Emerson Construction Company, Inc. and Western Surety Company v. Ranger Fire, Inc.
Opinion
TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN
JUDGMENT RENDERED AUGUST 29, 2013
NO. 03-09-00567-CV
Emerson Construction Company, Inc. and Western Surety Company, Appellants
v.
Ranger Fire, Inc., Appellee
APPEAL FROM THE 146TH DISTRICT COURT OF BELL COUNTY BEFORE CHIEF JUSTICE JONES, JUSTICES HENSON AND GOODWIN AFFIRMED -- OPINION BY JUSTICE GOODWIN; JUSTICE HENSON NOT PARTICIPATING
THIS CAUSE came on to be heard on the record of the court below, and the same being
considered, it is the opinion of this Court that there was no error in the trial court’s judgment: IT
IS THEREFORE considered, adjudged and ordered that the judgment of the trial court is in all
things affirmed. It is FURTHER ordered that the appellants pay all costs relating to this appeal,
both in this Court and the court below; and that this decision be certified below for observance.
Free access — add to your briefcase to read the full text and ask questions with AI
Emerson Construction Company, Inc. and Western Surety Company v. Ranger Fire, Inc. (Emerson Construction Company, Inc. and Western Surety Company v. Ranger Fire, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.