Sanders v. Total Heat & Air, Inc.

248 S.W.3d 907, 2008 Tex. App. LEXIS 2256, 2008 WL 836420
CourtCourt of Appeals of Texas
DecidedMarch 31, 2008
Docket05-05-00524-CV
StatusPublished
Cited by55 cases

This text of 248 S.W.3d 907 (Sanders v. Total Heat & Air, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sanders v. Total Heat & Air, Inc., 248 S.W.3d 907, 2008 Tex. App. LEXIS 2256, 2008 WL 836420 (Tex. Ct. App. 2008).

Opinion

OPINION

Opinion by

Justice MOSELEY.

This case arises out of a construction dispute involving a house. Appellee Total Heat & Air performed work on the home of appellants Wayne and Kathleen Sanders, pursuant to a proposal prepared by Total and signed and accepted by Mike Deaton, who is not a party to the case. The principle issue is whether Deaton signed the proposal in his own right as a general contractor or as an agent acting on behalf of the homeowners. The trial court found Deaton was acting as the homeowners’ agent, meaning that Total’s contract was with the homeowners, not Dea-ton. Because we conclude there is no evidence to support this finding, we reverse the trial court’s judgment in part and render judgment that Total take nothing from the homeowners. Because we conclude the homeowners did not prove their counterclaim against Total as a matter of law, or show the trial court’s failure to find the counterclaim was against the overwhelming weight of the evidence, we affirm the rest of the trial court’s judgment.

Background

Total’s president, Steve Lauten, met with Kathleen Sanders, Deaton, her architect, and others concerning the installation of a sophisticated geothermal heating and air conditioning system (HVAC) in the Sanderses’ home. After these meetings, Total submitted a written proposal for the project. A few days later, Mike Deaton signed the proposal in a blank area underneath the word “Acceptance.” Deaton is the principal of Mike Deaton Custom Remodeling; his signature did not indicate he was signing on anyone else’s behalf.

Total installed the HVAC system over several months and delivered invoices billed to Deaton at his address in Euless. The invoices noted they were for work done at the Sanderses house in Highland Park. Deaton paid the invoices. However, Kathleen Sanders complained the system did not perform as it should have. Several attempts were made to resolve the complaints, to no avail.

After receiving payments of more than $181,000, four of Total’s invoices remained unpaid, amounting to more than $24,000. Total sued the homeowners — not Deaton— for the balance of the unpaid invoices, asserting claims for breach of contract and for quantum meruit. It alleged that Dea-ton, in signing to accept Total’s proposal, acted as the homeowners’ agent.

The homeowners filed a sworn answer denying liability. Among other things, they contended there was no privity between them and Total because Total contracted with Deaton, their general contractor. They also filed a counterclaim for damages resulting from the system’s failure to perform as expected and for expenses incurred in replacing several components in the system.

After a nonjury trial, the trial court rendered judgment in favor of Total on its *912 claims for the unpaid invoices and against the homeowners on their counterclaim. The trial court filed written findings of fact and conclusions of law in support of its judgment. Among other things, the trial court found that at all relevant times Dea-ton acted as the homeowners’ agent.

Issues Presented

The homeowners’ first and second issues challenge the legal and factual sufficiency of the evidence to support the trial court’s judgment on Total’s breach of contract (sworn account) and quantum meruit grounds. 1 They argue the evidence fails to prove privity of contract or that Total rendered valuable services to the homeowners under circumstances reasonably notifying them that Total expected payment directly from them. Their fourth issue challenges the trial court’s take nothing judgment on their counterclaim. Our resolution of these issues disposes of this appeal and we do not address the homeowners’ other issues. See Tex.R.App. P. 47.1.

Standard of Review

Findings of fact in a nonjury trial have the same force and dignity as a jury’s verdict and may be reviewed for legal and factual sufficiency under the same standards. Ortiz v. Jones, 917 S.W.2d 770, 772 (Tex.1996) (per curiam); Catalina v. Blasdel, 881 S.W.2d 295, 297 (Tex.1994); Ashcraft v. Lookadoo, 952 S.W.2d 907, 910 (Tex.App.-Dallas 1997), pet. denied, 977 S.W.2d 562 (Tex.1998) (per curiam). To evaluate the legal sufficiency of the evidence to support a finding, we must “determine whether the proffered evidence as a whole rises to a level that would enable reasonable and fair-minded people to differ in their conclusions.” Transp. Ins. Co. v. Moriel, 879 S.W.2d 10, 25 (Tex.1994); see also St. Joseph Hosp. v. Wolff, 94 S.W.3d 513, 519 (Tex.2002) (plurality op.). We view the evidence in the light favorable to the finding, crediting favorable evidence if a reasonable fact-finder could, and disregarding contrary evidence unless a reasonable fact-finder could not. City of Keller v. Wilson, 168 S.W.3d 802, 827 (Tex.2005).

To evaluate the factual sufficiency of the evidence to support a finding, we consider all the evidence and set aside the finding only if the evidence supporting it is so weak or so against the overwhelming weight of the evidence that the finding is clearly wrong and unjust. See Cain v. Bain, 709 S.W.2d 175, 176 (Tex.1986); Dyson v. Olin Corp., 692 S.W.2d 456, 457 (Tex.1985).

Applicable Law

Privity is an essential element for recovery in any action based on contract; a breach of contract action normally requires privity between the injured party and the party sought to be held liable. See Basic Capital Mgmt., Inc. v. Dynex Commercial, Inc., 2008 WL 509385, at *4, — S.W.3d -, - (Tex.App.-Dallas 2008, no pet. h.); Jensen Const. Co. v. Dallas County, 920 S.W.2d 761, 772 (Tex. App.-Dallas 1996, writ denied), overruled in part by Travis County v. Pelzel & Assocs., Inc., 77 S.W.3d 246, 251 (Tex. 2002). The plaintiff in a breach of contract action has the burden to “prove that the defendant has obligated himself under the contract.” Basic Capital Mgmt., Inc., 2008 WL 509385 at *4,-S.W.3d at-(quoting Miles v. Plumbing Servs. of Houston, Inc., 668 S.W.2d 509, 512 (Tex. App.-Houston [14th Dist.] 1984, writ ref d *913 n.r.e.)). Absent an express agreement otherwise, in construction cases “a subcontractor is not in privity with the owner and must look to the general contractor, while the owner is liable only to the general contractor.” Jensen Const. Co., 920 S.W.2d at 772. Persons performing services or providing materials to a general contractor are paid by the general contractor, not the owner, even if “the work is done under the direction of and in accordance with the plans furnished by the owner.” City of Corpus Christi v. Acme Mech. Contractors, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AZZ, Inc. v. Southeast Texas Industries, Inc.
Tex. App. Ct., 9th Dist. (Beaumont), 2026
KIRKHAM v. TAXACT, INC.
E.D. Pennsylvania, 2024
HOF Partners LLC v. Nautilus Insurance Company
Court of Appeals of Texas, 2023
George H. Clements, III v. HLF Funding
Court of Appeals of Texas, 2021
OBO, Inc. v. Apache Corporation
566 S.W.3d 26 (Court of Appeals of Texas, 2018)
Nine Syllables, LLC v. Gary C. Evans
Court of Appeals of Texas, 2015

Cite This Page — Counsel Stack

Bluebook (online)
248 S.W.3d 907, 2008 Tex. App. LEXIS 2256, 2008 WL 836420, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sanders-v-total-heat-air-inc-texapp-2008.