Austin Bridge Co. v. Teague

149 S.W.2d 674, 1941 Tex. App. LEXIS 201
CourtCourt of Appeals of Texas
DecidedMarch 5, 1941
DocketNo. 9007.
StatusPublished
Cited by3 cases

This text of 149 S.W.2d 674 (Austin Bridge Co. v. Teague) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Austin Bridge Co. v. Teague, 149 S.W.2d 674, 1941 Tex. App. LEXIS 201 (Tex. Ct. App. 1941).

Opinion

BLAIR, Justice.

Appellee, B. C. Teague, sued appellants, Austin Bridge Company, Austin Road Company, and the Superior Lloyds .of America, as surety, for the difference in the wages paid him as an unskilled laborer and the wages claimed to be due him as a skilled laborer for work done on a public works contract; and on a trial to the court without a jury recovered judgment for $479.40 as the balance of wages due, less 1% for payment of old age benefits; $47.-94 as attorney’s fees; and 6% interest on the judgment from its date; hence this appeal.

Appellee sued as a third party beneficiary under a contract between Austin Bridge Company-Austin Road Company and the State Highway Commission for the difference between the amount paid him as an unskilled laborer and the amount claimed to be due him for labor performed as a skilled laborer or master finisher of cement in the construction of bridges and culverts for the State of Texas on its Federal Aid Project #74 (2) in Travis County; appellee pleading as the basis of his right of recovery the. contract and the provisions of Article 5159a, Vernon’s Ann. Civ.Statutes (Acts 1933, 43rd Leg. p. 91), which statute was expressly made a part of the contract. Appellants contend that this statute does not afford appellee the remedy sought by him, and that he was not a third party beneficiary under the contract. Neither contention is sustained.

The emergency clause of the Act of 1933 recites that its purpose is to protect “laborers, workmen and mechanics engaged in doing and performing work on public works” and to secure to them the payment of certain per diem wages. The portions of the Act applicable here provide in substance as follows:

1. That before undertaking any public work the State Highway Commission “shall ascertain the general prevailing rate of per diem wages in the locality in which the work is to be performed for each craft or type of workman or mechanic needed to execute the contract”; and shall fix the rate of per diem wages to be paid them in the execution of the contract at “not less than the general prevailing rate of per diem wages for work of a similar character in the locality in which the work is performed”; and “shall specify in the call for bids for said contract, and in the contract itself,” the rate of per diem wages so ascertained and . fixed.

2. That the prevailing rate'of per diem wages so determined by the Commission “shall be final.”

3. That “it shall be mandatory upon the contractor * * * and * * * subcontractor * * * to pay not less than the said specified rates.”

4. That “the contractor shall forfeit as a penalty to the State * * * Ten Dollars ($10.00) for each laborer, workman or mechanic employed, for each calendar day, or portion thereof, such laborer, workman or mechanic is paid less than the said stip *676 ulated rates for any work done under said contract/’ and the Commission shall “cause to be inserted in the contract a stipulation to this effect.”

5. That “it shall be the duty of such public body [Commission] awarding the contract, and its agents and officers, to take cognizance of complaints of all violations of the provisions of this Act committed in the course of the execution of the contract, and, when making payments to the contractor of monies becoming due under said contract, to withhold and retain therefrom all sums and amounts which shall have been forfeited pursuant to the herein said stipulation and the terms of this Act.”

Section 5 of said Ac( of 1933 is Art. 1581a of Vernon’s Ann. Penal Code and provides that a fine of not exceeding $500 or six months’ imprisonment, or both, may be imposed upon any contractor or any representative of the state or political subdivision thereof, who shall wilfully violate or omit to comply with any of the provisions of the Act.

The contract referred to and made the Act of 1933 a part of it, and as directed by the Act, the Commission inserted the penalty clause in the contract, and specified in its call for bids and caused to be inserted in the contract its order ascertaining and fixing the general prevailing rate of per diem wages on an eight hour per day basis at $1 per hour for skilled labor; fifty cents per hour for intermediate labor; and forty cents per hour for unskilled labor. This order also defined in general terms the three stated classifications of labor, listing various kinds of laborers, workmen and mechanics under each classification; and listed under the classification “Skilled Labor,” among others, is “Master Finisher (pavement and structure).”

Appellants concede that the Act is primarily for the protection and benefit of the laborers and workmen in securing to them payment of the minimum wages prescribed. They contend, however, that since the Act does not specifically authorize workmen to bring suit for such wages claimed to be due them for work performed in the execution of a public works contract, they have no such right. In this connection, appellants cite the provisions of the Act giving the Commission the right to require the contractor to keep accurate records of work done by each laborer and the amount paid him; its right and duty to investigate all complaints for violation of the Act; and its right to forfeit to the state $10 per day for each laborer for each day he is paid less than the minimum' rate of wages prescribed; as being summary remedies provided by the statute in behalf of the workmen, and as being the exclusive remedies afforded by the statute. In addition, the penal code imposing a fine of $500 or six months’ imprisonment, or both, upon any contractor or any representative of the state or any subdivision thereof, for violation of the statute, is also cited as a further summary remedy in behalf of the workmen.

It is true that these remedies or provisions for the enforcement of the statute may indirectly aid workmen in securing the payment of the minimum rate of wages; but we do not regard them as being exclusive. Such provisions are penal in nature and like all penal laws were intended as deterrents to contractors not to pay less than the minimum rate of wages. Their enforcement, however, does not actually pay the minimum rate of wages prescribed, which is the primary objective of the statute, and we can conceive of no good reason why the legislature would give workmen the right to require a contractor of public works to pay them a minimum rate of wages, and then deny them the right to sue the contractor for such wages. We think the Act contemplates the authority of ’ workmen to enforce their right to be paid such wages by suit against the contractor. This becomes apparent when the Act in question is considered with other statutes enacted for the benefit and protection of workmen or laborers furnishing labor to any contractor for any public works. That is, Chap. 17, Acts 1925, 39th Leg., p. 44, Vernon’s Ann.Civ.St. Arts. 5472a, 5472b, provides that a workman or laborer furnishing labor to any contractor for any public improvements shall have a lien on any money, etc., which may become due the contractor by notifying in writing the public officials of the state of his claim. Chap. 78, Acts 1929, 41st Leg., p. 154, Vernon’s Ann.Civ.St. art. 5472b — 1, provides that when a claim or claims to fix the lien provided by Chap. 17 have been filed the contractor may release the lien by giving bond in double the amount of the claim, payable to the laborer and upon which he may sue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

STUCKEY v. APEX MATERIALS, LLC
142 Nev. Adv. Op. No. 17 (Nevada Supreme Court, 2026)
Austin Bridge Co. v. Teague
152 S.W.2d 1091 (Texas Supreme Court, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
149 S.W.2d 674, 1941 Tex. App. LEXIS 201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/austin-bridge-co-v-teague-texapp-1941.