Zannoth v. Booth Radio Stations, Inc.

52 N.W.2d 678, 333 Mich. 233, 1952 Mich. LEXIS 469
CourtMichigan Supreme Court
DecidedApril 7, 1952
DocketDocket 41, Calendar 45,260
StatusPublished
Cited by11 cases

This text of 52 N.W.2d 678 (Zannoth v. Booth Radio Stations, Inc.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zannoth v. Booth Radio Stations, Inc., 52 N.W.2d 678, 333 Mich. 233, 1952 Mich. LEXIS 469 (Mich. 1952).

Opinion

Butzel, J.

Plaintiff, George G. Zannoth, an architect, sought recovery in 1 suit for architectural services rendered during 1946, and 1947 for Booth Radio Stations, Inc., defendant, for 4 different building jobs, 2 in Flint, Michigan, and 2 in Highland Park, Michigan. They will be discussed separately where different problems are involved.

The 2 buildings in Flint were completed. Those in Highland Park were to consist of a small transmitter station, and also a large building on Midland ■avenue for a studio and transmitter station. .The latter building was never built and defendant contends that plaintiff has failed to prove any liability, even on a quantum meruit count, for any services rendered in ■ planning this building. Defendant agrees that there is still an amount due plaintiff for services rendered for the 2 Flint buildings, but plaintiff disputes defendant’s claim that certain credits should be allowed as setoffs. There is also a *236 dispute in regard to the charges for plans for the small transmitter station in Highland Park.

At the end of the trial, after both sides had rested, the trial judge decided that the case presented no questions of fact, but only those of law, and directed a verdict in the full amount claimed by plaintiff for work on the 2 buildings in Flint and plans for the small station in Highland Park, amounting in the aggregate to $7,284.48 and $50 costs; at the same time directing a verdict of no cause of action in favor of defendant on plaintiff’s claim for architectural fees for the large Highland Park building.

Plaintiff appeals from the disallowance of his claim for services for the contemplated large Highland Park building, and defendant cross-appeals from amounts allowed plaintiff for the other 3 buildings. The case is appealed on 1 record which contains the testimony in regard to the various claims.

Flint jobs. The parties contracted for the construction of a radio transmitter building on Bristol road in Flint on December 17, 1946. The contract provided as follows:

“The owner agrees to pay the architect for such services a fee of 6% of the cost of the work. * * * Charges for previous preliminary work submitted before Dec. 17, are at the rate of $6 per hour, as set forth in letter of November 30, 1946. * * *
“1. The architect’s services. — The architect’s professional services consist of the necessary conferences, the preparation of preliminary studies, working drawings, specifications, large scale and full size detail drawings; the drafting of forms of proposals and contracts.”

Another contract for remodeling a store at 112 W. Water in Flint for radio broadcasting studio and offices was signed on February 17,1947, and contains similar provisions except that 8% of the cost of the ■work was to-be the base rate.

*237 In each, case, it appears that plaintiff did some work consisting of drawing sketches, plans and specifications, as well as participating in certain conferences, before the contracts were signed.' All of the work before the dates of such contracts was billed and paid for at the rate of $6 an hour by defendant. The cost of the buildings and the percentage thereof to which plaintiff is entitled was agreed to by the parties. The only dispute appears to be whether or not defendant is entitled to offset the payments made for work done prior to entering into the written contracts against plaintiff’s stipulated fees under the contracts. The trial court denied the offset.

There was no error. Ordinarily tinder the standard architect’s contract, the base rate, as is specified by the parties, would include all of the work done by the architect, as nothing therein is said about 2 kinds of preliminary work; but the instant contracts clearly state that previous preliminary work will be paid for at the rate of $6 an hour. Defendants contend that the hourly provision was simply a method of devising payments from time to time to apply on the fees for the completed building. However, there would be no reason for adding a provision for such payments as the method of payment under the contract is already covered by the standard form of •architect’s contract. Judgment denying defendant the right to offset payments and holding in favor of plaintiff for the amounts claimed by plaintiff and as found by the trial court is affirmed.

Highland Parle studio and transmitter building. Plaintiff first was contacted by defendant relative to building a broadcasting studio and transmitter building on Midland avenue in Highland Park on September 9,1946, when John Lord Booth, president of defendant, proposed a very complete and attractive building. During the following winter plaintiff drew various preliminary sketches of the proposed. *238 building and delivered the first blueprints in February, 1947. To the Civilian Production Administration plaintiff estimated the cost of the building as $45,000, but it is claimed and not denied that this was at the request of Booth, who hoped a smaller building’ would .be approved more readily.

Karl B. Foster, a general contractor, was contacted by Booth in March, 1947, relative to the construction of such a building which Foster thought at the time would cost at least $250,000. Preliminary work on the site began April 1st. In the meantime, work on the-2 Flint jobs had been begun and was concluded later in 1947. Their cost went far beyond the original estimates. After a certain number of conferences relative to the Highland Park building, the work was abandoned until June when CPA restrictions were lifted.

Early in July, 1947, public ground-breaking ceremonies took place at the site. Booth publicly stated that the building was to cost $100,000. After more preliminary plans and sketches, and on August 6, 1947, the written agreement was signed providing for 8% of final cost as plaintiff’s fee. During August, 1947, both parties made a definite attempt to cut the cost of the proposed building. Plaintiff, Foster and Clark, the vice-president of defendant, met at Flint just prior to August 25th and Clark testified he stated there that the cost of such building could be no more than $55,000, or a simple transmitter building should be built instead. Plaintiff and Foster deny that costs were discussed at the meeting. On August 25, 1947, Booth requested that a substantial part of the proposed building, including the entire second floor, be omitted from future planning' in an effort to cut final building costs. Obviously he expected the costs to be cut substantially by such extreme measures.

On September 4, 1947, Booth wrote plaintiff a *239 letter in which he directed further omissions and explicitly stated that the building was not to cost in excess of $52,500. Plaintiff; replied on September 6th that no estimate of costs could be made until the plans were complete in detail. He consistently maintained this position until November, 1947, when the first bids were received, in the meantime, refusing to make any kind of statement as to what the costs of the project would be. The general contractor had not been notified of the maximum which had been set.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Post, Buckley, Schuh & Jernigan, Inc. v. Monroe County
851 So. 2d 908 (District Court of Appeal of Florida, 2003)
Getzschman v. Miller Chemical Co., Inc.
443 N.W.2d 260 (Nebraska Supreme Court, 1989)
Williams Engineering, Inc. v. Goodyear
496 So. 2d 1012 (Supreme Court of Louisiana, 1986)
Reynolds v. Long
154 S.E.2d 299 (Court of Appeals of Georgia, 1967)
George Wagschal Associates, Inc. v. West
107 N.W.2d 874 (Michigan Supreme Court, 1961)
Warburton v. Tacoma School District No. 10
350 P.2d 161 (Washington Supreme Court, 1960)
Baylor University v. Carlander
316 S.W.2d 277 (Court of Appeals of Texas, 1958)
Parrish v. Tahtaras
318 P.2d 642 (Utah Supreme Court, 1957)
Shannon v. Polish Falcons of America
82 N.W.2d 523 (Michigan Supreme Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
52 N.W.2d 678, 333 Mich. 233, 1952 Mich. LEXIS 469, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zannoth-v-booth-radio-stations-inc-mich-1952.