen, because, he insists, the arbitrators went outside of the scope of their authority and rendered an award that they were not entitled to render because, as shown by Issue No. 18, they found damage against defendant Bagwell, whether he was responsible for it or whether it was the responsibility of someone else. For this argument he relies largely on an opinion by Chief Justice Nealon, of this court, found in Johnson v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atlas Chemical Industries, Inc. v. Anderson
514 S.W.2d 309 (Court of Appeals of Texas, 1974)
National Automobile & Casualty Insurance Co. v. Holland
483 S.W.2d 28 (Court of Appeals of Texas, 1972)
Brown v. Eubank
443 S.W.2d 386 (Court of Appeals of Texas, 1969)
Smith v. Southern Land Development Co.
385 S.W.2d 552 (Court of Appeals of Texas, 1964)
Smith v. Barnett
373 S.W.2d 762 (Court of Appeals of Texas, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
317 S.W.2d 781, 1958 Tex. App. LEXIS 2307, Counsel Stack Legal Research, https://law.counselstack.com/opinion/haddad-v-bagwell-texapp-1958.