Gunter Hotel of San Antonio Inc. v. Buck

775 S.W.2d 689, 1989 Tex. App. LEXIS 2438, 1989 WL 107248
CourtCourt of Appeals of Texas
DecidedJune 28, 1989
Docket04-87-00402-CV
StatusPublished
Cited by5 cases

This text of 775 S.W.2d 689 (Gunter Hotel of San Antonio Inc. v. Buck) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gunter Hotel of San Antonio Inc. v. Buck, 775 S.W.2d 689, 1989 Tex. App. LEXIS 2438, 1989 WL 107248 (Tex. Ct. App. 1989).

Opinion

*691 OPINION

CARR, Justice.

This is a construction contract case. The appellant (Hotel) filed suit seeking a declaratory judgment that appellee (Buck) had been fully paid under its interpretation of the contract, and asserting causes of action for breach of contract and negligence. Buck counterclaimed for alleged fees due under the contract calculated on a percentage basis on the planned future additions and for lost profits.

The record reflects that in the spring of 1981, the Hotel employed Buck by written contract as the project architect for the Hotel. The contract covered renovation and new construction. Three projects were involved, the renovation of the Hotel itself, the construction of a new structure adjacent to the Hotel, which the parties generally called the “Travis Tower,” and a structure connecting the Hotel and the Travis Tower, which the parties called the “forty-foot addition.”

It is undisputed that the terms of the written contract are contained in three documents consisting of:

(1) a letter agreement dated May 7,1981;

(2) Standard Form of Agreement Between Owner and Architect. AIA Document B141 (for a definition of phases as referred to in the letter agreement); and

(3) a letter of agreement dated April 16, 1982, modifying the May 7, 1981 agreement.

Under the terms of the initial May 1981 contract, Buck was to be compensated by receiving a percentage of the construction costs for each of the projects, receiving 7% for the renovation and 5.75% for new construction. (In the April 16, 1982 letter, Buck subsequently agreed “since the scope of the Travis Tower has been greatly increased” to 4.25% of architectural fees for new construction of the Travis Tower.) The contract also provided that “the work will be billed at the hourly rate during the schematic phase until a budget is established.”

Buck was fully paid on his work on the renovation project for which no claim is sought.

Following trial, the jury found that Buck was entitled to a percentage fee for both the Tower and the forty-foot addition, that Buck had substantially performed, that the Hotel had illegally terminated Buck, that Buck was entitled to percentage fees of $121,281.00 for the Tower and $38,036.00 for the addition, plus lost profits of $100,-000.00 and $40,000.00 in attorneys’ fees. The Hotel was denied its claim for engineering fees. The trial court disregarded the award of lost profits on the Hotel’s motion but otherwise entered judgment on the verdict. This appeal followed.

Appellant has raised several points of error challenging the legal and factual sufficiency of the evidence to support the jury’s answers to special issues. Our standard of review applicable to each legal and factual insufficiency point of error is well settled.

A legal sufficiency point challenges the lack of competent evidence on some vital finding made by the trial court. “No evidence” points may only be sustained when the record discloses one of the following situations:

(a) a complete absence of evidence of a vital fact;

(b) the court is barred by rules of law or of evidence from giving weight to the only evidence offered to prove a vital fact;

(c) the evidence offered to prove a vital fact is no more than a mere scintilla;

(d) the evidence establishes conclusively the opposite of the vital fact.

Aetna Insurance Company v. Klein, 160 Tex. 61, 325 S.W.2d 376 (1959). When reviewing a “no evidence” challenge, this Court should consider only the evidence and reasonable inferences drawn from the evidence which support the jury verdict. Stafford v. Stafford, 726 S.W.2d 14 (Tex.1987). The Court must disregard all evidence and inferences to the contrary. Aim v. Aluminum Company of America, 717 S.W.2d 588, 593 (Tex.1986) If there is more than a scintilla of evidence to support the finding, the no evidence challenge must fail. See Stafford, 726 S.W.2d at 16. If the evidence furnishes some reasonable ba *692 sis for differing conclusions by reasonable minds as to the existence of the vital fact, it amounts to more than a scintilla of evidence. Kindred v. Con/Chem, Inc., 650 S.W.2d 61, 63 (Tex.1983).

Factual sufficiency points, on the other hand, maintain that the evidence is factually insufficient to support a finding of a vital fact or the finding of the vital fact is so contrary to the great weight and preponderance of the evidence as to be clearly wrong. Lofton v. Texas Brine Corp., 720 S.W.2d 804, 805 (Tex.1986). In reviewing a factual insufficiency challenge, the Court must first examine all of the evidence, and having considered and weighed all of the evidence, the Court may set aside the verdict only if it is so contrary to the overwhelming weight of the evidence as to be clearly wrong and unjust. Cain v. Bain, 709 S.W.2d 175, 176 (Tex.1986). An appellate court cannot pass upon the credibility of the witnesses or substitute its judgment for that of the trier of fact, even if there is conflicting evidence upon which a different conclusion could be supported. Clancy v. Zale Corporation, 705 S.W.2d 820, 826 (Tex.App.—Dallas 1986, writ ref’d n.r.e.).

In the first and second points of error, appellant alleged that the evidence was legally and factually insufficient to support the jury’s answer to Special Issue No. 1, wherein the jury found that all conditions of the contract were satisfied entitling Buck to a percentage fee for his services attributable to the schematic phase of the new tower.

The central issue in appellant’s first two points of error is the method by which Buck is entitled to calculate his contract compensation for his work on the proposed new construction of the Travis Tower. The Hotel contends that he is limited to an hourly fee because no budget was “established” within the meaning of the contract. Buck contends that he may calculate his fee as a percentage of the construction costs because he has completely complied with his contract architectural “duties” and “responsibilities” pertaining to his architectural services to be rendered in the schematic phase of the proposed new tower as set out in the contract.

Both parties agree that the issue is governed by the contract which clearly indicates the intention of the parties, that Buck is to be compensated on a percentage of the total construction cost basis when a budget is established. The term “budget is established” is not defined in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pinnacle Anesthesia Consultants, P.A. v. Fisher
309 S.W.3d 93 (Court of Appeals of Texas, 2010)
Stamp-Ad, Inc. v. Barton Raben, Inc.
915 S.W.2d 932 (Court of Appeals of Texas, 1996)
Indian River Colony Club, Inc. v. Schopke Const. & Engineering, Inc.
592 So. 2d 1185 (District Court of Appeal of Florida, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
775 S.W.2d 689, 1989 Tex. App. LEXIS 2438, 1989 WL 107248, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gunter-hotel-of-san-antonio-inc-v-buck-texapp-1989.