Hearn v. Ralph Sollitt & Sons Const. Co.

93 S.W.2d 551, 1936 Tex. App. LEXIS 347
CourtCourt of Appeals of Texas
DecidedMarch 12, 1936
DocketNo. 4828.
StatusPublished
Cited by5 cases

This text of 93 S.W.2d 551 (Hearn v. Ralph Sollitt & Sons Const. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hearn v. Ralph Sollitt & Sons Const. Co., 93 S.W.2d 551, 1936 Tex. App. LEXIS 347 (Tex. Ct. App. 1936).

Opinion

JOHNSON, Chief justice.

This suit was instituted by appellant, George Hearn, plaintiff in the trial court, against appellee, Ralph Sollitt & Sons Construction Company, defendant, to recover 70 cents per hour for 738 hours at $1 per hour, less credit paid of 30 cents per hour, leaving a balance of $516.60 alleged to be due plaintiff for labor performed by him in the capacity of signaling the hoisting engineer for 400 hours, operating a concrete mixer for 250 hours, and doing structural ironwork for 88 hours at the instance of defendant contractor constructing a federar courthouse and post office building in the city of Tyler, Smith county, Tex. The defendant answered by general demurrer and general denial. The general demurrer was overruled, and the cause proceeded to trial to a jury. At the close of plaintiff’s evidence, the court directed the jury to return a verdict in favor of the defendant. ⅛/⅞⅛ plaintiff has appealed.

The first matter to be determined is a motion presented in this court to dismiss the appeal for the reason, it is contended, that plaintiff’s petition shows on its face that the' amount involved, which plaintiff was entitled, if anything, to recover, is below the jurisdiction of the county court, the court in which the case was tried.

Plaintiff’s petition alleged in substance that defendant Ralph Sollitt & Sons Construction Company entered into a contract with the United States government to construct a courthouse and post office building in the city of Tyler, Smith county, Tex.; that for want of a copy of the contract plaintiff could not allege its provisions in full, and called on defendant to produce the same; on information and belief he alleged the contract provided that defendant should pay its laborers the prevailing wage scale; for that kind and character of work in that locality; that defendant contracted with Lloyd Orr Goble, construction engineer, and Thomas P. Hyland of the United States Department of Labor, acting for and in behalf of all laborers, including plaintiff, engaged in working on said building, to pay the engineer, hoisting, $1 per hour and the structural ironworkers $1 per hour, and many other laborers $1 per hour; that by virtue of said agreement plaintiff was entitled to recover for each hour’s labor performed by him in the capacity above stated the sum of $1 per hour; and further alleged:

“That Ralph Sollitt & Sons Construction Co., defendant herein, did wilfully, maliciously, negligently and with the intent to defraud this plaintiff only pay him thirty cents per hour for signaling the engineer, operating the concrete mixer, and doing structural iron work, where in truth and in fact he was entitled to receive $1.00 per *553 hour for these classes of labor, and which was in violation and not in keeping with its contract and agreement hereinabove referred to, and when the plaintiff was advised of the agreement as to the amount of money-defendant agreed to pay per hour for the kind and character of labor the plaintiff 'had done and was then doing, and when he the plaintiff made demand upon the defendant’s agent, R. E. Pritz, for the balance due him of 70 cents per hour which is the difference in the amount received and the amount due him, the said R. E. Pritz refused .to pay the plaintiff the difference of 70 cents per hour and then and there fired and discharged the plaintiff from the job, and still fails and refuses to pay him. That the defendant is indebted to plaintiff in the approximate sum of $516.60 dollars.
“That the plaintiff through his attorney presented his claim to Lloyd Orr Goble whom we understand is the agent of the Department of Labor and he refused to give us any assistance.
“Wherefore, premises considered, plaintiff prays that defendant be cited to appear and answer herein and that upon a hearing hereof that he have judgment against Ralph Sollitt & Sons Construction Co., a balance of 70 cents per hour for the number of hours plaintiff has worked at signaling the engineer, operating the concrete mixer and doing structural iron work, costs of suit and such other and further relief special and general in law and in equity to which he may show himself entitled.”

The record shows that appellee offered no special exceptions to the petition. In its motion presented to this court to dismiss the appeal for want of sufficient amount involved to confer jurisdiction of the trial court, appellee contends: “That the most appellant could have been entitled to recover, under the law and under the allegations of his petition, was $61.60 (for 88 hours structural ironwork at $1.00 per hour, less credit of 30(⅜ per hour paid), which facts were and are apparent from the face of said petition,” because the petition, it is contended, “does not allege that, in said contract appellee agreed to pay the hoisting engineer’s helper, or-the man who gave the hoisting engineer his signals, $1.00 per hour, or any other amount, * * * and does not allege that, in said contract appellee agreed to pay the operators of the concrete mixer $1.00 per hour, or any other amount.” In other words, appellee’s contention, is to the effect that appellant’s petition is insufficient in allegations of fact to admit evidence authorizing recovery upon the two alleged items of labor of 400 hours performed in signaling the hoisting engineer and 250 hours in operating the concrete mixer, and that the amount for doing structural ironwork which plaintiff was entitled to recover, being only $61.60, was below the jurisdiction of the trial court.

We- do not think the petition was so insufficient in lack of allegations of fact charging liability in respect to the two items of labor mentioned as to render the petition with respect to such items subject to general demurrer. Rule 17, adopted by the Supreme Court for practice in district and county courts (142 S.W. xviii), provides: “General exceptions shall point out the particular instrument in the pleadings, to wit, the original petition or answer, or the respective supplements to either; and in passing upon .such general exception every reasonable intendment arising upon the pleading excepted to shall be indulged in favor of its sufficiency.”

In Garza v. Kenedy (Tex.Com.App.) 299 S.W. 231, 233, it is held: “In testing the sufficiency of a petition by a general demurrer, much liberality is indulged by the courts, even though much of the pleading is made up of what is generally termed ‘conclusions of the pleader,’ drawn from the facts not revealed. Yet, such a defect in pleading can only be reached by special demurrer against that defect and cannot be reached by general demurrer. Bragg v. Houston Electric Co. (Tex.Civ.App.) 264 S.W. 245; Saner-Ragley Lumber Co. v. Spivey (Tex.Civ.App.) 255 S.W. 193.”

Appellee’s motion to dismiss the appeal is grounded upon the following authorities, among others : Askey v. Oliver Chilled Plow Works (Tex.Civ.App.) 57 S.W.(2d) 210; Carswell & Co. v. Habberzettle, 99 Tex. 1, 86 S.W. 738, 740, 122 -Am.St.Rep. 597; Richards Medicine Co. v. Graves (Tex.Civ.App.) 273 S.W. 702. From syllabi in Askey v. Oliver Chilled Plow Works, supra, is quoted: “Suit should be dismissed, though petition claims jurisdictional amount, if facts alleged show no cause of action for such part thereof as to reduce it below required sum.”

From Carswell & Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Novosk v. Reznick
56 N.E.2d 318 (Appellate Court of Illinois, 1944)
Bowers v. Mabry
159 S.W.2d 529 (Court of Appeals of Texas, 1942)
Austin Bridge Co. v. Teague
149 S.W.2d 674 (Court of Appeals of Texas, 1941)
Bishop & Babcock Sales Co. v. Haley
115 S.W.2d 772 (Court of Appeals of Texas, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
93 S.W.2d 551, 1936 Tex. App. LEXIS 347, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hearn-v-ralph-sollitt-sons-const-co-texapp-1936.