Bulldog Ironworks, LLC v. Top Flight Steel, Inc.

CourtCourt of Appeals of Texas
DecidedNovember 9, 2012
Docket05-10-01360-CV
StatusPublished

This text of Bulldog Ironworks, LLC v. Top Flight Steel, Inc. (Bulldog Ironworks, LLC v. Top Flight Steel, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bulldog Ironworks, LLC v. Top Flight Steel, Inc., (Tex. Ct. App. 2012).

Opinion

AFFIRM; Opinion flIed November 9,2012.

In The nurt nf Awi1i FiftIi Jitrirt Uf ixai tt ht11wi No. 05-10-01360-CV

BULLDOG IRON WORKS, L.L.C., Appellant

V.

TOP FLIGHT STEEL, INC., Appellee

On Appeal from the County Court at Law No. 2 I)allas County, Texas Trial Court Cause No. CC-09-04424-B

MEMORANDUM OPINION Before Justices Moseley, Lang-Miers, and Murphy Opinion By Justice Moseley

This is an appeal from a non-jury trial in a construction contract dispute between two

subcontractors. Bulldog Ironworks, L.L.C. sued Top Flight Steel, inc. asserting Top Flight failed

to complete its subcontract to erect steel dumpster panels and seeking to recover expenses Bulldog

incurred performing that job. Top Flight filed a counterclaim for breach of contract to recover the

remaining balance of its subcontract. After a bench trial, the trial court rendered judgment that

Bulldog take nothing from Top Flight and that Top Flight recover the balance on the subcontract plus

attorney’s fees. The trial court filed written findings of fact and conclusions of law.

Bulldog raises nine issues on appeal; in general Bulldog challenges the factual sufficiency

of the evidence to support the findings rejecting its claim and supporting the judgment for Top Flight. The background of the case and the evidence adduced at trial are well known to the parties:

thus, we do not recite them here in detail. Because all dispositive issues are settled in law, we issue

this memorandum opinion. TEx. R. Apr. P. 47.2(a). 47.4. We affirm the trial court’s judgment.

FAcTu,L B&cKGR0UND

This case concerns the installation of steel—reinforced concrete panels around the trash

dumpsters at a shopping center project. The geieral contractor, Mycon Construction Company,

subcontracted with Bulldog to fabricate the steel and erect the stcel-reinfbrced concrete panels for

the project. Bulldog in turn subcontracted the erection of the panels to Top Flight under a fixed-price

contract.

Before construction, Terry Blair for Top Flight, Eddie Gaston for Mycon. and Kevin Lassiter

for the concrete supplier, Pavecon, met at the site to determine the layout and construction

sequencing of the main building panels. At the time of the meeting, the plans for the dumpster

panels were not finalized and the sequencing and placement of the dumpster panels were not

decided.

The evidence conflicts about what happened at the meeting regarding the dumpster panels.

Gaston testified that Blair said the panels were light and could be poured anywhere without a

problem. Blair testified he told Gaston to pour the panels within fifty feet of where they needed to

be installed and he could install them. Lassiter agreed that Blair told Gaston about the fifty-foot

requirement. Lassiter said it was common for erectors to use a fifty-foot spacing requirement.

After the panels for the main building had been installed, the dumpster panels were ready to

be poured by the concrete supplier. It is undisputed that Gaston (for Mycon) directed Pavecon to

pour the dumpster panels on the front parking lot, several hundred feet from where they would be

installed at the back of the building. Bulldog was not involved in this decision.

—2— A few weeks after the dumpster panels had been poured, a Top Flight crew came out to

install them. Blair testified he was shocked that the panels had been poured in the front parking lot

and called Gaston to complain. Blair told Gaston Top Flight would have to bring a truck and a crane

to move the panels to the back before installing them and that there would be an additional cost.

Gaston responded that Blair had agreed the panels could be poured anywhere and could be installed

with no problem. Blair denied making that statement.

Shortly thereafter in December 2008, lop Flight sent an e-mail to Bulldog requesting a

change order for 7,500 for the extra cost of moving the panels, i.e., for the extra time involved and

the expense of a tnick and crane. Bulldog attempted to get Mycon to agree to the change order, but

Mycon refused. There is conflicting evidence about whether Top Flight was informed there would

be no change order, lop Flight’s president, Jaime Chacon, testified that Top Flight was willing to

install the panels before approval of a change order, but that it was never told when the panels were

ready to be installed. Blair testified that even without the change order, they probably could have

worked something out to do the installation. He said they could have negotiated the price of the

extra work, but no one asked to do so. Blair testified Gaston called him several times about

installing the panels, but when Blair went to the site, it was not prepared for the installation. Gaston

testified Top Flight refused to install the panels without the change order.

According to Bulldog, Mycon insisted that if the panels were not installed by April 2009, it

would hire another contractor to do the work and charge Bulldog for the expense. Bulldog then

rented equipment and used its own employees to install the panels, beginning March 31, 2009. On

April 1, 2009, unaware that Bulldog was doing the work, Chacon sent an e-mail to Bulldog asking

when Mycon would be ready to install the panels and stated he needed the change order. Soon after

this Blair went to the site and discovered that the panels had already been installed.

—)— Bulldog invoiced Top Flight for 815,7 19.60 for the cost of labor and equipment rentals for

installing the panels. Top Flight refused to pay. The evidence indicates that Top Flight had been

paid all of its contract price except the last ten percent ($ 10,894.20), which was retained by the general contractor until resolution of this dispute. Bulldog sued Top Flight for breach of contract

to recover the additional expense. Top Flight tiled a counterclaim for breach of contract and sought

to recover the balance due on the subcontract.

The trial court rendered judgment that Bulldog take nothing on its claim and Top Flight

recover the retainage amount from Bulldog plus prejudgment interest and attorney’s fees. The trial

court found, among other things, that Top Flight performed the entire contract except for installing

the dumpster panels, that Bulldog did not notify Top Flight to complete installation of the panels,

that Top Flight did not breach the subcontract, and that Bulldog breached the subcontract by

preventing Top Flight’s performance causing Top Flight damages in the amount of the retainage.

STANDkRD OF REvIEw AND APPLicABLE LAW

Findings of fact in a nonjury trial have the same force and dignity as ajury’s verdict and may

be reviewed for legal and factual sufficiency under the same standards. Sanders v. Total Heat & Aii

Inc., 248 S.W.3d 907, 912 (Tex. App.—-Dallas 2008, no pet). To evaluate the factual sufficiency

of the evidence to support a finding, we consider all the evidence and set aside the finding only if

the evidence supporting it is so weak or so against the overwhelming weight of the evidence that the

finding is clearly wrong and unjust. Id. The appellant should direct its sufficiency attack to specific

findings of fact rather than the judgment as a whole. See Shaw v. County of Dallas, 251 S.W.3d 165,

169 (Tex. App.—Dallas 2008, pet. denied).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanders v. Total Heat & Air, Inc.
248 S.W.3d 907 (Court of Appeals of Texas, 2008)
Cooke County Tax Appraisal District v. Teel
129 S.W.3d 724 (Court of Appeals of Texas, 2004)
Rich v. Olah
274 S.W.3d 878 (Court of Appeals of Texas, 2008)
Tower Contracting Company v. Flores
294 S.W.2d 266 (Court of Appeals of Texas, 1956)
Tower Contracting Company v. Flores
302 S.W.2d 396 (Texas Supreme Court, 1957)
Paragon General Contractors, Inc. v. Larco Construction Inc.
227 S.W.3d 876 (Court of Appeals of Texas, 2007)
Esty v. Beal Bank S.S.B.
298 S.W.3d 280 (Court of Appeals of Texas, 2009)
Shaw v. County of Dallas
251 S.W.3d 165 (Court of Appeals of Texas, 2008)
Kleiner v. Eubank
358 S.W.2d 902 (Court of Appeals of Texas, 1962)
Farris v. Smith Erectors, Inc.
516 S.W.2d 281 (Court of Appeals of Texas, 1974)
National Life & Accident Ins. Co. v. Valdez
3 S.W.2d 514 (Court of Appeals of Texas, 1928)
Carras v. Birge
211 S.W.2d 998 (Court of Appeals of Texas, 1948)
Smith v. Lipscomb
13 Tex. 532 (Texas Supreme Court, 1855)
Waco Tap Railroad v. Shirley
45 Tex. 355 (Texas Supreme Court, 1876)
Porter & McMillan v. Burkett, Murphy & Burns
65 Tex. 383 (Texas Supreme Court, 1886)

Cite This Page — Counsel Stack

Bluebook (online)
Bulldog Ironworks, LLC v. Top Flight Steel, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/bulldog-ironworks-llc-v-top-flight-steel-inc-texapp-2012.