Holmquest v. Priesmeyer

574 S.W.2d 173, 1978 Tex. App. LEXIS 3744
CourtCourt of Appeals of Texas
DecidedSeptember 28, 1978
Docket17174
StatusPublished
Cited by12 cases

This text of 574 S.W.2d 173 (Holmquest v. Priesmeyer) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holmquest v. Priesmeyer, 574 S.W.2d 173, 1978 Tex. App. LEXIS 3744 (Tex. Ct. App. 1978).

Opinions

EVANS, Justice.

This suit was brought by Larry Priesmeyer, an architect, to recover compensation for architectural services allegedly performed under written contract with the defendants Donald L. Holmquest and wife, Ann J. Holmquest. After a non-jury trial, the trial court entered judgment in favor of the architect for the sum of $2835.00, representing the unpaid balance of the amount due for his services under the contract and for the sum of $1,500.00 as attorney’s fees. The Holmquests bring this appeal.

In their first four points of error the Holmquests challenge the legal and factual sufficiency of the evidence to support the trial court’s monetary award for the value of the architect’s services and its implied finding that the architect had obtained the approval of the Holmquests before performing the work on the construction documents which constitutes the basis for this suit. Under these points the Holmquests argue that the architect failed to prove a right to any monetary recovery under the contract and that he also failed to prove that he had performed a condition precedent specified in the contract requiring that he obtain the owners’ approval to the preliminary drawings before proceeding with the work on the construction documents.

In late 1974 the Holmquests resided in the Bryan — College Station area of Brazos County, Texas, where Dr. Donald L. Holm-quest was employed as an Associate Dean of Medicine at Texas A & M University. According to the architect’s testimony, Dr. Holmquest mentioned to Mr. Raymond Reed, the Dean of the School of Architecture, that he and his wife wished to obtain an architectural design for a house which they planned to construct on some land they owned in that area. Mr. Reed transmitted this information, together with Dr. Holm-quest’s telephone number, to the architect who then contacted Dr. Holmquest. After several preliminary discussions between the Holmquests and the architect concerning the general type and size of the house the Holmquests wished to have designed, the architect prepared a written contract which the parties executed on January 19, 1975.

Under the terms of this contract the architect agreed to perform certain basic services on behalf of the Holmquests: (1) He agreed to consult with them to ascertain their requirements and to prepare schematic designs studies for their approval; (2) He agreed to prepare working drawings and specifications for their approval and to assist them in bidding the property; and (3) He agreed to advise and consult with them and to act as their representative in the construction phase of the project. For these services the parties agreed that the architect would receive as his compensation a sum equal to 9% of the total construction cost of the project payable as follows:

[176]*1761. $100.00 payable upon execution to the agreement, such sum to be deducted from the final payment upon completion of construction.
2. 35% upon completion of the schematic design.
3. 50% upon completion of the construction documents.
4. 15% upon completion of construction.

The contract provided that the architect’s basis compensation was to be determined from “the total cost or the estimated cost” of all work designed or specified by the architect and that for work not constructed such cost was to be “the lowest bona fide bid received from a qualified bidder for any and all of such work.” The contract contained a further provision which stipulated that in the event of termination “due to the fault of other” than the architect, he was to be entitled to compensation for his services performed to the date of termination.

The architect testified that after the execution of the contract he sought to determine from the Holmquests their “likes and dislikes” so that they could better prepare an architectural concept which he prepared to graphically communicate to them by means of schematic design drawings and models. During the spring of 1975, the architect worked on the schematic drawings which later served as a basis for the preparation of a three dimensional model of the architect’s concept. During that period of time and extending into the early summer of 1975, meetings were held between the architect and the Holmquests to discuss the work.

In July 1975, having completed his preliminary design phase of the work, the architect submitted his statement to the Holmquests in the amount of $2,205.00, which sum represented 35% of 9% of an estimated construction cost of $70,000.00. The estimated construction cost was apparently computed on the basis of an approximate $25.00 per square foot cost factor which the parties then considered to be the probable cost of construction.

After the architect completed the schematic design phase of the work, he began preparation of the construction or “working” drawings, and he and the Holmquests continued to have meetings throughout the summer and early fall of 1975. In the latter part of October 1975, a meeting was held between the architect, the Holmquests and two engineers to discuss construction details and costs. At this meeting the Holmquests received certain information from the engineers concerning the proposed foundation which did not meet their expectations, and they also indicated some concern with the architect’s opinion, based upon the “guesstimate” of a builder who had reviewed his working drawings, that the current cost of construction had risen to $30.50 per square foot, resulting in a total cost estimate of approximately $91,000.00.

The testimony is disputed concerning the discussions which occurred between the parties after the October, 1975 meeting. The architect testified that approximately 3 weeks after the meeting he received a phone call from Dr. Holmquest, advising that there had been a change in his wife’s professional plans and that they were no longer in a big hurry to construct the house. The architect was advised that he would take his time with the completion of the working drawings so long as construction could begin about the summer of 1976, and, accordingly, the architect continued with his work and did not contact Dr. Holmquest again until May 1976. At that time he had some difficulty reaching Dr. Holmquest, who failed to return his calls, but finally at the urging of a mutual friend, he made a concerted effort to get in touch with Dr. Holmquest and was able to do so. He advised Dr. Holmquest that the interior elevations were available for review and that the plans could be finalized within the next week. Dr. Holmquest then advised him that he had bought a house in Houston and had the Bryan property up for sale.

The Holmquests testified that after the October meeting, the architect told them that he would contact them “within 3 weeks”, and that when they did not hear from him until May 1976, they assumed that he had abandoned the project.

[177]*177It is the Holmquests’ contention that since the house was not constructed and because the architect did not obtain a bid from a qualified builder which could serve as a basis for computing the construction cost of the project, he did not prove that he was entitled to recover any compensation for the construction document phase of the work. This contention will be overruled.

The contract provision for determining the total construction cost based upon a bid of a qualified builder contemplates that completed construction documents would be available to the architect for delivery to the builder.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bobby Ferachi v. Shawn Cady
Court of Appeals of Texas, 2009
Opinion No.
Texas Attorney General Reports, 1999
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 1999
Voskamp v. Arnoldy
749 S.W.2d 113 (Court of Appeals of Texas, 1988)
American Quality Roofing, Inc. v. Ipock
730 S.W.2d 470 (Court of Appeals of Texas, 1987)
Puckett v. First City National Bank of Midland
702 S.W.2d 232 (Court of Appeals of Texas, 1985)
De La Fuente v. Home Savings Ass'n
669 S.W.2d 137 (Court of Appeals of Texas, 1984)
Langston v. Brewer
649 S.W.2d 827 (Court of Appeals of Texas, 1983)
Holmquest v. Priesmeyer
574 S.W.2d 173 (Court of Appeals of Texas, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
574 S.W.2d 173, 1978 Tex. App. LEXIS 3744, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holmquest-v-priesmeyer-texapp-1978.