Linch v. Paris Lumber and Grain Elevator Co.

15 S.W. 208, 80 Tex. 23, 1891 Tex. LEXIS 950
CourtTexas Supreme Court
DecidedJanuary 23, 1891
DocketNo. 6414.
StatusPublished
Cited by47 cases

This text of 15 S.W. 208 (Linch v. Paris Lumber and Grain Elevator Co.) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Linch v. Paris Lumber and Grain Elevator Co., 15 S.W. 208, 80 Tex. 23, 1891 Tex. LEXIS 950 (Tex. 1891).

Opinion

HENRY, Associate Justice.

This suit was brought by the appellee to recover damages for a breach of contract.

The parties signed a written contract in which appellant was styled ‘ ‘ employer ” and the appellee was styled contractor. ” We copy the-following extracts from the contract:

“1. The contractor agrees to furnish all the material and do all the-work of whatever kind required by or reasonably to be inferred from the plans and specifications prepared by W. A. McGinnis, said plans and specifications being hereby incorporated with and made part of this *27 contract, for the full and entire completion of a three-story brick business block in the city of Paris, Texas, for the sum of $16,450.
“2. The contractor agrees that all materials called for in the plans and specifications are to be of the first qualities of their respective kinds, and that all of the work shall be done in the most thorough and workmanlike manner, and that he will not vary in any manner from the said plans and specifications without the written consent of the employer.
“4. The employer reserves the right to order in writing any alteration he may deem proper from the said plans and specifications.
8. The employer reserves the right to appoint a superintendent or inspector of this improvement, and it is expressly stipulated and agreed that no claim shall be made or suit brought for any sum due or claimed to be due for said improvement unless upon certificate of said superintendent or inspector that the improvement has been made in strict accordance with the contract and plans and specifications, or such alterations as may have been made therein in accordance with the stipulations of this contract.
9. Upon the failure of the contractor to proceed with said improvement to the satisfaction of the employer so as to secure the completion of the improvement within the stipulated time, or upon his failure to comply with the requirements of this contract, it shall be lawful for the employer, after giving ten days’ notice of his intention so to do, to be served upon the contractor, either to complete said improvement by contract or by day’s work at the expense of the contractor, and recover from him and his sureties the additional expense thereby incurred, if any, over the amount due according to this contract; or at the option of the employer to entirely avoid the contract and bring suit at once against the contractor and his sureties for the damage occasioned thereby, in which latter case all work done and materials on the ground are to become the property of the employer without any further payment therefor. The payments are to be made, upon the production of the certificate of the superintendent, in the following manner:
(1) $1500 to be paid after the foundation is laid.
(2) $3000 to be* paid after the first story walls are up and second .set of joists are in and bridged.
(3) $2250 to be paid after the second story is up and the third set of joists are in position and bridged.
“(4) $2750 to be paid after the ceiling and roof joints and bridged roof and cornice are on.
(5) $2500 after floors are laid, ceilings up, and all sash in and hung.
(6) $3000 to be paid after the plastering is finished and the front put in.
(7) The last payment of $1450 to be made when the .building is finished and approved by the owner and superintendent.”

*28 The original plans are made part of the record, and it also contains the specifications, covering eighteen closely written pages.

The specifications minutely cover every detail of the improvement from the bottom of the foundation to the top of the roof, and the plans exhibit it in the same way.

Among others the specifications contain the following provisions:

“Said building to be erected in strict accordance with these specifications and accompanying drawings prepared by W. A. McGinnis, architect.

“The several floor plans and”elevations are drawn to a uniform scale of four feet to one inch, but in all cases the figures marked on the several drawings are to be taken in preference to measurements by such scale, and should any error be discovered the same must be referred to the architect for adjustment and correction.

“The contractors for the work shall have a competent foreman on the work at all times to whom the architect can give instructions in the absence of the- contractor.

“All work to be done in a thorough, workmanlike manner, to the full satisfaction of the architect and owner, and any material condemned must be immediately removed from the building and grounds, and any work that may be condemned must immediately be made good.

“Iron work: The angle or box columns on front to be 16" face, 16" back or sides 16"; Ho. 4, 3-16"xl6"xl5' 16". Intermediate columns Ho. 47, 8" 15' 6". Interior columns similar to Ho. 16. Girders to be 17" double ribbed. Door and window sills to have a face to match stone work. The above numbers refer to Pullis Bros’. Catalogue. Sills of doors to be 181". All window sills to be 8" wide and extend into the wall at least 4" at each end. Window sills on south and west fronts to have a box 2J" back and to extend out flush with stone belt. _ Sills in the east end to be plain but boxed. Owner’s name to be placed or cast on all door sills. All columns to be full f thick.”

Plaintiff’s original petition charged that while it was proceeding in good faith to construct the improvement according to the contract, and when it had so completed the first story of the building and had placed the joists thereon and become entitled to have paid to it the second installment of its compensation, the defendant willfully and wrongfully, refused to carry out the contract, unlawfully took possession of the building, and ejected therefrom plaintiff’s workmen, etc.; and it gave a specific statement of the damages that had resulted to it from defendant’s breach of the contract.

We copy a statement of the subsequent pleadings of the parties from appellant’s brief which, in so far as it becomes necessary to consider them on this appeal, are as follows:

“The defendant alleged that by the terms of the contract all materials were to be of the best quality, the work to be done in the most thorough *29

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robert Marx and Debbie Marx v. Fdp, Lp
Court of Appeals of Texas, 2015
Ashford Partners, Ltd. v. Eco Resources, Inc.
401 S.W.3d 35 (Texas Supreme Court, 2012)
TA Operating Corp. v. Solar Applications Engineering, Inc.
191 S.W.3d 173 (Court of Appeals of Texas, 2006)
R.C. Small & Associates, Inc. v. Southern Mechanical, Inc.
730 S.W.2d 100 (Court of Appeals of Texas, 1987)
Advance Components, Inc. v. Goodstein
608 S.W.2d 737 (Court of Appeals of Texas, 1980)
Bernhardt v. McGuire & Pritchard
607 S.W.2d 8 (Court of Appeals of Texas, 1980)
Baldwin v. Smith
586 S.W.2d 624 (Court of Appeals of Texas, 1979)
Dietz Memorial Co. v. Texas Steel Building Co.
578 S.W.2d 872 (Court of Appeals of Texas, 1979)
Warren v. Denison
563 S.W.2d 299 (Court of Appeals of Texas, 1978)
Longview Construction & Development, Inc. v. Loggins Construction Co.
523 S.W.2d 771 (Court of Appeals of Texas, 1975)
Perryman v. Sims
506 S.W.2d 753 (Court of Appeals of Texas, 1974)
Montclair Corporation v. Earl N. Lightfoot Paving Co.
417 S.W.2d 820 (Court of Appeals of Texas, 1967)
Pacific Coast Engineering Co. v. Trinity Construction Co.
410 S.W.2d 797 (Court of Appeals of Texas, 1967)
Harsha v. Renfro Drug Co.
77 S.W.2d 584 (Court of Appeals of Texas, 1934)
Olivas v. El Paso Electric Co.
54 S.W.2d 154 (Court of Appeals of Texas, 1932)
Hoffer Oil Corp. v. Hughes
48 S.W.2d 426 (Court of Appeals of Texas, 1932)
Anderson v. Parsley
37 S.W.2d 358 (Court of Appeals of Texas, 1931)
Scott v. Crawford
9 Ohio Law. Abs. 146 (Ohio Court of Appeals, 1930)
Davidson v. Swanson
24 S.W.2d 776 (Court of Appeals of Texas, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
15 S.W. 208, 80 Tex. 23, 1891 Tex. LEXIS 950, Counsel Stack Legal Research, https://law.counselstack.com/opinion/linch-v-paris-lumber-and-grain-elevator-co-tex-1891.