Kleiner v. Eubank

358 S.W.2d 902, 1962 Tex. App. LEXIS 2580
CourtCourt of Appeals of Texas
DecidedJune 13, 1962
Docket10956
StatusPublished
Cited by30 cases

This text of 358 S.W.2d 902 (Kleiner v. Eubank) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kleiner v. Eubank, 358 S.W.2d 902, 1962 Tex. App. LEXIS 2580 (Tex. Ct. App. 1962).

Opinion

RICHARDS, Justice.

Our original opinion is withdrawn and the following opinion is substituted. Suit was brought by H. E. Eubank upon a promissory note in the sum of $17,580.00 executed by Elizabeth Kleiner, a feme sole, appellant, in favor of Mr. and Mrs. James W. Bird, the note being secured by a mechanic’s lien contract and deed of trust entered into between appellant as owner and Mrs. Bird as builder for the construction of a house to be built upon appellant’s property in the City of Austin. The note, together with the mechanic’s lien contract and deed of trust had been assigned by Mr. and Mrs. Bird to Eubank after its maturity.

In his petition Eubank first sought recovery against appellant on the note for $17,580.00, together with 10% interest from maturity and 10% attorneys’ fees as provided therein and for foreclosure of the mechanic’s lien contract and deed of trust upon appellant’s property. In the alternative, in the event Eubank was not entitled to recover upon the note, recovery was sought against appellant for the full contract price of $17,580.00 as evidenced by the contract and note, together with interest and attorneys’ fees and foreclosure of the liens, Eubank alleging that Mr. and Mrs. Bird, hereinafter referred to as “builder”, had entered upon the construction of and substantially completed the house according to the contract and plans and specifications.

It was also alleged that appellant, hereinafter referred to as “owner”, had requested certain extras, changes and modifications of the plans and specifications as agreed upon between the owner and the builder which had been completed by the builder and that the reasonable value of the work done and material furnished was $1,304.39, upon which sum certain credits in the sum of $560.00 had been allowed the owner by the builder and that as a result of the substantial completion of the construction contract and the furnishing of the extras the owner was indebted to Eubank as assignee of the builder in the sum of $18,324.39.

As a second alternative cause of action Eubank alleged that in the event that the builder did not substantially complete the construction contract, then the performance of the contract was prevented by the conduct of the owner in making unreasonable and arbitrary demands upon the builder and interfering with the completion of the work according to the contract, thereby preventing the builder from fully performing the contract and that since the builder had partially performed the construction of the house, the owner had taken possession, and had benefited therefrom for the reasonable value of the work performed and materials furnished in the sum of $18,324.34.

Under the alternative allegations based upon the note, mechanic’s lien and deed of trust, Eubank alleged that he was entitled to recover attorneys’ fees in the amount of 10% of the obligation plus 10% interest from the date of the maturity of the note.

*904 Eubank also joined as parties defendant Freddie Lee Parks, Morris A. Walden, James Anthony, Robert L. Wilkes and Cal-casieu Lumber Company alleging that such parties had asserted claims as materialmen and laborers for materials furnished and work performed on the house. Each of the materialmen and laborers as cross-plaintiffs brought cross-actions against Mrs. Bird as builder for the amounts owed them alleging the furnishing of work or materials and asking for the establishment and enforcement of mechanic’s liens against the owner’s property.

The trial was to a jury and based upon the jury’s answers to the special issues the Trial Court entered judgment in favor of Eubank against appellant Kleiner in the aggregate amount of $23,775.67, being (1) for the sum of $15,580.00 on the alleged contract, plus $1,620.00 for “extras furnished” with interest on both sums “from November 15, 1959” at 10% per annum in the sum of $2,723.34, together with attorneys’ fees calculated at 10% of the total of the foregoing amounts in the sum of $1,-992.33 and interest on the entire amount at the rate of 10% per annum until paid; (2) for $1,860.00 as “damages” with interest thereon at the rate of'6% from the date of the judgment until paid and costs of suit; and (3) for foreclosure of the mechanic’s lien asserted against appellant’s property.

The impleaded laborers and materialmen were awarded judgment against Mrs. Bird as builder for the amounts of their claims plus interest and attorneys’ fees and foreclosure of the mechanic’s and materialmen’s liens against appellant’s property with a proviso that the proceeds of the sale under foreclosure be applied, first, to the payment of the cost of suit, second, to the payment of the laborer’s and materialmen’s liens, and third, to the payment of the judgment and lien in favor of Eubank, from which judgment this appeal has been perfected.

Appellant predicates her appeal upon five points of error, the first two of which are based upon the jury’s answer to Special Issue No. 2 that the failure of the builder to complete the house in a good and workmanlike manner according to the plans and specifications was caused by interference or delay on the part of the owner upon the ground that there was no evidence to support the finding of the jury, or in the alternative that the finding is contrary to the overwhelming weight and preponderance of the evidence.

Special Issue No. 2 is as follows:

“Do you find from a preponderance of the evidence that Mrs. J. W. Bird’s failure to complete the house in question in a good workmanlike manner according to the plans and specifications was caused by interference or delay on the part of the Defendant Kleiner, if any?”

to which the jury answered “Yes”.

From a careful examination of the statement of facts, consisting of 800 pages, it is our opinion that appellant’s first two points of error are without merit and must be overruled. The testimony of both the owner, the builder and the various subcontractors and materialmen (cross-plaintiffs) is conflicting as to whether the failure of the builder to complete the house in a good workmanlike manner according to the plans and specifications under the terms of the contract was caused by the interference and delay on the part of the owner or by the admitted failure of the builder and her subcontractors and materialmen to perform their respective obligations under their contracts in a good and workmanlike manner and to furnish materials and perform the work in compliance with the plans and specifications.

Appellant objected to the submission of Special Issue No. 2 upon the ground that it was a general charge and that the jury were not given any standard by which they could gauge the completion of the house and further that the issue should inquire as to the builder’s failure to substantially complete the house with an appropri *905 ate explanatory definition of the phrase “substantially complete” which objection was refused by the Trial Court. Appellant did not request the submission of any issue as to whether the builder’s failure to substantially complete the house according to the plans and specifications was due to the delays caused by the builder’s or the subcontractor’s and materialmen’s failure to furnish materials and perform their work in a good workmanlike manner according to the plans and specifications and thereby waived the submission of such issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. Wallace v. Flintco Inc.
143 F.3d 955 (Fifth Circuit, 1998)
Ramirez Co. v. Housing Authority of City of Houston
777 S.W.2d 167 (Court of Appeals of Texas, 1989)
Gunter Hotel of San Antonio Inc. v. Buck
775 S.W.2d 689 (Court of Appeals of Texas, 1989)
Shafer Plumbing & Heating, Inc. v. Controlled Air, Inc.
742 S.W.2d 717 (Court of Appeals of Texas, 1987)
Box v. Au Forgeron de la Cour-Dieu, Inc.
708 S.W.2d 538 (Court of Appeals of Texas, 1986)
Skaggs v. Guerra
704 S.W.2d 51 (Court of Appeals of Texas, 1985)
Employers Insurance of Wausau v. Schaefer
662 S.W.2d 414 (Court of Appeals of Texas, 1983)
Manufactured Housing Management Corp. v. Tubb
643 S.W.2d 483 (Court of Appeals of Texas, 1982)
Beeman v. Worrell
612 S.W.2d 953 (Court of Appeals of Texas, 1981)
Longoria v. Atlantic Gulf Enterprises, Inc.
572 S.W.2d 71 (Court of Appeals of Texas, 1978)
Herron v. Lackey
554 S.W.2d 708 (Court of Appeals of Texas, 1977)
J. Weingarten, Inc. v. Higginbotham
523 S.W.2d 450 (Court of Appeals of Texas, 1975)
McCRACKEN CONSTRUCTION CO., INC. v. Urrutia
518 S.W.2d 618 (Court of Appeals of Texas, 1974)
Williams v. General Motors Corporation
501 S.W.2d 930 (Court of Appeals of Texas, 1973)
International Security Life Insurance Co. v. Finck
475 S.W.2d 363 (Court of Appeals of Texas, 1971)
Hays v. H. J. Hogan, Inc.
474 S.W.2d 330 (Court of Appeals of Texas, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
358 S.W.2d 902, 1962 Tex. App. LEXIS 2580, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kleiner-v-eubank-texapp-1962.