Baylor University v. Carlander

316 S.W.2d 277
CourtCourt of Appeals of Texas
DecidedJune 27, 1958
Docket15359
StatusPublished
Cited by10 cases

This text of 316 S.W.2d 277 (Baylor University v. Carlander) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baylor University v. Carlander, 316 S.W.2d 277 (Tex. Ct. App. 1958).

Opinion

YOUNG, Justice.

The suit of appellee architect was for compensation allegedly due under a written contract of employment of date March 10, 1949; the trial court rendering judgment upon jury issues in his favor and against defendant Baylor University for $92,657.42, inclusive of interest to March 25, 1957, attorney’s fees and travel ex *280 penses, after allowance for credits. The recovery was based upon 4}4 percent of the “lowest bona fide bid” ($1,511,194, Lump Sum), as well as the usual reasonable and customary compensation for furnishing completed plans and specifications in accordance with “preliminary studies”. Subject matter was the proposed construction of Tidwell Bible Building on Baylor University Campus at Waco.

After pretrial and sustaining of special exceptions to defendant’s third amended original answer, its principal fact defenses consisted of alleged fraudulent representations made by plaintiff to defendant’s Building Committee in oral statements, letters and conduct concerning cost of the contemplated building, on which they relied; in effect, that such cost would not be substantially in excess of $600,000, and that in consequence of the fraud and misrepresentation plaintiff was not entitled to recover anything under said contract.

Fact questions raised by the testimony and pleading of the respective parties on which they went to trial are reflected in the jury issues and answers; in summary, that (1) the usual, reasonable and customary compensation for all work designed and specified by plaintiff and abandoned by defendant was $68,003.73; (2) after March 10, 1949 (date of contract) plaintiff made trips authorized by defendant; (3) the reasonable expense incurred and paid by plaintiff in connection with such authorized travel was $1,130.73; (4) defendant had knowledge or belief by August 9, 1950 that the proposed building designed by plaintiff would cost substantially in excess of $600,000; (5) defendant had knowledge by August 9, 1950 that would cause a reasonably prudent person to believe that the proposed building designed by plaintiff would cost substantially more than $600,000 to construct; (6) plaintiff, in continuing to work upon final plans and specifications did not rely upon the letter from Guy Newman of August 18, 1950; (7) a reasonable attorney’s fee for plaintiff’s attorneys was $10,000.00; (8) plaintiff Carlander did not represent to defendant’s building committee that cost of the proposed building shown in preliminary drawings, identified as plaintiff’s Exhibits 2-6, would not be substantially more than $600,000. Issues 9, 10, 11 and 12 were conditional on issue 8 and not answered. (13) Plaintiff, in exercise of that degree of care and skill ordinarily exercised by a competent architect under the same or similar circumstances, should have known that such representation, if any, was false (referable to issue 8); (14) plaintiff, before signing the written contract in question, represented to defendant’s Building Committee that in the event the entire building shown in preliminary drawings identified as plaintiff’s Exhibits 2-6 could not be constructed for $600,000, a usable portion of such building could be constructed for such amount; (15) such representation was true. Issues 16, 17 and 18, conditional and not answered. (19) Plaintiff, in exercise of that degree of care and skill ordinarily exercised by competent architects should not have known that such representation was false; (20) plaintiff and defendant’s Building Committee on November 2, 1948 agreed that the $6,000 payment theretofore received by plaintiff was in full payment for all services rendered by him up to that date; (21) after March 10, 1949, date of the written contract, plaintiff did not unreasonably delay completion of final plans and specifications of the building in question; issue 22, conditional, not answered; (23) when the bid of Farnsworth & Chambers was opened plaintiff advised defendant’s Executive Committee that same was unreasonably high; (24) plaintiff acquiesced in and agreed to the rejection of such bid. (Note: The court’s charge included the following instructions: “The term 'represent’ means to make a representation. A representation may be express or implied and may consist of oral or written statements, concealment of information, or other conduct, intended to lead another person to believe in the truth of a particu *281 lar matter of fact.” And relative to jury answer to above issue No. 4, it is conceded in the record that defendant had as much information concerning cost of the proposed building in March 1949 as it had on August 9, 1950.)

Appellant’s first seven points complain of the court’s ruling on special exceptions whereby certain allegations were stricken from defendant’s answer; allegations, in effect, (1) “that plaintiff was in a position of trust and confidence and failed to make a full and complete disclosure of his opinion and belief that the proposed building would probably cost far in excess of the figure he knew defendant intended to spend”; (2) “that an essential term of the agreement between the parties, though not included in the written contract, was that the plans for the proposed building should be prepared in such a manner that the building could be completed with the funds available for that purpose, and that plaintiff failed to prepare the plans in such manner”; (3) “that the written contract was incomplete and ambiguous in that it did not describe particularly the proposed building, and that the parties intended that the building be designed so that it could be erected substantially with the funds available”; (4) “that plaintiff failed to comply with defendant’s instructions concerning the cost of the proposed building”; (5) “that if it was not feasible to carry out defendant’s instructions concerning the cost of the building, plaintiff had the duty to advise defendant of such fact and request further instructions, but that he failed to do so”; (6) “that plaintiff failed to carry out his contract with that degree of care and skill required of an architect, in. that he failed to follow the usual and customary practice in the architectural profession to take into consideration the owner’s known financial resources and either design a building in keeping with such resources, or advise the owner that the owner’s instructions concerning the building could not be carried out within such resources”; (7) “that defendant’s Building Committee had no authority to enter into a contract with plaintiff to prepare plans for a building with no limitation of the cost.”

The remaining nine points of error relate to the court’s rulings during course of trial; such as improper restriction on cross-examination of plaintiff; argument of plaintiff’s counsel, erroneous rendition in plaintiff’s favor for $68,003.73 on various grounds, and lastly to issue No. 1, that the inquiry should have been directed to 1 value of plaintiff’s services rather than to the “usual reasonable and customary compensation.”

It will be observed that defendant’s defenses of fraudulent representations were disposed of adversely to it, which jury findings have not been attacked.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Getzschman v. Miller Chemical Co., Inc.
443 N.W.2d 260 (Nebraska Supreme Court, 1989)
Holmquest v. Priesmeyer
574 S.W.2d 173 (Court of Appeals of Texas, 1978)
Beller v. De Lara
565 S.W.2d 319 (Court of Appeals of Texas, 1978)
Cobb v. Thomas
565 S.W.2d 281 (Court of Appeals of Texas, 1978)
King v. Clodfelter
518 P.2d 206 (Court of Appeals of Washington, 1974)
Moore v. Bolton
480 S.W.2d 805 (Court of Appeals of Texas, 1972)
First National Bank of Bowie v. Elam
432 S.W.2d 186 (Court of Appeals of Texas, 1968)
Rose v. Shearrer
431 S.W.2d 939 (Court of Appeals of Texas, 1968)
Chenault v. County of Shelby
320 S.W.2d 431 (Court of Appeals of Texas, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
316 S.W.2d 277, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baylor-university-v-carlander-texapp-1958.