Parrish v. Tahtaras

318 P.2d 642, 7 Utah 2d 87, 1957 Utah LEXIS 196
CourtUtah Supreme Court
DecidedNovember 26, 1957
Docket8514
StatusPublished
Cited by12 cases

This text of 318 P.2d 642 (Parrish v. Tahtaras) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parrish v. Tahtaras, 318 P.2d 642, 7 Utah 2d 87, 1957 Utah LEXIS 196 (Utah 1957).

Opinion

McDONOUGH, Chief Justice.

Defendants appeal from an adverse judgment in an action by an architect, Lowell Parrish, for the value of his services in designing and planning a home for defendants, Mr. and Mrs. Tahtaras.

Defendants assail the findings of the trial court, sitting without a jury, the sufficiency of the findings of the court to support, the judgment, and the introduction of evidence based on quantum meruit, which was unpleaded until the complaint was amended. Plaintiff stands both on the sufficiency of the record to support the findings, and on the contract of services, including application of the doctrine of quantum meruit

*89 Since the court made findings and entered judgment based thereon, it is our duty to review the evidence in a light most favorable to the findings. 1 In reciting the facts, therefore, we state them as found by the trial court so long as the. record shows some competent evidence from which such findings could derive.

In April of 1954, Mr. and Mrs. Tahtaras engaged the services of architect Lowell Parrish to design for them a custom residence on a lot owned, by defendants in Indian Hills Subdivision, Salt Lake City, Utah. The court found that under the ■agreement the total cost of said residence should not exceed $65,000, including architect’s fees. This cost limitation, however, was set orally after the signing of a standard architect’s contract, and there is evidence to support a finding that no other lower figure was discussed prior thereto. Between April, 1954, and January, 1955, plaintiff prepared the drawings and specifi■cations, consulted with defendants, directed certain alterations and prepared there-after the final sketches, drawings and •specifications for the home on defendants’ lot. Bids were called for. They ranged from $73,280 to $90,000. At all times the ■plaintiff was ready, willing and able to reduce the plans to meet the cost limitation •of $65,000 imposed by the above described mutual oral agreement, and in fact made, under direction of defendants, one subsequent alteration in the plans after being directed by the defendants to “go ahead do what is necessary.” Thereafter he resubmitted them for rebidding. On January 14, .1955, after defendants had rejected the rebids, they notified plaintiff of their intention to abandon the project of constructing a residence; and thereafter nothing further was. done with the plans. Immediately plaintiff sent a bill for services up to that point. Defendants had paid $1,300 to Mr. Parrish, and when they refused to pay the balance, plaintiff brought this action to recover damages by reason of the contract breach. Defendants counterclaimed for the $1,300 alleging a nonperformance on Parrish’s part in failing to keep within either a $40,000 limit or the $65,000 limit. The trial court, as recited above, found no limitation of $40,000 imposed, found a cost limitation of $65,000, including architect’s fees, found plaintiff ready, willing and able to perform his part of the contract, and awarded damages in the sum of $1,709.27 on the theory of quantum meruit, after granting a motion to amend the pleadings to conform to the proof.

The following should be observed with respect to the cost limitation found by the trial court. The only place in the record where a cost limitation of $65,000 is to be found is in the testimony of the plaintiff. *90 This is to the effect that after the plans and specifications were completely prepared and submitted to the defendants, a discussion was had with respect to the probable cost. In connection therewith, Mr. Tahtaras stated that he would be willing to go as high as $65,000. True, the findings of fact of the trial court would indicate that he concluded that there was a $65,000 limitation, including architectural fees, at the time of the authorization to prepare the plans. However, this must have been inferred by the trial court from the conversation testified to subsequent to the drawing of the plans and from evidence offered as to the general custom of architects relative to having an approximation of costs before commencing his work as an architect. It is mentioned because at that time a great portion of the plaintiff’s work as an architect, other than the supervision of construction, had been then completed.

Under the facts found by the trial court, we confront the question of whether the architect may prevail in an action for his services rendered under a contract or by quantum meruit, in the alternative.

It is the general rule that an architect may not recover for services rendered when his contract of employment specifically limits the total construction cost to an amount stated as a conditional cost limitation, without complying substantially with such condition. Wetzel v. Roberts, 296 Mich. 114, 295 N.W. 580; Zannoth v. Booth Radio Stations, Inc., 333 Mich. 233, 52 N.W.2d 678; Annotation 127 A.L.R. 410. However, such general rule is not here applicable. The defendants abandoned by an unequivocal act the project after they had told plaintiff to go ahead and modify the plans to come within the cost limitations set, and while plaintiff remained ready, willing and able to proceed with such modifications for a second time, the first modification having been rebid and rejected by the defendants.. In the case of abandonment by the owners of their contract with an architect, where the architect is in the process of fulfilling the conditions under his contract for services, the architect may bring an action for damages on the contract, or in the alternative, sue in quasi contract under the theory of quantum meruit. Bebb v. Jordan, 111 Wash. 73, 189 P. 553, 9 A.L.R. 1035. This is but an application of the general rule of contracts, which, in reference to the factual situation here confronted, is aptly stated in 3 Corbin on Contracts, page 953, as follows:

“It is to be observed that since the defendant’s duty to pay was originally conditional on a performance by plaintiff, the defendant’s refusal to pay would not have been wrongful except for the fact that the nonperformance of the condition was unjustly caused by himself. It is his prevention of per *91 formance of the condition that makes his refusal to pay a breach of contract. Prevention eliminates the condition, for purposes of remedy. But the extent of that remedy is governed by the usual remedial rules. If the defendant’s prevention has saved some expenditure on the plaintiff’s part, the amount of that saving must he deducted from the full contract price. It is only the balance to which judgment will be given as damages for defendant’s breach.”

The alternate remedies, although formerly limited by a strict election doctrine, may be pleaded in alternative form and may even be inserted by amendment late in the proceedings. Taylor v. E. M. Royle Corp., 1 Utah 2d 175, 264 P.2d 279; U.R.C.P. Rule 54(c) (1); Restatement of Contracts, Section 381, Comment b. By the use of the alternative pleading of restitution asked under quantum meruit, a total breach of the contract may result in rescission with the remedy of restoration of that which is owing the parties for their reliance on the contract. Thompson v. Miller, 101 Vt. 452, 144 A. 376.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Helf v. Chevron U.S.A. Inc.
2015 UT 81 (Utah Supreme Court, 2015)
Butera v. Boucher
798 A.2d 340 (Supreme Court of Rhode Island, 2002)
Romy Hammes, Inc. v. McNeil Construction Co.
532 P.2d 263 (Nevada Supreme Court, 1975)
Siegal v. Haver
417 P.2d 928 (Court of Appeals of Arizona, 1966)
Barnes v. Lozoff
123 N.W.2d 543 (Wisconsin Supreme Court, 1963)
Lynch v. MacDonald
367 P.2d 464 (Utah Supreme Court, 1962)
Allsup v. Space
367 P.2d 531 (New Mexico Supreme Court, 1961)
Warburton v. Tacoma School District No. 10
350 P.2d 161 (Washington Supreme Court, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
318 P.2d 642, 7 Utah 2d 87, 1957 Utah LEXIS 196, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parrish-v-tahtaras-utah-1957.