Montclair Corporation v. Earl N. Lightfoot Paving Co.

417 S.W.2d 820, 1967 Tex. App. LEXIS 2899
CourtCourt of Appeals of Texas
DecidedJune 22, 1967
Docket14686
StatusPublished
Cited by14 cases

This text of 417 S.W.2d 820 (Montclair Corporation v. Earl N. Lightfoot Paving Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Montclair Corporation v. Earl N. Lightfoot Paving Co., 417 S.W.2d 820, 1967 Tex. App. LEXIS 2899 (Tex. Ct. App. 1967).

Opinions

BELL, Chief Justice.

Majority Opinion

This is an appeal from a judgment rendered in favor of appellee, Earl N. Light-foot Paving Co., Inc., against appellant for $16,536.50, with interest from the date of judgment, plus $6,500.00 as an attorney’s fee, with interest thereon from the date of judgment. The purpose of the suit filed by appellee was to recover for work done and labor and material furnished under a written contract in the laying of pavement in a parking area at the Montclair Shopping Center in Houston and the construction of sidewalks and driveways in connection therewith. There were, of course, certain specifications that were a part of the contract in accordance with which the improvements were to be constructed. The contract also obligated appellee to maintain the surface for six months. Too, the suit encompassed an effort to recover for additional materials and labor furnished that were not called for in the contract.

Appellee asserted right of recovery on the theory of full performance of the contract and for the extras furnished. It, alternatively, asserted right of recovery on the theory of substantial performance, and, further in the alternative, on the theory of quantum meruit for all labor, material and services furnished both under the contract and those not covered by the contract.

Appellant defended on a basis of nonperformance in numerous specified particulars. On the theory that the improvements were not performed in conformity with the contract and that the improvements as constructed were wholly worthless and could, not be corrected except by tearing up the pavement and other improvements, appellant filed a cross action against appellee [822]*822and its surety, Aetna Casualty & Surety Company, for $150,000.00. Judgment was against appellant on its cross-action.

The case was submitted on 35 special issues, many of which were unanswered because conditionally submitted. All theories noticed above were submitted.

The jury answered as follows on the issues relating to performance of the work called for by the contract, they relating to whether the work was performed in compliance with the contract or substantially performed:

1. Issue No. 1. Appellee did not perform the work in accordance with the contract of May 25, 1959, as amended.

2. Issue No. 3. Appellee substantially performed the work in accordance with said contract.

3. Issue No. 4. For substantially performing the work called for by said contract there was due appellee the sum of $71,693.51.

We specifically note that the amount found due for substantial performance of the work called for by the contract was the full amount for which appellant had been invoiced at the contract price. Without dispute appellant had paid $55,-614.42. Deducting the amount admittedly paid from the amount the jury found to be due under the contract for substantial performance of the work would leave a balance owing, assuming appellee in this case would be entitled to recover on the contract, of $16,079.09.

The jury in answer to issues submitting the theory of recovery on quantum meruit, including work, labor and material furnished under the written contract, and for extras not called for by the contract, found all issues of liability in favor of appellee, and found appellee was due and owing for the reasonable value to appellant of the materials and services furnished the sum of $16,536.50.

Appellee had sued for extras in the amount of $1,250.40.

An award of an attorney’s fee of $6,-500.00 was also made.

The jury also found that appellant accepted the work after appellee claimed it was completed. It found that the architect accepted the work after appellee claimed it was completed. It also found that appellant waived the issuance by the architect of the final certificate of completion and acceptance of the work performed.

In response to Special Issue No. 16, the jury found that appellee did not fail to install the paving in accordance with the contract, and in response to Special Issue No. 18 it was found that appellee did not fail to install such paving in a good and workmanlike manner.

In response to Special Issue No. 20, it was found that appellee did not fail to construct the driveways in accordance with the contract.

The jury found that appellee failed to maintain the improvements for the period of time provided in the contract; that such was a material failure, but that appellee was excused for such failure because of the failure of appellant to perform its obligations under the contract.

Special Issue No. 31 was conditionally submitted. It was predicated on a “We do” answer to either Special Issue No. 16 or No. 20. The jury had, however, answered “We do not” to each issue, the effect of such answers being to find that appellee had not failed to install the paving and driveways in accordance with the contract. Special Issue No. 31 was, therefore, not answered, but it had inquired whether any alterations would have been required to make “such improvements" (paving and driveways) conform to the contract. Special Issue No. 32 was predicated on a “We do” answer to Special Issue No. 31 and inquired whether such alterations would have been substantial. It was unanswered. Special Issue No. 33 was predicated on a [823]*823“We do” answer to Special Issue No. 32, and inquired as to the value in the year 1959 to appellant of the improvements called for by the contract.. It was unanswered. Special Issue No. 34 was also predicated on a “We do” answer to Special Issue No. 32, and inquired as to the value in 1959 to appellant of the improvements as actually constructed. It was unanswered. Special Issue No. 35 was predicated on a “We do” answer to Special Issue No. 31, and inquired as to the reasonable cost of such alterations, if any, required to make such improvements (paving and driveways) conform to the contract. It was unanswered.

We believe we have noticed all issues submitted, together with the jury’s response to them, if any, that are material to this appeal. The jury did not fail to answer any unconditionally submitted issue.

The court rendered judgment for appel-lee, as above stated, for $16,536.50, which is the amount found by the jury as the unpaid sum of money due appellee for the reasonable value to appellant of materials and services furnished by appellee. This was, therefore, apparently a rendition of judgment on the theory of quantum meruit for the materials and services furnished under the written contract and for some extras sued for in the amount of $457.41. This conclusion is based on our notice that the effect of the jury’s answer to Special Issue No. 4 was that there was a balance due for work done under the written contract of $16,079.09, the jury having found substantial performance. Additionally, judgment was rendered for an attorney’s fee.

Appellant asserts the following five Points of Error, the substance of which we state:

1.The trial court erred in refusing to render judgment for appellant and in rendering judgment for appellee on the theory of quantum meruit because an express contract was pled and proved and appellee’s theory of the case was that it had fully performed.

2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brockhaus v. Gallego Basteri
188 F. Supp. 3d 306 (S.D. New York, 2016)
Austin v. Truly
721 S.W.2d 913 (Court of Appeals of Texas, 1986)
Widmer v. Stamps
663 S.W.2d 875 (Court of Appeals of Texas, 1984)
Cameo Construction Co. v. Campbell
642 S.W.2d 10 (Court of Appeals of Texas, 1982)
Duncan Development, Inc. v. Haney
634 S.W.2d 811 (Texas Supreme Court, 1982)
Beller v. De Lara
565 S.W.2d 319 (Court of Appeals of Texas, 1978)
W. G. Tufts & Sons v. Herider Farms, Inc.
485 S.W.2d 300 (Court of Appeals of Texas, 1972)
Coon v. Schoeneman
476 S.W.2d 439 (Court of Appeals of Texas, 1972)
Electric Wire & Cable Co. v. Ray
456 S.W.2d 260 (Court of Appeals of Texas, 1970)
Montclair Corporation v. Earl N. Lightfoot Paving Co.
417 S.W.2d 820 (Court of Appeals of Texas, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
417 S.W.2d 820, 1967 Tex. App. LEXIS 2899, Counsel Stack Legal Research, https://law.counselstack.com/opinion/montclair-corporation-v-earl-n-lightfoot-paving-co-texapp-1967.