Shafer Plumbing & Heating, Inc. v. Controlled Air, Inc.

742 S.W.2d 717, 1987 Tex. App. LEXIS 9221, 1987 WL 35006
CourtCourt of Appeals of Texas
DecidedOctober 21, 1987
Docket04-86-00537-CV
StatusPublished
Cited by3 cases

This text of 742 S.W.2d 717 (Shafer Plumbing & Heating, Inc. v. Controlled Air, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shafer Plumbing & Heating, Inc. v. Controlled Air, Inc., 742 S.W.2d 717, 1987 Tex. App. LEXIS 9221, 1987 WL 35006 (Tex. Ct. App. 1987).

Opinion

OPINION

CHAPA, Justice.

This is an appeal from a building construction case. Appellee, subcontractor Controlled Air, Incorporated (Controlled) contracted with appellant subcontractor Shafer Plumbing & Heating, Inc. (Shafer) to construct the air-conditioning duct work on behalf of Shafer for a church project. After considerable work on the project, Controlled submitted a bill to Shafer for $36,000.00. Shafer refused to pay contending that the work was defective, and Controlled abandoned the project due to nonpayment. Controlled sued for breach of contract, open account and quantum meru-it. Shafer counterclaimed for cost of completion and repair above the original contract price. Based upon the jury findings, the trial court entered judgment in favor of Controlled for $36,000.00, $15,000.00 attorney’s fees, interest and costs, and severed the mechanic’s lien claims of Controlled against the owner and contractor. We affirm.

The issues before us are:

1) whether the trial court erred in submitting broad Issues No. 1 and No. 2;

2) whether there is no evidence or insufficient evidence to support the jury answer to Issue No. 2;

3) whether the trial court erred in severing the cause of Controlled against Shafer from the causes against the owner and general contractor, Trinity Church Wind-crest and Contemporary Enterprises, Inc., which involved the mechanic's lien claim; and

4) whether the trial court erred in not granting Shafer a directed verdict as to the mechanic’s lien claim.

The evidence is uncontradicted that:

1) Controlled contracted with Shafer to do the air conditioning duct work on behalf of Shafer on a church project;

2) Controlled performed services and provided material on the project under the contract until they abandoned the project;

3) Shafer refused to pay Controlled anything when Controlled submitted its initial bill for $36,000.00.

Shafer attempted to establish that they were justified in making no payment to Controlled, because of defective work of Controlled, which required repair and replacement. Controlled attempted to establish that their work was in accordance with the contract, and they were justified in abandoning the project due to non-payment.

Shafer contends the trial court erred in submitting broad Issues No. 1 and No. 2. The issues in question as answered by the jury are:

SPECIAL ISSUE NO. 1
Do you find from a preponderance of the evidence that the Plaintiff was justified in abandoning the job because of the failure of the Defendant, SHAFER PLUMBING & HEATING, INC., to pay Plaintiff?
Answer “Yes” or “No.”
Answer: Yes
If you have answered Special Issue No. 1 “Yes,” then answer Special Issue No. 2; otherwise, do not answer Special Issue No. 2.
SPECIAL ISSUE NO. 2
Find from preponderance of the evidence the reasonable value of the labor and materials put into the building by CONTROLLED AIR, INC. in accordance with the contract.in question by and between CONTROLLED AIR, INC. and SHAFER PLUMBING & HEATING, INC.
Answer in dollars and cents, if any.
Answer: $36,000.00

*719 In its brief, Shafer argues that the court should have submitted their requested Special Issue No. 2. However, the record discloses that Shafer only submitted the following written requested issue:

SPECIAL ISSUE NO. 1
Do you find from a preponderance of the evidence that Controlled Air, Inc. performed its work in accordance with the contract in question by and between Controlled Air, Inc. and Shafer Plumbing & Heating, Inc., which justified payment? ANSWER: WE DO_
WE DO NOT_
ACCEPTED_ REFUSED x
has been modified & submitted in No. 2
—RR— JUDGE PRESIDING

TEX.R.CIV.P. 277 provides:

It shall be discretionary with the court whether to submit separate questions with respect to each element of a case or to submit issues broadly. It shall not be objectionable that a question is general or includes a combination of elements or issues.

“This court has repeatedly written that Rule 277 will be applied as written.” Burk Royalty Co. v. Walls, 616 S.W.2d 911, 924 (Tex.1981). Where the court has fairly submitted the controlling issues raised by the pleadings and the evidence, the case shall not be reversed because of the failure to submit other various phases or different shades of the same issue. TEX.R.CIV.P. 279; Holmes v. J.C. Penney Company, 382 S.W.2d 472 (Tex.1964). A special issue not requested in writing is waived and presents nothing for review on appeal. TEX.R. CIV.P. 279; Edwards v. Gifford, 137 Tex. 559, 155 S.W.2d 786 (1941).

In Morgan v. Singley, 560 S.W.2d 746 (Tex.Civ.App.—Texarkana 1977, no writ), Morgan, the subcontractor to Singley, abandoned the project claiming justification due to non-payment of the installment by Singley. The jury found Morgan abandoned the project without justification. The Court of Appeals concluded that:

1. Morgan’s abandoning the project without justification was a breach of the contract;

2. Singley’s refusal to pay was not a breach of the contract by implied finding of the trial court (TEX.R.CIV.P. 279);

3. reciprocal agreements in a contract are presumed dependent and not independent absent an intent to the contrary, and that the breach of one will excuse performance of the other.

Under contracts for personal service, “it has been recognized that if performance is wrongfully prevented by the other party, the injured party may recover either on the contract itself or in quantum meruit, at his election.” Garlitz v. Carrasco, 339 S.W.2d 92, 96 (Tex.Civ.App.—El Paso 1960, writ ref'd n.r.e.). “If the contractor’s failure to complete the building results from the owner’s breach rather than his own, the contractor may elect to rescind the contract and recover for the reasonable value of his services. Kleiner v. Eubank, 358 S.W.2d 902, 905 (Tex.Civ.App.—Austin 1962, writ ref’d n.r.e.). In that event, the contractor is entitled to recover in quantum meruit the reasonable value of the labor and materials he has put into the building in accordance with the contract, whether the result has any value to the owner or not. See Manett, Seastrunk & Buckner v. Terminal Building Corp., 120 Tex.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
742 S.W.2d 717, 1987 Tex. App. LEXIS 9221, 1987 WL 35006, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shafer-plumbing-heating-inc-v-controlled-air-inc-texapp-1987.