Beller v. De Lara

565 S.W.2d 319, 1978 Tex. App. LEXIS 3129
CourtCourt of Appeals of Texas
DecidedApril 5, 1978
Docket15894
StatusPublished
Cited by8 cases

This text of 565 S.W.2d 319 (Beller v. De Lara) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beller v. De Lara, 565 S.W.2d 319, 1978 Tex. App. LEXIS 3129 (Tex. Ct. App. 1978).

Opinion

KLINGEMAN, Justice.

This is a suit by Jose Garcia De Lara, an architect, against Dr. Barry M. Beller for damages for breach of contract and, in the alternative, on quantum meruit. The contract involved was a Standard Form of Agreement Between Owner and Architect of the American Institute of Architecture, and covered the construction of a lake house at Lake Lyndon B. Johnson for defendant. Defendant terminated the contract after he had paid plaintiff a small amount for services during the early phases of the contract. Trial was to a jury with a number of special issues submitted 1 and judgment was entered on the jury’s verdict that plaintiff recover from defendant the sum of $3,000 less the sum of $721.84 paid by defendant, and for attorney’s fees in the amount of $2,500.

The plaintiff is a registered architect. The contract calls for a fee of eight per cent of the construction cost, payable at various stages of the contract, with certain additional services to be paid for on a basis of $12 per hour. The contract contains this provision as to termination of the contract:

*320 ARTICLE 8
TERMINATION OF AGREEMENT This agreement may be terminated by either party upon seven days’ written notice should the other party fail substantially to perform in accordance with its terms through no fault of the other. In the event of termination due to fault of others than the Architect, the Architect shall be paid his compensation for services performed to termination date, in- . eluding Reimbursible Expenses then due and all terminal expenses.

Plaintiff testified that he took the contract on a moonlight basis so he charged eight per cent rather than the normal 12 per cent. He stated that the majority of the work of an architect is completed before construction begins; that he had frequent meetings with defendant to discuss the design phases; that the construction documents were 95 per cent finished; that any qualified builder or contractor could take the plans made by him and build the house; that in connection with the work he had employed a structural engineer to determine the structural beams, stresses, etc., and had been billed for such services. He testified that defendant had fired him by letter. The record contains as an exhibit a letter terminating the contract, recited to be in accordance with Article 8 of the contract, and also making demand for the return of the sum of $721.84 previously paid by defendant to plaintiff.

It is not disputed that the house was never constructed. The architect’s contract provides that the architect’s fee is to be paid in five phases:

1. schematic 15 per cent
2. design development 35 per cent
3. construction document 75 per cent
4. bidding 80 per cent
5. construction administration 100 per cent

Dr. Beller testified that he and plaintiff had signed the contract; that his banker had requested complete plans before any money could be lent; that plaintiff took too much time and interest rates were going up; that it was understood that the house would be built by Christmas but by November 11 he had never received a set of design developments; that he had his attorney send a letter terminating the contract.

There is testimony by a building contractor that from the plans and specifications made by plaintiff, he could build the house. An architect testified that plaintiff has an excellent reputation as an architect in the San Antonio area; that a great deal of work went into the De Lara drawings; and that in his opinion the value of architect’s services on this $69,000 house was 14 per cent of the cost. Another architect testified that the plans were well done; that the reasonable value of the services performed by plaintiff is in the neighborhood of $5,500 to $6,000.

An architect called by defendant testified that plaintiff’s latest plans do not complete the design phase (phase 2) and that he could not prepare phase 3 unless phase 2 was completed; that at mid-phase, the drawings would be of some value, but basically of no value because you could not get a completed price on the house.

A disinterested attorney from San Antonio testified that reasonable attorney’s fees in the case would be $4,500.

By several points of error, defendant complains that the trial court erred in submitting Special Issues Nos. 3 and 4 because the undisputed evidence established that the parties entered into an express contract and quantum meruit was not applicable as a matter of law. The gist of defendant’s contention in this regard is that you cannot recover on an implied contract when there is an express contract, and that plaintiff’s recovery is limited to the contract. This rule is set forth in Woodard v. Southwest States, Inc., 384 S.W.2d 674, 675 (Tex.1964) as follows:

Recovery on an express contract and on quantum meruit are inconsistent. Where there exists a valid express contract covering the subject matter, there can be no implied contract.

Plaintiff asserts that he pleaded both an express contract and, in the alternative, quantum meruit, and relies on the line of cases and authorities that a plaintiff can *321 seek to recover both on an express contract and upon quantum meruit, and can allege and recover as the evidence may show. Colbert v. Dallas Joint Stock Land Bank of Dallas, 129 Tex. 235, 102 S.W.2d 1031 (1937); Olivares v. Porter Poultry & Egg Company, 523 S.W.2d 726 (Tex.Civ.App.— San Antonio 1975, no writ); Freeman v. Carroll, 499 S.W.2d 668 (Tex.Civ.App.—Tyler 1973, writ ref’d n. r. e.); Coon v. Schoeneman, 476 S.W.2d 439 (Tex.Civ.App.—Dallas 1972, writ ref’d n. r. e.); Montclair Corporation v. Earl N. Lightfoot Paving Co., 417 S.W.2d 820 (Tex.Civ.App.—Houston 1967, writ ref’d n. r. e.); Clower v. Brookman, 325 S.W.2d 440 (Tex.Civ.App.—San Antonio 1959, no writ); 13 Tex.Jur.2d Contracts, § 7 at 120 (1960); Rule 48, Tex.R.Civ.P.

In Montclair Corporation v. Earl N. Lightfoot Paving Co., supra, the court said:

It has long and many times been held in this State that though there be an express contract there may be a recovery in quantum meruit if there has been partial performance as distinguished from full performance (citing authorities).

In Freeman v. Carroll, supra, the Court said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

KIVA, Inc. v. Central Texas Barricades
Court of Appeals of Texas, 2010
In Re the Palms at Water's Edge, L.P.
334 B.R. 853 (W.D. Texas, 2005)
Gunter Hotel of San Antonio Inc. v. Buck
775 S.W.2d 689 (Court of Appeals of Texas, 1989)
Truly v. Austin
744 S.W.2d 934 (Texas Supreme Court, 1988)
Tatum v. Tatum
606 S.W.2d 31 (Court of Appeals of Texas, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
565 S.W.2d 319, 1978 Tex. App. LEXIS 3129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beller-v-de-lara-texapp-1978.